China Mobile Hohhot Data Center

Completed Operational

China · 3 projects · Last reported

Summary

China Mobile Hohhot B25/B27 Expansion

HVRAC publishes a whole-article contractor-attributed technical report confirming B25/B27 construction completion acceptance. October 10 is the report/relay date, not the exact acceptance day or authenticated contractor original date. Operation and whole-campus completion remain unverified. evidence

暖通制冷空调在线 (HVRAC) · published 2026-10-10

China Mobile Hohhot Data Center — B02 machine building operations

On 12 October 2026 the Horinger New Area investment promotion services bureau stated that the China Mobile Hohhot Data Center's B02 machine building has been put into operation (B02机楼已投运), its PUE falling from 1.315 to 1.209 with cooling supplied by waste heat from the Jingneng Shengle thermal power plant over a 4.6 km pipeline, and about 560,000 kWh saved so far. The record covers operation of the B02 building as of the publication date only; its original service date, IT capacity and rack count are not stated, the PUE values are the bureau's description (measurement period unknown) and are not recorded as efficiency observations, and the other machine buildings, the liquid-cooled intelligent computing centre and the B25/B27 expansion are not included. evidence

Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区招商服务局) · published 2026-10-12

China Mobile Hohhot Data Center — existing intelligent computing centre operations

On 27 August 2026 the Horinger New Area administrative approval bureau reported that guests on the 23 August industry tour visited the China Mobile intelligent computing centre. The bureau describes it as the world's largest single liquid-cooled operator intelligent computing centre, which has deployed about 20,000 AI accelerator cards (over 89% domestic chips) with up to 6.7 EFLOPS of intelligent compute. The New Area's 10 August 2026 item, attached as context, says the China Mobile Hohhot liquid-cooled intelligent computing centre has 6.7 EFLOPS in total. It also says the centre has run a 10,000-card cluster for 22 days of uninterrupted training, with 86% direct green power and a machine-room PUE as low as 1.15. These present-tense government statements support operation of the existing intelligent computing centre as of 27 August 2026. They name no buildings. The B25/B27 expansion, still under construction then and completed on 10 October 2026, is a separate project and is not included. evidence

Administrative Approval and Government Services Bureau, China (Inner Mongolia) Pilot Free Trade Zone Hohhot Area / Horinger New Area (行政审批和政务服务局) · published 2026-08-27

Location

The interactive map needs JavaScript. Display anchor: 40.53688, 111.81636 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (3)

China Mobile Hohhot B25/B27 Expansion

Completed last observed as of · Firsthand project statement

Contractor disclosure identifies B25/B27, Hohhot Helingeer New District, two data-center buildings and 120MW IT project scope. Supports identity only in this batch; it is older than the freshness window. evidence

China State Construction Engineering Corporation · published 2026-03-24

Source and location review
Status source
HVRAC contractor-attributed completion report: China Mobile Hohhot B25/B27 evidence row
暖通制冷空调在线 (HVRAC) · published 2026-10-10 · News
Locator
Campus locator · Community mapped · community_mapped_named_parent_campus_point evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 17 days before the data update on 2026-10-27

China Mobile Hohhot Data Center — B02 machine building operations

Operational last observed as of · Authoritative status update

Companies
  • Operator: China Mobile (中国移动) (current) evidence
Source and location review
Status source
Horinger New Area news item: 'Compute-power-cooling-carbon collaborative innovation empowers green computing industry upgrading' (算电冷碳协同创新 赋能绿色算力产业升级), 12 October 2026 evidence row
Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区招商服务局) · published 2026-10-12 · Government record
Locator
Campus locator · Community mapped · community_mapped_named_parent_campus_point evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 15 days before the data update on 2026-10-27

China Mobile Hohhot Data Center — existing intelligent computing centre operations

Operational last observed as of · Authoritative status update

Picture-news item dated 15 October 2026 (发布日期) on the Hohhot DRC website, source line 青橙融媒. It says the China Mobile Hohhot Data Center B25 and B27 project in Horinger New Area, just completed by China Construction Third Engineering Bureau (CNY 2.7 billion, 44,500 m2, 120 MW), adds another hard-core piece to the world's largest single operator intelligent computing centre. This ties the operator's intelligent computing centre to the China Mobile Hohhot Data Center campus whose B25/B27 project is already in the Atlas. evidence

Hohhot Development and Reform Commission (reposting 青橙融媒, the Hohhot integrated media centre) · published 2026-10-15

Companies
  • Operator: China Mobile (中国移动) (current) evidence
Source and location review
Status source
Horinger New Area news item: 'Exploring China Cloud Valley — the 2026 green computing and AI industry tour visits the Hohhot area of the free trade zone and Horinger New Area', 27 August 2026 evidence row
Administrative Approval and Government Services Bureau, China (Inner Mongolia) Pilot Free Trade Zone Hohhot Area / Horinger New Area (行政审批和政务服务局) · published 2026-08-27 · Government record
Locator
Campus locator · Community mapped · community_mapped_named_parent_campus_point evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 61 days before the data update on 2026-10-27

Location details
Coordinates
40.53688, 111.81636
Geometry licence
ODbL-1.0
Use scope
Campus locator
Scope class
community_mapped_named_parent_campus_point
Authority
Community mapped
Source entity
Campus
Method
osm_named_campus_vector_polygon_bounding_box_midpoint_verified_inside
Derivation
direct_geometry
Precision scope
Representative point inside the community-mapped named China Mobile Hohhot Data Center parent campus. It does not identify B25/B27 buildings, active work, entrance, survey point, parcel boundary or full current campus boundary.
Horizontal uncertainty
Not reported

No measured horizontal accuracy is supplied for the OSM campus polygon. Offsets between this parent-campus marker and B25/B27 are unknown.

Geometry evidence
7ca96b06

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for China Mobile Hohhot Data Center
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
CSCEC reports award of China Mobile Hohhot B25/B27 EPC project
Archived copy
China State Construction Engineering Corporation
Company disclosure
Site and project identityall-rights-reservedChina State Construction Engineering Corporationd3c345cca963c19d250e5e21dc46df536cc8c71fae765903a280c8dce79ea699
Retained source material; see source provenance
Hohhot DRC picture news (from 青橙融媒): expansion of the world's largest single operator intelligent computing centre completed in Hohhot, 15 October 2026
Archived copy
Hohhot Development and Reform Commission (reposting 青橙融媒, the Hohhot integrated media centre)
News
Site and project identityall-rights-reserved呼和浩特市发展和改革委员会 website; 信息来源:青橙融媒6ef7f91105b2c6d8bfcd644953c3613ff8ff27877546e85a940651e7725a9b14
Retained source material; see source provenance
Horinger New Area news item: 'Compute-power-cooling-carbon collaborative innovation empowers green computing industry upgrading' (算电冷碳协同创新 赋能绿色算力产业升级), 12 October 2026
Archived copy
Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区招商服务局)
Government record
Physical status, Operator claimall-rights-reserved自贸试验区呼和浩特片区、和林格尔新区招商服务局, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn)fff7c269ffa6e437fb72f491224da9e453262e13f192000a663173449f53368f
Retained source material; see source provenance
Horinger New Area news item: 'Exploring China Cloud Valley — the 2026 green computing and AI industry tour visits the Hohhot area of the free trade zone and Horinger New Area', 27 August 2026
Archived copy
Administrative Approval and Government Services Bureau, China (Inner Mongolia) Pilot Free Trade Zone Hohhot Area / Horinger New Area (行政审批和政务服务局)
Government record
Physical status, Operator claimall-rights-reserved自贸试验区呼和浩特片区、和林格尔新区行政审批和政务服务局, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn)3cae96a3a0be296c6aef6cc6c0bdde6414932d129307f88573976a353d590528
Retained source material; see source provenance
Horinger New Area news item: 'From WAIC to Inner Mongolia Horinger New Area: three looks at the compute acceleration in the free trade zone' (从WAIC到内蒙古和林格尔新区:“三看”自贸试验区里的算力“加速度”), 10 August 2026
Archived copy
Inner Mongolia Horinger New Area Party-Mass Service Center (内蒙古和林格尔新区党群服务中心)
Government record
Site and project identity, Physical status, Operator claimall-rights-reserved内蒙古和林格尔新区党群服务中心, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn)6cccbcc8c8de9c82f37e7af13ba3a6ae74ba5c35b18905bc478a8d386d81ff15
Retained source material; see source provenance
HVRAC contractor-attributed completion report: China Mobile Hohhot B25/B27
Archived copy
暖通制冷空调在线 (HVRAC)
News
Physical statusall-rights-reserved暖通制冷空调在线 (HVRAC); institutional source credited by the publisher: 中建三局一公司2e7af680257282a11ee400200ec4f6ceb599915f75f611fec904444040c7e837
Retained source material; see source provenance
Named China Mobile Hohhot Data Center campus, OSM way 699967332
Archived copy
OpenStreetMap contributors
OpenStreetMap
Geometrynot statedODbL-1.0OpenStreetMap contributors01899534bd9f84a892a9b88e2ea15d1d76352e70b79796d779512caec35e272a
Retained source material; see source provenance