Verne says it marked the start of construction of the first 70 MW on its Mäntsälä campus with a foundation-stone ceremony. evidence
Verne · published 2026-06-17
Location
The interactive map needs JavaScript. Display anchor: 60.63530, 25.28619 (Polygon locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Official parcel or permit boundary.
Projects (1)
Verne Mäntsälä Current Campus Development
Under construction last observed as of · Authoritative construction start
Source and location review
- Status source
- Verne begins construction of the first 70 MW on its data center campus in Mäntsälä evidence row
Verne · published 2026-06-17 · Company disclosure - Locator
- Official boundary · Official source · official_cadastral_campus_parcel_boundary evidence
- Source checks
Not reviewed against imagery not_
reviewed_ for_ core_ preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 132 days before the data update on 2026-10-27
Location details
- Coordinates
- 60.63530, 25.28619
- Geometry licence
- all-rights-reserved
- Use scope
- Official boundary
- Scope class
- official_cadastral_campus_parcel_boundary
- Authority
- Official source
- Source entity
- Campus
- Method
- authoritative_site_plan
- Derivation
- direct_geometry
- Precision scope
- Exact municipal cadastral polygon for property 505-407-7-137, inherited through the explicit project-to-campus link; it is the full campus parcel, not a building or the current 70 MW development footprint.
- Horizontal uncertainty
Not reported
official source does not state positional accuracy
- Geometry evidence
- 708cee21
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Mäntsälä official cadastral geometry for property 505-407-7-137 Archived copy | Municipality of Mäntsälä Government record | Geometry | not stated | all-rights-reserved | Municipality of Mäntsälä | e9998583917b7bc03bc5e9593968d72f4ceca6b39aa18f10cc5bc5d503ecf291Retained source material; see source provenance | |
| Verne begins construction of the first 70 MW on its data center campus in Mäntsälä Archived copy | Verne Company disclosure | Physical status | all-rights-reserved | Verne | 2ec376832ffe1fb1c1313375cebc197834b657cec18beec6df37dc2152795ebcRetained source material; see source provenance |
Cite this site
Kyars, K. (2026). Verne Mäntsälä Data Center Campus [site vcc-site-00808116377785b5c125]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-00808116377785b5c125/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction