Sify Rabale data center campus (Mumbai 03), Navi Mumbai

Partially operational

India · 1 project · Last reported

Summary

Sify Infinit Spaces' Rabale campus in the TTC Industrial Area, Navi Mumbai, one of its largest, is designed for 12 towers, of which five are operating. Sify's campus page gives 96.94 MW of IT power for them, the figure its October 2025 prospectus reports as built capacity at mid-2025. The hyperscale and AI-ready Tower 5, designed for 43.2 MW, came into service in the 2023-24 financial year and had 30.24 MW installed by June 2025. Sify's website gives more than 377 MW of IT power for the full campus. Towers 11 and 12 (38.88 MW together) were under construction in October 2025 at an estimated INR 11.3 billion, targeted for the year to March 2028.

Source record as of 2026-10-09 · Details and sources

Location

The interactive map needs JavaScript. Display anchor: 19.14417, 73.00861 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Town or locality reference only; the facility position is not established.

Projects (1)

Sify Rabale data center campus (Mumbai 03), Navi Mumbai

Partially operational last observed as of · Reported status

Location: Rabale, Navi Mumbai (TTC Industrial Area), Thane district, Maharashtra, IN. Sify gives the address as Plot R-847, TTC Industrial Area, Rabale, Navi Mumbai, and the prospectus places towers 11 and 12 on Plot R-978 in the same industrial area. The point is the Rabale coordinate from its Wikipedia article (which also gives Thane district), so it marks the neighbourhood rather than the plots. Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India); Wikipedia

Use: Colocation, Cloud, Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacitymore than 377 MWPlanned · Campus · It load2026-10-09Design capacity across 12 towers from Sify's undated website, read on the access date.Sify Technologies
Power capacity96.94 MWOperational · Phase · It load · Towers 1-52026-10-09Sify's undated campus page, read on the access date, gives 96.94 MW of IT power with five of 12 towers fully operational. The prospectus gives the same figure as the built capacity of towers 1-5 at 30 June 2025, when Tower 5 had only 30.24 MW of its 43.2 MW installed, so commissioned capacity at that date was lower.Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Power capacity43.2 MWPlanned · Phase · It load · Tower 5 (design / built capacity)2025-06-30Sify's campus page says Tower 5 is designed for 43.2 MW of IT power; the prospectus gives the same figure as its built capacity. The prospectus defines built capacity as the maximum IT load a facility is engineered to support on its present design, and installed capacity as the part that is equipped, powered and commissioned.Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Power capacity30.24 MWOperational · Phase · It load · Tower 5 (installed capacity)2025-06-30Installed IT capacity of Tower 5 at 30 June 2025, up from 6.48 MW at 31 March 2024.Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Power capacity38.88 MWUnder construction · Phase · It load · Towers 11 and 122025-10-1619.44 MW in each tower, with operations targeted by the financial year ending March 2028.Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Investment11,276,930,000 INRAnnounced · Phase · Towers 11 and 122025-10-16Estimated cost of towers 11 and 12 excluding land, certified by an independent chartered engineer; INR 8.6 billion was to come from IPO proceeds and the rest from borrowing.Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Buildings12 countPlanned · Campus2025-10-16Sify Technologies; Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Buildings5 countOperational · Campus2025-06-30Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)

Companies and organizations

NameRoleNotesSources
Sify Infinit Spaces LimitedDeveloperData center subsidiary of Sify Technologies, which is one of its promoters.Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Sify Infinit Spaces LimitedOperatorSify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)

Timeline

DateEventActual or plannedNotesSources
2025-10-16OtherActualProspectus reports towers 11 and 12 under construction, to be part-funded by the planned IPO of Sify Infinit Spaces.Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
2026OtherPlannedSify's campus page says towers 6, 7, 11 and 12 are slated to be operational by 2026; the October 2025 prospectus targets towers 11 and 12 for the year ending March 2028.Sify Technologies

Power supply

TypeDescriptionSources
GridTowers 1 to 3 are served by an on-site 110 kV substation and the later towers by an on-site 220 kV GIS substation (towers 4 and 5 in the prospectus, towers 4 to 6 on Sify's campus page).Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
SolarRenewable power from solar and wind, bought through power purchase agreements, covers up to 70% of campus operations; Sify's campus page cites 99 MW of green power.Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
WindWind generation is part of the renewable supply bought through power purchase agreements.Sify Technologies; Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)

The partially operational status and the 2026 tower schedule come from Sify's undated campus page (s2), read on 2026-10-09; it says towers 6, 7, 11 and 12 are slated for 2026 and towers 8 to 10 are in planning, while the October 2025 prospectus targets towers 11 and 12 for the year ending March 2028. The prospectus shows no Tower 5 capacity in the year to March 2023 and 43.2 MW built by March 2024. Towers 11 and 12 stand on Plot R-978, sub-leased from Gargantuan Industrial Space Solutions, which is to deliver the buildings built-to-suit. Rabale coordinates and the district come from Wikipedia (s4), used only for the location.

Sources for these details
Companies
  • Developer: Sify Infinit Spaces Limited (unknown scope) evidence
  • Operator: Sify Infinit Spaces Limited (unknown scope) evidence
  • Operator: Sify Infinit Spaces Limited (unknown scope) evidence
Source and location review
Status source
Mumbai data center evidence row
Sify Technologies · publication date not stated · Company disclosure
Locator
Locality reference only · Compiled location reference · locality evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 18 days before the data update on 2026-10-27

Location details
Coordinates
19.14417, 73.00861
Geometry licence
source-terms-not-recorded
Use scope
Locality reference only
Scope class
locality
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
Sify gives the address as Plot R-847, TTC Industrial Area, Rabale, Navi Mumbai, and the prospectus places towers 11 and 12 on Plot R-978 in the same industrial area. The point is the Rabale coordinate from its Wikipedia article (which also gives Thane district), so it marks the neighbourhood rather than the plots.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
3ca04bf3

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Sify Rabale data center campus (Mumbai 03), Navi Mumbai
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Data centre
Archived copy
Sify Technologies
Company disclosure
Imported: Record, Metric: Buildings, Metric: Power Capacitynot statedsource-terms-not-recordedSify Technologies1fc8f94386a8decc71f800a277fa353788ff24757b5b2415641f2a15af8bf385
Factual source record; not the publisher page
Mumbai data center
Archived copy
Sify Technologies
Company disclosure
Imported: Geometry, Imported: Record, Imported: Status, Metric: Buildings, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Power Source: Solar, Power Source: Wind, Operator claimnot statedsource-terms-not-recordedSify Technologiesdd5f16d9d02aa25cabc1a100d539005aa49a1b87c735733276288042313ebc07
Factual source record; not the publisher page
Rabale
Archived copy
Wikipedia
Other
Imported: Geometry, Imported: Recordnot statedsource-terms-not-recordedWikipediadbac7b52e9fd5a60d83ed881713d0456768e9b1af445c41d7dece6952bbede2a
Factual source record; not the publisher page
Sify Infinit Spaces Limited: Draft Red Herring Prospectus (filing version)
Archived copy
Sify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)
Regulatory filing
Imported: Geometry, Imported: Record, Imported: Status, Metric: Buildings, Metric: Investment, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Power Source: Solar, Power Source: Wind, Role: Developer, Operator claimsource-terms-not-recordedSify Infinit Spaces Limited (filed with SEBI; hosted by National Stock Exchange of India)0864ac5be91d6f33978ee8bc2242f8773965f1d24d24eda91360b5d62048b1dc
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). Sify Rabale data center campus (Mumbai 03), Navi Mumbai [site vcc-site-2088ce1cae4288c3f3a1]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-2088ce1cae4288c3f3a1/