Ascenty reports construction of Vinhedo 3 and separately reports a 20 MW increase for its sixth Sao Paulo data center; both values remain untyped metadata. evidence

Ascenty · published 2026-05-28T12:05:17+00:00

Location

The interactive map needs JavaScript. Display anchor: -23.07022, -47.01299 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Ascenty Vinhedo 3

Under construction last observed as of · Authoritative status update

Source and location review
Status source
Ascenty Secures 150 Megawatts of New AI Contracts with Leading Global Hyperscalers evidence row
Ascenty · published 2026-05-28T12:05:17+00:00 · Company disclosure
Locator
Campus locator · Official source · named_constituent_facility_point evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 152 days before the data update on 2026-10-27

Location details
Coordinates
-23.07022, -47.01299
Geometry licence
all-rights-reserved-fact-extraction-only
Use scope
Campus locator
Scope class
named_constituent_facility_point
Authority
Official source
Source entity
Campus
Method
first_party_published_coordinate
Derivation
coordinates_to_point
Precision scope
Exact publisher coordinate for VIN02, used only as a broad Vinhedo campus locator for Vinhedo 3; not Vinhedo 3 parcel, building, or work footprint.
Horizontal uncertainty
Not reported

The factsheet does not state coordinate accuracy.

Geometry evidence
2184bacc

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Ascenty Vinhedo Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Ascenty Campus Vinhedo factsheet
Archived copy
Ascenty
Company disclosure
Geometrynot statedall-rights-reserved-fact-extraction-onlyAscentyc30210635d897e4545605e8f035a1678a7e0449d950f206fd4f27cb782c66e3a
Retained source material; see source provenance
Ascenty Secures 150 Megawatts of New AI Contracts with Leading Global Hyperscalers
Archived copy
Ascenty
Company disclosure
Source location context, Physical statusall-rights-reservedAscenty966870f4e9dc712246aaa91720f200ebb422da97c408f2ddedb8b9b1daa0e132
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Ascenty Vinhedo Campus [site vcc-site-29c7aa69cf49aaa11516]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-29c7aa69cf49aaa11516/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction