Niger National Data Center PK5
Under construction
Niger · 1 project · Last reported
Summary
The Niger government says civil-engineering work for the National Data Center was finalized and technical equipment needed for operationalization was being installed progressively. evidence
Gouvernement de la République du Niger · published 2026-06-18
Location
The interactive map needs JavaScript. Display anchor: 13.55968, 2.11351 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Project locator; building footprints are not mapped.
Projects (1)
Niger National Data Center PK5 Current Build
Under construction last observed as of · Authoritative status update
Source and location review
- Status source
- Communication et numérique : le Niger ambitionne de devenir un hub régional des télécommunications evidence row
Gouvernement de la République du Niger · published 2026-06-18 · Government record - Locator
- Project locator · Official source · official_environmental_assessment_project_point evidence
- Source checks
Not reviewed against imagery not_
reviewed_ for_ core_ preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 131 days before the data update on 2026-10-27
Location details
- Coordinates
- 13.55968, 2.11351
- Geometry licence
- all-rights-reserved
- Use scope
- Project locator
- Scope class
- official_environmental_assessment_project_point
- Authority
- Official source
- Source entity
- Project
- Method
- bnee_eies_project_area_coordinate
- Derivation
- official_dms_coordinate_to_point
- Precision scope
- The point is the EIES-reported coordinate of the project area at the selected Niger Telecom PK5 site. It is not a surveyed entrance, parcel centroid, building footprint, campus boundary, or current-work extent.
- Horizontal uncertainty
Not reported
The EIES reports DMS precision but no survey method, datum-specific accuracy statement, or bounded horizontal uncertainty.
- Geometry evidence
- e8b0b9c1
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Communication et numérique : le Niger ambitionne de devenir un hub régional des télécommunications Archived copy | Gouvernement de la République du Niger Government record | Source location context, Physical status | all-rights-reserved | Gouvernement de la République du Niger | 96810113fba7a58ddffe4d8f1ce6fec016c7a58478ebd9db59594eb992e743bdRetained source material; see source provenance | ||
| Final environmental and social impact assessment - national data center at PK5, Niamey II Archived copy | Bureau National d'Evaluation Environnementale, Republic of Niger Government record | Geometry identity context, Geometry | all-rights-reserved | Republic of Niger, Ministry of Posts and New Information Technologies / BNEE | f9fc8e51e9cabc4e6bfd30f9b09f678a2a68fb92a61b1f62973c41210f108fb1Retained source material; see source provenance |
Cite this site
Kyars, K. (2026). Niger National Data Center PK5 [site vcc-site-4586aa46386f0cb18dc7]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-4586aa46386f0cb18dc7/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction