Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park
Under construction
China · 1 project · Last reported
Summary
On 20 October 2026 the Shapotou District Branch of the Zhongwei Market Supervision Administration reported that its Xuanhe office, serving workers on the key data-centre projects under construction in Xuanhe (数据中心重点在建项目), had contacted the China Mobile, CIDC and Zhonglian (中联) project leaders and guided the building of construction-site canteens, and would keep supervising canteens at projects under construction. In Xuanhe Town the Zhonglian project is the Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park, whose June 2026 substation EIA already described the park as formally under construction (site enclosed and levelled, a camp of over 11,000 m2 built). The record names no zone or building: it supports construction of the park development as a whole, not the stage of any building, and no completion or operation is established. evidence
Shapotou District Branch, Zhongwei Market Supervision Administration · published 2026-10-20
Location
The interactive map needs JavaScript. Display anchor: 37.36835, 105.49051 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Campus reference; individual project footprints are not mapped.
Projects (1)
Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park — Park Development (A-Zone and B-Zone, Data-Centre Buildings 1#–8#)
Under construction last observed as of · Authoritative status update
Acceptance notice (index 640501012/2026-02269) listing one project accepted on 9 June 2026: 中联零碳智算(宣和)产业园A区项目330千伏变电站工程, location Wangyuan Village, Xuanhe Town, builder Ningxia Western Intelligent Computing Big Data Technology Co., Ltd., with the report form attached (P020260609636232435863.pdf). The separate Zhonglian Cloud Base park substation of the same day is located in the Zhongwei Industrial Park, not Xuanhe. evidence
Zhongwei Ecology and Environment Bureau · published 2026-06-09
Post-issuance publicity (index 640501011/2025-00339) of construction-project planning permit 6405022025GG0054519 issued 2 July 2025 to Ningxia Western Intelligent Computing Big Data Technology Co., Ltd. for the A-zone data-centre buildings 1#-4# and the 330 kV substation at Xuanhe Town (west to Sandang Highway; east, south and north open land): 200,506.81 m2 GFA (195,076.87 m2 above ground). Validity marked effective. evidence
Zhongwei Natural Resources Bureau · published 2025-07-02
Land-use planning permit 6405022025YG0026516 issued 1 July 2025 to Ningxia Western Intelligent Computing Big Data Technology Co., Ltd. (land approval 卫政土批字〔2025〕17号): 169,536 m2 of industrial land for cloud computing and big-data centres at Xuanhe Town, west to Sandang Highway; four data-centre buildings with supporting electromechanical facilities, each with 4,928 16-kW and 16 4-kW racks. evidence
Zhongwei Natural Resources Bureau · published 2025-07-01
Land-use planning permit 6405022025YG0027526 issued 19 June 2025 to Ningxia Zhongshu Western Intelligent Computing Data Technology Co., Ltd. (宁夏中数西部智算数据科技有限公司) under the same land approval: 169,359 m2 of industrial land for cloud computing and big-data centres at Xuanhe Town, west to Sandang Highway; four data-centre buildings. No B-zone construction-project planning permit was found in the Zhongwei NRB permit lists back to April 2025. evidence
Zhongwei Natural Resources Bureau · published 2025-06-26
Pre-approval publicity (index 640501011/2026-00700) of a local adjustment to the A-zone planning scheme, with its board image (W020260921534581325198.png, captured separately). evidence
Zhongwei Natural Resources Bureau · published 2026-09-17
Board (7,680 x 4,320 px; builder Ningxia Western Intelligent Computing Big Data Technology Co., Ltd.; designer 匡邑规划建筑设计研究院(上海)有限公司) for the 17-24 September 2026 publicity. It adjusts the height and floor area of data-centre buildings 3# and 4# and the diesel-generator buildings, and reproduces the originally approved 1:1000 general plans of the A-zone (data-centre buildings 1#-4#) and B-zone (5#-8#) as one park east of Sandang Highway, with the 1# 330 kV substation on the A-zone west side beside a 137 m access strip to the highway and a north-west jog of 62.01 m by 77.75 m. Used for the locator check (geometry facts file). evidence
Zhongwei Natural Resources Bureau · published 2026-09-21
Government-site news item (source 中卫市新闻传媒中心) stating that in Xuanhe Town China Mobile, Zhonglian Zero-Carbon Intelligent Computing (中联零碳智算) and CIDC (中金数据) hold national compute-infrastructure approvals, with three core projects totalling 82.87 billion yuan: the China Mobile Data Center Xuanhe Park (中国移动数据中心宣和园区), the Zhonglian Zero-Carbon Intelligent Computing Industrial Base (中联零碳智算产业基地) and the CIDC Green Intelligent Computing Industrial Base (中金数据绿色智算产业基地); Jinko Power (晶科科技), Chindata, China Unicom and GDS (万国数据) are described only as intending to locate there. evidence
Zhongwei News Media Centre (Shapotou District People's Government website) · published 2026-07-24
Imagery used to check the WGS84 reading of the Zhonglian substation point: the point lies at the west edge of an about 480 m wide levelled area east of Sandang Highway, with blue-roofed site buildings east of it; the CIDC point lies on land still unbuilt in the 2025 mosaic. See the geometry facts file. Not a lifecycle observation. evidence
EOX IT Services GmbH · publication date not stated
Official Xuanhe detailed plan (20 August 2026). Its page-4 land-use map, registered to imagery in sources/research-countries-2026-10-22-cn-ningxia-gansu-p1-gds-xuanhe-a-zone-geometry-facts.json, is used here only to check the two EIA substation points against the Zhonglian block (Sandang Highway auxiliary road, Weisi, Jingwu and Weiwu Roads) and the CIDC block (auxiliary road, Weier and Jingsi Roads). Rehashed on 23 October 2026 (sha256 unchanged). evidence
Zhongwei Data Bureau · published 2026-08-20
- Companies
- Owner: Ningxia Western Intelligent Computing Big Data Technology Co., Ltd. (宁夏西部智算大数据科技有限公司) (current) evidence
Source and location review
- Status source
- Shapotou District department news: Xuanhe market-supervision office special food-safety campaign at canteens of projects under construction (20 October 2026) evidence row
Shapotou District Branch, Zhongwei Market Supervision Administration · published 2026-10-20 · Government record - Locator
- Campus locator · Official source · official_eia_on_campus_substation_locator evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 7 days before the data update on 2026-10-27
Location details
- Coordinates
- 37.36835, 105.49051
- Geometry licence
- all-rights-reserved
- Use scope
- Campus locator
- Scope class
- official_eia_on_campus_substation_locator
- Authority
- Official source
- Source entity
- Campus
- Method
- official_eia_geographic_dms_point_transcription
- Derivation
- direct_geometry
- Precision scope
- EIA centre point of the park's own 330 kV substation, which the report places on reserved land on the west side of the Zhonglian Xuanhe compute-centre industrial park, beside the No.2 data-centre building. Locates the park through on-campus support infrastructure; not a data-centre building footprint, parcel centroid, entrance or construction extent. The park (A-zone and B-zone, about 34 ha) extends up to about 650 m east and south of the point.
- Horizontal uncertainty
Not reported
No datum or positional accuracy is stated. The WGS84 reading is supported by agreement within about 50 m with the official site board placed on the registered detailed plan (itself about 5 m RMS image-to-image against imagery of unstated accuracy) and by the levelled ground in the 2025 Sentinel-2 mosaic. Estimated within roughly 100 m of the planned substation centre; the point may fall on the park's west edge or access strip. Decimal places are transcription precision, not accuracy.
- Geometry evidence
- d3f41e9a
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Environmental impact report form: Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park A-zone 330 kV substation (Zhongwei EEB acceptance notice, 9 June 2026) Archived copy | Zhongwei Ecology and Environment Bureau Government record | Geometry, Owner claim | all-rights-reserved | Zhongwei Ecology and Environment Bureau | 86626d44fe095170acab4a55e8a1b6971b4c7a8077a1269011f5668ff35f0df5Retained source material; see source provenance | ||
| EOX Sentinel-2 cloudless 2025 mosaic: Zhongwei data-centre cluster Xuanhe area (EPSG:4326 WMS extract, 105.47-105.53E, 37.35-37.39N) Archived copy | EOX IT Services GmbH Other | Site and project identity | not stated | CC-BY-NC-SA-4.0 | Sentinel-2 cloudless - https://s2maps.eu by EOX IT Services GmbH (Contains modified Copernicus Sentinel data 2025) | 278d5fb520a5e616f115beb946c82d5554d30b13dce04fe7c408571b4ee24946Retained source material; see source provenance | |
| Plan board: Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park A-zone local optimisation scheme, pre-approval publicity (17-24 September 2026) Archived copy | Zhongwei Natural Resources Bureau Government record | Site and project identity | all-rights-reserved | Zhongwei Natural Resources Bureau | 15042a155b4e1a5522e373fe4fcd0a616f3e8da1e18272c04012f19cc2f0db27Retained source material; see source provenance | ||
| Shapotou District department news: Xuanhe market-supervision office special food-safety campaign at canteens of projects under construction (20 October 2026) Archived copy | Shapotou District Branch, Zhongwei Market Supervision Administration Government record | Physical status | all-rights-reserved | 中卫市市场监督管理局沙坡头区分局 (Shapotou District Branch, Zhongwei Market Supervision Administration), via the Shapotou District People's Government website | c533bdc34da6e598592d01d135689f0c4264a23bdbef0edd83d1e1162b7de785Retained source material; see source provenance | ||
| Shapotou District government news: Xuanhe Town supports the high-quality development of the digital information industry (24 July 2026) Archived copy | Zhongwei News Media Centre (Shapotou District People's Government website) News | Site and project identity | all-rights-reserved | 中卫市新闻传媒中心 (Zhongwei News Media Centre), via the Shapotou District People's Government website | 27464206a4ffeab738f36da60ba038c708bfea3e36a60a86beb42bc54bfbde0fRetained source material; see source provenance | ||
| Zhongwei Ecology and Environment Bureau: notice of EIA documents accepted on 9 June 2026 (Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park A-zone 330 kV substation) Archived copy | Zhongwei Ecology and Environment Bureau Government record | Site and project identity | all-rights-reserved | Zhongwei Ecology and Environment Bureau | 4b31c65f3f61310582fa9c27921052a4b37e28e2a6fadf395db1c7081ef24226Retained source material; see source provenance | ||
| Zhongwei Natural Resources Bureau post-issuance notice: construction-project planning permit, Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park A-zone (data-centre buildings 1#-4# and 330 kV substation) Archived copy | Zhongwei Natural Resources Bureau Government record | Site and project identity | all-rights-reserved | Zhongwei Natural Resources Bureau | d1c4783624a9a57f5dc91cb5f42a1925f5845cacf6745f087b481f50194d7bffRetained source material; see source provenance | ||
| Zhongwei Natural Resources Bureau post-issuance notice: land-use planning permit, Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park A-zone Archived copy | Zhongwei Natural Resources Bureau Government record | Site and project identity | all-rights-reserved | Zhongwei Natural Resources Bureau | e43aa16b36320c0ecebe532ed2bd6a8a634b5840ec55dcf99694f0bf7457db62Retained source material; see source provenance | ||
| Zhongwei Natural Resources Bureau post-issuance notice: land-use planning permit, Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park B-zone Archived copy | Zhongwei Natural Resources Bureau Government record | Site and project identity | all-rights-reserved | Zhongwei Natural Resources Bureau | 11446926bd65551cbe77febdd3eb03dcdc799fa526367bd09e393e7020f1e700Retained source material; see source provenance | ||
| Zhongwei Natural Resources Bureau pre-approval notice: local optimisation of the Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park A-zone scheme (17 September 2026) Archived copy | Zhongwei Natural Resources Bureau Government record | Site and project identity | all-rights-reserved | Zhongwei Natural Resources Bureau | 00e1227f0f86e15d1658601ad7df15f7a2b75d0da6a85fb901ed150734a01150Retained source material; see source provenance | ||
| 中卫数据中心集群宣和片区详细规划(公布稿)— Zhongwei Data Center Cluster Xuanhe Area Detailed Plan (published version) Archived copy | Zhongwei Data Bureau Government record | Site and project identity, Geometry | all-rights-reserved | Zhongwei Data Bureau (中卫市数据局) | 7d0c7a664373bf609305b1862393ea7a7e11c3640949cb87cdddd00e04134991Retained source material; see source provenance |
Cite this site
Kyars, K. (2026). Zhonglian Zero-Carbon Intelligent Computing (Xuanhe) Industrial Park [site vcc-site-59f5181a670956fe610c]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-59f5181a670956fe610c/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction