NTT DATA Group and its data center arm NTT Global Data Centers announced in April 2026 that they had begun developing Tokyo TKY12, a six-building hyperscale campus in Shiroi City, Chiba Prefecture, in the Inzai-Shiroi data center cluster east of Tokyo. It is planned for about 200 MW of total IT capacity on a flat site about 20 m above sea level, near NTT's 50 MW TKY11 facility, which is due to open in April 2027. The first building is to enter service in 2030 or later, once the utility supplies power. No investment figure or construction start date has been disclosed.

Source record as of 2026-04-22 · Details and sources

Location

The interactive map needs JavaScript. Display anchor: 35.79147, 140.05631 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Town or locality reference only; the facility position is not established.

Projects (1)

NTT Global Data Centers Tokyo TKY12 campus, Shiroi

Announced last observed as of · Reported status

Location: Shiroi, Chiba Prefecture, JP. NTT names Shiroi City, Chiba Prefecture, without an address. The point is the Shiroi city coordinate from its Wikipedia article, so it marks the city rather than the site. NTT DATA Group / NTT Global Data Centers; W.Media; Wikipedia

Use: Cloud, Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacityabout 200 MWPlanned · Campus · It load2026-04-17Total IT capacity of TKY12. NTT's headline figure of about 250 MW for the Inzai-Shiroi development matches TKY12 plus the nearby 50 MW TKY11, a separate facility, though the release does not break it down.NTT DATA Group / NTT Global Data Centers; W.Media
Buildings6 countPlanned · Campus2026-04-17NTT DATA Group / NTT Global Data Centers; W.Media

Companies and organizations

NameRoleNotesSources
NTT Global Data Centers CorporationDeveloperData center subsidiary of NTT DATA Group, which co-issued the announcement.NTT DATA Group / NTT Global Data Centers; W.Media

Timeline

DateEventActual or plannedNotesSources
2026-04-17AnnouncedActualNTT DATA and NTT GDC announced the start of development.NTT DATA Group / NTT Global Data Centers; W.Media
2030First operationalPlannedFirst building to start service in 2030 or later, after power is received from the utility.NTT DATA Group / NTT Global Data Centers; W.Media

Power supply

TypeDescriptionSources
GridService at the first building depends on power being supplied by the local utility, which is not named.NTT DATA Group / NTT Global Data Centers

The status is 'announced' because NTT described the start of development but gave no construction start date. TKY11, the nearby 50 MW facility due in April 2027, is not part of this record. Shiroi coordinates come from Wikipedia (s3), used only for the map point.

Sources for these details
Companies
  • Developer: NTT Global Data Centers Corporation (unknown scope) evidence
  • Developer: NTT Global Data Centers Corporation (unknown scope) evidence
Source and location review
Status source
国内最大級、千葉県印西・白井エリアで約250メガワット(MW)のデータセンターキャンパス開発を始動 evidence row
NTT DATA Group / NTT Global Data Centers · published 2026-04-17 · Company disclosure
Locator
Locality reference only · Compiled location reference · locality evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 188 days before the data update on 2026-10-27

Location details
Coordinates
35.79147, 140.05631
Geometry licence
source-terms-not-recorded
Use scope
Locality reference only
Scope class
locality
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
NTT names Shiroi City, Chiba Prefecture, without an address. The point is the Shiroi city coordinate from its Wikipedia article, so it marks the city rather than the site.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
23498602

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for NTT Global Data Centers Tokyo TKY12 campus, Shiroi
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
NTT Data plans a 200 MW data center campus in Japan
Archived copy
W.Media
Trade publication
Imported: Geometry, Imported: Record, Imported: Status, Metric: Buildings, Metric: Power Capacity, Milestone: Announced, Milestone: First Operational, Role: Developersource-terms-not-recordedW.Media0648ffc8941fedb51bd67c95ecb43e0371b215f79d6b7cda5a9f7d8d550d68c0
Factual source record; not the publisher page
Shiroi
Archived copy
Wikipedia
Other
Imported: Geometry, Imported: Recordnot statedsource-terms-not-recordedWikipedia9a7643725a732caa8e211dc37113e802d707a9588a103448aefbb81c9bbe75e3
Factual source record; not the publisher page
国内最大級、千葉県印西・白井エリアで約250メガワット(MW)のデータセンターキャンパス開発を始動
Archived copy
NTT DATA Group / NTT Global Data Centers
Company disclosure
Imported: Geometry, Imported: Record, Imported: Status, Metric: Buildings, Metric: Power Capacity, Milestone: Announced, Milestone: First Operational, Power Source: Grid, Role: Developersource-terms-not-recordedNTT DATA Group / NTT Global Data Centersf8c174680a9236dfed387b898946d8dbb2320a57604c08ccef4707c51b1c3f7f
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). NTT Global Data Centers Tokyo TKY12 campus, Shiroi [site vcc-site-627bed0b413c9b712d70]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-627bed0b413c9b712d70/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction