Greenergy Hüüru Data Center Campus

Under construction

Estonia · 1 project · Last reported

Summary

On 28 September 2026 MCF Group Estonia, operator of Greenergy Data Centers in Hüüru, stated that the first part of the data center designed for artificial intelligence is currently being built out, with Nebius as its tenant, and that this first phase of the AI factory will be completed by the end of 2026, raising the facility's IT load to about 22 MW. Under construction as of 28 September 2026. Completion, commissioning and operation of the expansion are not asserted; the year-end completion, the 22 MW IT load and the 200 MW grid application are forecasts or applications. evidence

MCF Group Estonia OÜ (Greenergy Data Centers) · published 2026-09-28

Location

The interactive map needs JavaScript. Display anchor: 59.38610, 24.56196 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Greenergy Hüüru Data-Hall Expansion

Under construction last observed as of · Authoritative status update

Source and location review
Status source
Greenergy Data Centers (MCF Group Estonia): Estonian investors raise their stake in the Hüüru data center to 42.5 percent (28 September 2026) evidence row
MCF Group Estonia OÜ (Greenergy Data Centers) · published 2026-09-28 · Company disclosure
Locator
Campus locator · Community source · community_named_enclosure_representative_point evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 29 days before the data update on 2026-10-27

Location details
Coordinates
59.38610, 24.56196
Geometry licence
ODbL-1.0, no-open-license-asserted
Use scope
Campus locator
Scope class
community_named_enclosure_representative_point
Authority
Community source
Source entity
Campus
Method
OSM_way_1043819046_full_ordered_nodes_WGS84_Shapely_representative_point
Derivation
representative_point_of_exact_named_OSM_enclosure
Precision scope
Interior representative point of exact named community-mapped Greenergy enclosure. Not a surveyed or official boundary, building footprint, entrance, work extent or inferred office locator. The underlying enclosure's name, address, phone and website match the operator data-center page.
Horizontal uncertainty
Not reported

No source quantifies positional accuracy. Seven-decimal source coordinates and extra derived decimals are not survey accuracy.

Geometry evidence
20f56b6a 77ce34d0 892c8445

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Greenergy Hüüru Data Center Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Caverion Finnish parallel release retains narrower employment wording
Archived copy
Caverion
Company disclosure
Geometry identity context, Site distinctness contextno-open-license-assertedCaverion0f7d92aa916827989a61811d99abd7f6a02dd7c57c9d1a50dc527ade34d04790
Retained source material; see source provenance
Caverion July 31 Greenergy data-hall expansion and on-site workforce
Archived copy
Caverion
Company disclosure
Geometry identity context, Site distinctness contextno-open-license-assertedCaverionbae47a62882058d6b713f106c0a06069c8c3bcee80143dead533431bab8a03fc
Retained source material; see source provenance
Estonian investment agency distinguishes development inside Greenergy's existing building
Archived copy
Estonian Business and Innovation Agency / Invest Estonia
Government record
Geometry identity context, Site distinctness contextnot statedno-open-license-assertedEstonian Business and Innovation Agency / Invest Estoniab315e919580a33908f181a6b97c47d7b65d085a08d23583162df2234ff98b174
Retained source material; see source provenance
Greenergy and Tensor August 12 release keeps the first expansion deployment in the future
Archived copy
Greenergy Data Centers and Tensor Estate
Company disclosure
Site distinctness contextno-open-license-assertedGreenergy Data Centers and Tensor Estateb39e213f3a9d2ce6003ba5390cef9e515f46732e2ace425e5cc600f888fb2a9f
Retained source material; see source provenance
Greenergy Data Centers (MCF Group Estonia): Estonian investors raise their stake in the Hüüru data center to 42.5 percent (28 September 2026)
Archived copy
MCF Group Estonia OÜ (Greenergy Data Centers)
Company disclosure
Physical statusno-open-license-assertedMCF Group Estonia OÜ / Greenergy Data Centersb19295f0f470ab6a9655521a28ce184e5b1b682cd5b8fdde467202aaf48fad69
Retained source material; see source provenance
Greenergy operator contact page explicitly identifies its data center
Archived copy
Greenergy Data Centers
Company disclosure
Geometry identity context, Site distinctness contextnot statedno-open-license-assertedGreenergy Data Centers7065309ff1464e9d0784e671e35c0fe8da85828121b1ec39e7b11993fdcc47b2
Retained source material; see source provenance
MCF Group Estonia July 30 release states preparatory construction has begun
Archived copy
MCF Group Estonia, hosted by shareholder Tensor Estate
Company disclosure
Geometry identity context, Site distinctness context, Physical statusno-open-license-assertedMCF Group Estonia / Tensor Estate94f829a7ee267a6eac7c4449f5fcc0e2ff2c41730c36333b9ff4253b3a164495
Retained source material; see source provenance
OSM copyright and ODbL attribution policy
Archived copy
OpenStreetMap Foundation
OpenStreetMap
Site distinctness context, Geometrynot statedno-open-license-assertedOpenStreetMap Foundation97c8da4341cb2ae34e913cb3c483c16d028996d3c0f65db957f0a46576a0c20d
Retained source material; see source provenance
OSM exact named Greenergy enclosure with address and operator website
Archived copy
OpenStreetMap contributors
OpenStreetMap
Site distinctness context, Geometrynot statedODbL-1.0OpenStreetMap contributors0c6c8eaff6ac2a3294625d314fd2067622789b2c1b61fb35452aa603a98ebc64
Retained source material; see source provenance
OSM node documentation defines latitude and longitude in WGS84
Archived copy
OpenStreetMap contributors
OpenStreetMap
Site distinctness context, Geometrynot statedno-open-license-assertedOpenStreetMap contributors990fd845fdfc40181881afbe628e14e486597549cd496175061de6366013c89b
Retained source material; see source provenance