EdgeConneX Greater Osaka campus (Kagoya Tatara Campus, Kyotanabe)
Under construction
Japan · 1 project · Last reported
Summary
EdgeConneX, a data center developer backed by EQT Infrastructure, began building a 200 MW AI-ready hyperscale campus in March 2026 on a site of about 130,000 square metres at the Kagoya Tatara Campus in Kyotanabe City, roughly 30 km from central Osaka. The company calls it its first data center campus in Japan. It is being developed in partnership with Kagoya Asset Management; the groundbreaking was for a first building named ITM01, and the first phase is targeted to be ready for service in the first quarter of 2028. EdgeConneX said it plans about 350 MW in total across Greater Osaka, including a second project announced in August 2025.
Source record as of 2026-03-18 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: 34.81444, 135.76778 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Town or locality reference only; the facility position is not established.
Projects (1)
EdgeConneX Greater Osaka campus (Kagoya Tatara Campus, Kyotanabe)
Under construction last observed as of · Reported status
Location: Kyotanabe, Kyoto Prefecture, JP. The releases name the Kagoya Tatara Campus and place it in Kyotanabe City through a quote from the city's mayor; no address is given. The point and the prefecture come from the Kyotanabe Wikipedia article, so the point marks the city rather than the site. EdgeConneX; EdgeConneX; Wikipedia
Use: Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 200 MW | Planned · Campus · Unspecified | 2026-03-17 | Described as 200 MW of power capacity; neither release says whether this is IT or facility power. | EdgeConneX; EdgeConneX |
| Land area | about 13 hectares | Reported · Campus | 2026-03-17 | The Japanese release gives about 130,000 square metres as the site area; the English release says the campus spans 130,000 square metres. | EdgeConneX; EdgeConneX |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| EdgeConneX | Developer | Backed by EQT Infrastructure, part of the investment organisation EQT. | EdgeConneX; EdgeConneX |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2026-03 | Construction started | Actual | Groundbreaking for the first building, ITM01, reported in releases dated 17 and 18 March 2026. | EdgeConneX; EdgeConneX |
| 2028-Q1 | First operational | Planned | Ready-for-service target for the first phase. | EdgeConneX; EdgeConneX |
Only EdgeConneX's own English and Japanese releases were found for this campus; they carry different dates (17 and 18 March 2026). Kagoya Asset Management is described as EdgeConneX's partner on the project without a stated ownership or development role, and Kyotanabe's mayor is quoted congratulating the parties on the groundbreaking, so neither is listed as a party. The roughly 350 MW Greater Osaka (Kansai) total includes a separate second project and is not a figure for this campus. No investment amount, utility or power arrangement was disclosed. Kyotanabe coordinates and the prefecture come from Wikipedia (s3), used only for the location.
Sources for these details
- EdgeConneX Commences Construction of 200MW AI-Ready Hyperscale Campus in Greater Osaka — EdgeConneX; 2026-03-17 · Archived source
- EdgeConneX、関西エリアに200MWのAI対応ハイパースケールキャンパスの開発に着手 — EdgeConneX; 2026-03-18 · Archived source
- Kyōtanabe — Wikipedia; publication date not stated
- Companies
Source and location review
- Status source
- EdgeConneX Commences Construction of 200MW AI-Ready Hyperscale Campus in Greater Osaka evidence row
EdgeConneX · published 2026-03-17 · Company disclosure - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 223 days before the data update on 2026-10-27
Location details
- Coordinates
- 34.81444, 135.76778
- Geometry licence
- source-terms-not-recorded
- Use scope
- Locality reference only
- Scope class
- locality
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- The releases name the Kagoya Tatara Campus and place it in Kyotanabe City through a quote from the city's mayor; no address is given. The point and the prefecture come from the Kyotanabe Wikipedia article, so the point marks the city rather than the site.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 604f97e6
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| EdgeConneX Commences Construction of 200MW AI-Ready Hyperscale Campus in Greater Osaka Archived copy | EdgeConneX Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Land Area, Metric: Power Capacity, Milestone: Construction Started, Milestone: First Operational, Role: Developer | source-terms-not-recorded | EdgeConneX | 14db02de9af6c8cbbd1ca21c38e6ee107507c7ff44651cdb117a4b70fcd482a9Factual source record; not the publisher page | ||
| EdgeConneX、関西エリアに200MWのAI対応ハイパースケールキャンパスの開発に着手 Archived copy | EdgeConneX Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Land Area, Metric: Power Capacity, Milestone: Construction Started, Milestone: First Operational, Role: Developer | source-terms-not-recorded | EdgeConneX | 7de0786b54342483859a17da7d0accb61588a52704cda8d036b3e648ab634227Factual source record; not the publisher page | ||
| Kyōtanabe Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | 7c32f66172bce2c0be08728dd214df39706408930a3e077ce6eb972d3c6a5b58Factual source record; not the publisher page |
Cite this site
Kyars, K. (2026). EdgeConneX Greater Osaka campus (Kagoya Tatara Campus, Kyotanabe) [site vcc-site-6fbf2c20aeb106991c61]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-6fbf2c20aeb106991c61/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction