Alto Infrastructure SP01 Granada Data Center Campus

Under construction

Spain · 1 project · Last reported

Summary

Invest in Spain reports that Alto has begun construction of SP01 and explicitly types the first 10 MW as IT capacity, while preserving later ramps and total-power figures as distinct scopes. evidence

Invest in Spain, ICEX España Exportación e Inversiones · published 2026-07-09

Location

The interactive map needs JavaScript. Display anchor: 37.08328, -3.75204 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Project locator; building footprints are not mapped.

Projects (1)

Alto Infrastructure SP01 Phase 1 10 MW Critical IT

Under construction last observed as of · Authoritative construction start

The production application served by Alto's official site contains the current SP01 route, including the phased IT roadmap, 130 kV grid design, 100,000 square-meter site label, high-density design, intended 24/7 operations, and 1.29 design PUE. evidence

Alto Infrastructure · publication date not stated

Companies
  • Operator: Alto Infrastructure (intended) evidence
Workloads
  • AI (unspecified) (intended; government record, as of 2026-07-09) evidence
  • General cloud (intended; government record, as of 2026-07-09) evidence
  • HPC (intended; government record, as of 2026-07-09) evidence

Power

MetricStageValueAs ofMethodNotesEvidence
Critical IT loadPlanned10 MWReportedSource-explicit planned Phase 1 IT capacity only. The nested later 25 MW and full-build 70 MW IT scopes, 15 MW unspecified electrical figure, contracted 100 MW total-power figure, 130 kV grid voltage, design PUE, current load, generation, and annual energy are not this row and are not added or converted.evidence
Source and location review
Status source
Alto construye un centro de datos de última generación en Granada evidence row
Invest in Spain, ICEX España Exportación e Inversiones · published 2026-07-09 · Government record
Locator
Project locator · Official source · official_government_project_event_reference_point evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 110 days before the data update on 2026-10-27

Location details
Coordinates
37.08328, -3.75204
Geometry licence
rights-status-not-established
Use scope
Project locator
Scope class
official_government_project_event_reference_point
Authority
Official source
Source entity
Project
Method
official_junta_sp01_event_location_link_to_coordinate_point
Derivation
direct_geometry
Precision scope
Official project-event locator point used only to locate SP01. The seven-decimal redirect coordinate is preserved as published but is not treated as survey accuracy, parcel geometry, or a project centroid.
Horizontal uncertainty
Not reported

Neither the Junta agenda nor linked location redirect states the reference feature, collection method, or numeric horizontal accuracy.

Geometry evidence
dfffb2f5

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Alto Infrastructure SP01 Granada Data Center Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Alto construye un centro de datos de última generación en Granada
Archived copy
Invest in Spain, ICEX España Exportación e Inversiones
Government record
Physical status, Critical IT load observation, Workload, Intended workloadall-rights-reservedInvest in Spain, ICEX España Exportación e Inversiones9f55a303819fa94306ea8f99918bf6c807d6eeafee4862f11a7d085681d0587a
Retained source material; see source provenance
Alto Infrastructure production web application bundle containing the SP01 route
Archived copy
Alto Infrastructure
Company disclosure
Operator claimnot statedall-rights-reservedAlto Infrastructure7e5ec53ff90be0a65d73059192807716629e1608d3b8336f12dae6d56b932461
Retained source material; see source provenance
Junta de Andalucía agenda 217027 — colocación de la primera piedra de SP01
Archived copy
Junta de Andalucía
Government event project locator
Geometryrights-status-not-establishedJunta de Andalucía80ec02820f9c070b8416ba1a168fc1eee71b0ced77f1680f31d1408a73ea8bc3
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Alto Infrastructure SP01 Granada Data Center Campus [site vcc-site-7e1b680aa925165fe2ef]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-7e1b680aa925165fe2ef/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction