Princeton Digital Group JC3 Greater Jakarta
Under construction
Indonesia · 1 project · Last reported
Summary
Princeton Digital Group broke ground in November 2025 on JC3, a USD 1 billion, 120 MW AI-ready hyperscale campus in the Greenland International Industrial Center in Bekasi Regency, Greater Jakarta, about 25 km from its JC2 campus in Cibitung. The campus offers direct-to-chip liquid cooling alongside conventional cooling and dual grid feeds from state utility PLN, with a first phase targeted to be ready for service in the fourth quarter of 2026. In May 2026 PDG said it was raising about USD 856 million of debt to fund the ongoing build-out.
Source record as of 2026-05-07 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: -6.38360, 107.19110 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Approximate site reference; the exact facility position is unverified.
Projects (1)
Princeton Digital Group JC3 Greater Jakarta
Under construction last observed as of · Reported status
Location: Bekasi Regency, West Java, ID. PDG places JC3 in the Greenland International Industrial Center (GIIC), Bekasi Regency, without a street address; coordinates are the OpenStreetMap Nominatim centroid of the GIIC industrial estate. Princeton Digital Group; Princeton Digital Group
Use: Cloud, Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 120 MW | Under construction · Campus · Unspecified | 2026-05-07 | Princeton Digital Group; Princeton Digital Group | |
| Investment | 1,000,000,000 USD | Announced · Campus | 2025-11-19 | Princeton Digital Group |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Princeton Digital Group | Developer | Princeton Digital Group; Princeton Digital Group | |
| Princeton Digital Group | Operator | Princeton Digital Group | |
| PT Perusahaan Listrik Negara (PLN) | Utility | Provides dual grid feeds. | Princeton Digital Group |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2025-11-19 | Construction started | Actual | Groundbreaking. | Princeton Digital Group |
| 2026-Q4 | First operational | Planned | First phase targeted to be ready for service. | Princeton Digital Group |
| 2026-05-07 | Other | Actual | PDG announced about USD 856 million of debt (a USD 456 million underwritten syndicated loan plus an accordion of about USD 400 million in progress) for the JC3 build-out. | Princeton Digital Group |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Dual grid feeds from PLN. | Princeton Digital Group |
Related projects: pdg jc4 bekasi
Sources for these details
- Princeton Digital Group Breaks Ground on Milestone USD 1 Billion, 120 MW Greater Jakarta Campus — Princeton Digital Group; 2025-11-19
- PDG Raising ~USD 856 Million Debt for its Hyperscale Data Center Expansion in Indonesia — Princeton Digital Group; 2026-05-07 · Archived source
- PDG Acquires 240 MW of Powered Land in Jakarta, Advancing Its Rapid Expansion Across Asia — Princeton Digital Group; 2026-04-30
- Companies
Source and location review
- Status source
- Princeton Digital Group Breaks Ground on Milestone USD 1 Billion, 120 MW Greater Jakarta Campus evidence row
Princeton Digital Group · published 2025-11-19 · Company disclosure - Locator
- Approximate site reference · Compiled location reference · approximate_site evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 173 days before the data update on 2026-10-27
Location details
- Coordinates
- -6.38360, 107.19110
- Geometry licence
- source-terms-not-recorded
- Use scope
- Approximate site reference
- Scope class
- approximate_site
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- PDG places JC3 in the Greenland International Industrial Center (GIIC), Bekasi Regency, without a street address; coordinates are the OpenStreetMap Nominatim centroid of the GIIC industrial estate.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 701fe2a3
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| PDG Acquires 240 MW of Powered Land in Jakarta, Advancing Its Rapid Expansion Across Asia Archived copy | Princeton Digital Group Company disclosure | Imported: Geometry, Imported: Record | source-terms-not-recorded | Princeton Digital Group | 2df14d3f3abf87f00673c8f40fb6a4e8346e7e514bb67269fd8a1a1ea451871bFactual source record; not the publisher page | ||
| PDG Raising ~USD 856 Million Debt for its Hyperscale Data Center Expansion in Indonesia Archived copy | Princeton Digital Group Company disclosure | Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Other, Role: Developer | source-terms-not-recorded | Princeton Digital Group | 9e5e0e3ea15cf75ab0cd3c38aa5fd98947ed190552e3b4eac8effde59b4069b0Factual source record; not the publisher page | ||
| Princeton Digital Group Breaks Ground on Milestone USD 1 Billion, 120 MW Greater Jakarta Campus Archived copy | Princeton Digital Group Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Investment, Metric: Power Capacity, Milestone: Construction Started, Milestone: First Operational, Power Source: Grid, Role: Developer, Operator claim, Role: Utility | source-terms-not-recorded | Princeton Digital Group | 652604a33a598903ba3036d8966fe62fff52543ecd5a5dae78aad1cde82634b5Factual source record; not the publisher page |
Cite this site
Kyars, K. (2026). Princeton Digital Group JC3 Greater Jakarta [site vcc-site-99d9ae40e299f5a9f017]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-99d9ae40e299f5a9f017/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction