Huawei Cloud Horinger Data Center — Yungu South Zone
Shell
China · 1 project · Last reported
Summary
On 13 October 2026 the Horinger New Area investment promotion services bureau reported that the No. 3 data-centre machine-room building of the Phase 1 South Zone of the Huawei Cloud Horinger Data Center project had formally topped out (an item of 9 October 2026 had reported the topping out as recent). Topping out establishes work on the building structure (shell stage) by that date. Completion of the building, fit-out, commissioning and operation are not asserted; the Ascend 950 deployment, 1024 super-node architecture and card figures are design intentions. The other South Zone Phase 1 buildings, the South Zone 220 kV substation and the separate West and North Zones of the Huawei Horinger project are not included. evidence
Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区招商服务局) · published 2026-10-13
Location
The interactive map needs JavaScript. Display anchor: 40.54246, 111.85340 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Campus reference; individual project footprints are not mapped.
Projects (1)
Huawei Cloud Horinger Yungu South Zone Phase 1 — 3# data-centre machine-room building (3D data centre)
Shell last observed as of · Authoritative status update
Earlier government work-news item (发布日期 2026-10-09 09:46) by the same bureau: 'recently' (近日) the No. 3 data-centre machine-room building of the Phase 1 South Zone of the Huawei Cloud Horinger Data Center project formally topped out; it is Huawei's first 3D data centre in north China, to deploy Ascend 950 chips on the 1024 super-node architecture, with a design that lets a single building hold 100,000 AI accelerator cards (design figure). Corroborates the 13 October status record; identity and date context only. evidence
Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (中国(内蒙古)自由贸易试验区呼和浩特片区、内蒙古和林格尔新区招商服务局) · published 2026-10-09
Approval-result publicity page (发布时间 2025-02-10 16:15) in the department's nuclear and radiation supervision list, titled as the approval result of the radiation-category EIA for the Huawei Cloud Horinger Data Center project - Yungu South Zone (Phase 1) 220 kV substation, with the report form as its attachment. It approves ancillary grid works and is not consent for the data-centre buildings. evidence
Inner Mongolia Autonomous Region Department of Ecology and Environment · published 2025-02-10
- Companies
- Owner: Huawei Cloud Computing Technology Co., Ltd. (华为云计算技术有限公司) (current) evidence
Source and location review
- Status source
- Horinger New Area news item: 'Huawei's first 3D data centre in north China tops out' (华为北方首个3D数据中心封顶), 13 October 2026 evidence row
Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区招商服务局) · published 2026-10-13 · Government record - Locator
- Campus locator · Official source · official_eia_on_campus_substation_locator evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 14 days before the data update on 2026-10-27
Location details
- Coordinates
- 40.54246, 111.85340
- Geometry licence
- all-rights-reserved
- Use scope
- Campus locator
- Scope class
- official_eia_on_campus_substation_locator
- Authority
- Official source
- Source entity
- Campus
- Method
- official_eia_geographic_dms_point_transcription
- Derivation
- direct_geometry
- Precision scope
- EIA centre point of the South Zone Phase 1 project's own 220 kV substation building (147.1 m x 42.2 m), which the report states is one of the South Zone Phase 1 buildings and lies inside that project's land. Locates the South Zone campus through on-campus power infrastructure at its south-east side; not the 3# machine-room building whose topping out is recorded, nor an entrance or parcel centroid. The campus's data-centre buildings lie north-west of the point.
- Horizontal uncertainty
Not reported
No datum or positional accuracy is stated. The WGS84/CGCS2000 reading is supported by the report's internally consistent monitoring points and by agreement with independent Esri imagery of unstated accuracy and date (manual visual comparison, about 10-15 m). The point marks the campus's substation building at its south-east side, up to a few hundred metres from the 3# machine-room building. Decimal places are transcription precision, not accuracy.
- Geometry evidence
- 6eeb18ad
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Environmental impact report form: Huawei Cloud Horinger Data Center project - Yungu South Zone (Phase 1) 220 kV substation (华为云和林格尔数据中心项目-云谷南区(一期)220kV变电站建设项目环境影响评价报告表), Inner Mongolia Department of Ecology and Environment radiation-EIA approval-result publicity of 10 February 2025 Archived copy | Inner Mongolia Autonomous Region Department of Ecology and Environment Environmental assessment document | Geometry, Owner claim | all-rights-reserved | Inner Mongolia Autonomous Region Department of Ecology and Environment; report form prepared for 华为云计算技术有限公司 | 43373abd1e7cbebce5385004c643585775c906ed24b1994365b81c07a7a39645Retained source material; see source provenance | ||
| Esri World Imagery EPSG:4326 export around the Huawei Cloud Horinger Yungu South Zone and the Shengmu dairy ranch, Horinger (request bbox 111.8440-111.8630E, 40.5370-40.5480N) Archived copy | Esri Map feature | Site and project identity | not stated | all-rights-reserved | Esri, Maxar, Earthstar Geographics and the GIS user community (World Imagery) | f1f87a2e96503d7c02c37ef9296a97e7b96c167012de3372c3bbce0818449075Retained source material; see source provenance | |
| Horinger New Area news item: 'Huawei's first 3D data centre in north China tops out in Horinger New Area' (华为北方首个3D数据中心在和林格尔新区封顶), 9 October 2026 Archived copy | Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (中国(内蒙古)自由贸易试验区呼和浩特片区、内蒙古和林格尔新区招商服务局) Government record | Site and project identity | all-rights-reserved | 中国(内蒙古)自由贸易试验区呼和浩特片区、内蒙古和林格尔新区招商服务局, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn) | 3132a4267baea3013c4681563b665ef251736f94f0482362861141cb990ea6e2Retained source material; see source provenance | ||
| Horinger New Area news item: 'Huawei's first 3D data centre in north China tops out' (华为北方首个3D数据中心封顶), 13 October 2026 Archived copy | Investment Promotion Services Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区招商服务局) Government record | Site and project identity, Physical status | all-rights-reserved | 自贸试验区呼和浩特片区、和林格尔新区招商服务局, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn) | 306978d461918c0f215358a37c57e7d0ef159e766c0fb7d6ce3bd17ffd2a5c26Retained source material; see source provenance | ||
| Inner Mongolia Department of Ecology and Environment approval-result publicity for the radiation-category EIA of the Huawei Cloud Horinger Data Center project - Yungu South Zone (Phase 1) 220 kV substation, 10 February 2025 Archived copy | Inner Mongolia Autonomous Region Department of Ecology and Environment Government record | Site and project identity | all-rights-reserved | Inner Mongolia Autonomous Region Department of Ecology and Environment | 2c048a1a3a899ea143a52f5122e0c108ab5e7622ca92e38badfc4393021ba52cRetained source material; see source provenance |
Cite this site
Kyars, K. (2026). Huawei Cloud Horinger Data Center — Yungu South Zone [site vcc-site-aef6f651cb9065d646b0]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-aef6f651cb9065d646b0/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction