DayOne Data Centers, a Singapore-based operator, is building the Chonburi Tech Park hyperscale campus in the AMATA City area of Chonburi province, southeast of Bangkok. Groundbreaking was reported in March 2025 for a design of 180 MW of grid capacity in two phases, which trade press tied to a US$1 billion multi-year investment. In November 2025 DayOne added adjacent land that lifts the first site (CTP1) to 300 MW and signed an MoU with Amata for a second plot (CTP2) aimed at a 1 GW platform, plus a floating-solar supply deal. In April 2026 DayOne said more than 100 MW of IT capacity was expected to go live during 2026.

Source record as of 2026-04-26 · Details and sources

DayOne's F-1, filed October 5, 2026, reports its Thailand campuses at Chonburi Tech Park as of September 20, 2026. They had 120 MW of bookings: 73 MW of Capacity In Service (ready for service and fully fitted out) and 47 MW under construction. The campus is therefore partly in service; this does not establish completion of every phase or site. evidence

DayOne Data Centers Limited via SEC EDGAR · published 2026-10-05

Location

The interactive map needs JavaScript. Display anchor: 13.21700, 101.18300 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

State or region reference only; the facility position is not established.

Projects (1)

DayOne Chonburi Tech Park (CTP) data center campus

Operational last observed as of · Authoritative status update

This record reports under construction as of 2026-04-26. DayOne Data Centers (via AAP / Cision)

Location: AMATA City Chonburi industrial estate, Chonburi, TH. Sources place the campus in the AMATA City estate in Chonburi province but give no district or address. The point is the province coordinate from the Chonburi province Wikipedia article, so it marks the province, not the site. Intelligent CIO APAC; DayOne Data Centers; Wikipedia

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity180 MWPlanned · Campus · Grid connection2025-03-19Grid capacity of the campus as designed at groundbreaking, to be built in two phases; later raised for CTP1 (see the 300 MW figure).Intelligent CIO APAC
Power capacity300 MWPlanned · Phase · Unspecified · CTP1 with November 2025 land expansion2025-11-10Site power capacity of the first plot after adding adjacent land; the sources do not say whether this is IT or grid capacity.DayOne Data Centers; Bernama; DayOne Data Centers
Power capacity1,000 MWPlanned · Campus · Unspecified2025-11-10Target for a combined 1 GW power platform across CTP1 and the future CTP2 plot; CTP2 was covered only by an MoU.DayOne Data Centers; Bernama
Power capacitymore than 100 MWPlanned · Phase · It load · Capacity due to go live in 20262026-04-26IT capacity DayOne expected to bring online during 2026 as part of a multi-phase rollout.DayOne Data Centers (via AAP / Cision)
Investment1,000,000,000 USDAnnounced · Campus2025-03-19Intelligent CIO ties a US$1 billion investment, committed over the next few years, to this campus. DayOne's April 2026 release (s4) instead describes US$1 billion as the commitment it made on entering Thailand, without tying it to the campus; the conflict is unresolved.Intelligent CIO APAC
Land areaabout 12.2 hectaresReported · Campus2025-03-19Reported as 122,000 square metres for the campus at groundbreaking, before the November 2025 additions.Intelligent CIO APAC
Land areaabout 16.3 acresPlanned · Phase · CTP1 adjacent land added in November 20252025-11-10Reported as 41.3 rai of adjacent land.DayOne Data Centers; Bernama

Companies and organizations

NameRoleNotesSources
DayOne Data CentersDeveloperSingapore-headquartered developer and operator of the campus.Intelligent CIO APAC; DayOne Data Centers; DayOne Data Centers (via AAP / Cision)
Amata B.Grimm Renewable Energy (AMBRE)Power supplierSigned a private power purchase agreement to supply floating-solar electricity to the campus.DayOne Data Centers; Bernama
Provincial Electricity Authority (PEA)UtilityPart of the three-way arrangement that delivers the solar power over its grid.DayOne Data Centers

Timeline

DateEventActual or plannedNotesSources
2024-11AnnouncedActualDayOne announced its entry into Thailand.DayOne Data Centers
2025-03Construction startedActualGroundbreaking reported by Intelligent CIO on 2025-03-19 without a ceremony date; DayOne's April 2026 release gives only the year 2025.Intelligent CIO APAC; DayOne Data Centers (via AAP / Cision)
2025-11-10Expansion announcedActualMoU with Amata for CTP2 and adjacent CTP1 land, lifting CTP1 to 300 MW and targeting a 1 GW platform; solar PPA signed the same day.DayOne Data Centers; Bernama
2026First operationalPlannedMore than 100 MW of IT capacity expected to go live in 2026; DayOne's market page lists a 2026 ready-for-service date.DayOne Data Centers (via AAP / Cision); DayOne Data Centers
2027OtherPlannedExpected commercial operation of the floating-solar plant and start of renewable integration.DayOne Data Centers; DayOne Data Centers (via AAP / Cision)

Power supply

TypeDescriptionSources
GridThe campus was designed around 180 MW of grid capacity; solar power is delivered through the Provincial Electricity Authority grid.Intelligent CIO APAC; DayOne Data Centers
SolarPrivate power purchase agreement with AMBRE for a 22 kV floating-solar plant in the AMATA City estate, initially 42.5 MWp, expected to start commercial operation in 2027.DayOne Data Centers; Bernama

Amata Corporation signed the November 2025 MoU covering CTP2 and the land added to CTP1 and is called a strategic partner, but no formal ownership or development role is stated, so it is not listed as a party. The US$1 billion rests on one trade-press report (s1); DayOne's April 2026 release frames it as a Thailand-entry commitment. That release describes the campus as under development with capacity due in 2026; no source confirms capacity was live by October 2026. Only Intelligent CIO places the campus in AMATA City; DayOne's pages name Chonburi province. Province coordinates come from Wikipedia (s5), used only for the map point.

Sources for these details
Companies
  • Developer: DayOne Data Centers (unknown scope) evidence
  • Developer: DayOne Data Centers (unknown scope) evidence
  • Developer: DayOne Data Centers (unknown scope) evidence
  • Power Supplier: Amata B.Grimm Renewable Energy (AMBRE) (unknown scope) evidence
  • Power Supplier: Amata B.Grimm Renewable Energy (AMBRE) (unknown scope) evidence
  • Utility: Provincial Electricity Authority (PEA) (unknown scope) evidence
Source and location review
Status source
DayOne Data Centers Limited Form F-1 registration statement, filed October 5, 2026 (Internet Archive copy of the EDGAR document) evidence row
DayOne Data Centers Limited via SEC EDGAR · published 2026-10-05 · Regulatory filing
Locator
State or region reference only · Compiled location reference · admin1 evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 37 days before the data update on 2026-10-27

Location details
Coordinates
13.21700, 101.18300
Geometry licence
source-terms-not-recorded
Use scope
State or region reference only
Scope class
admin1
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
Sources place the campus in the AMATA City estate in Chonburi province but give no district or address. The point is the province coordinate from the Chonburi province Wikipedia article, so it marks the province, not the site.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
3ec56c55

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for DayOne Chonburi Tech Park (CTP) data center campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Chonburi province
Archived copy
Wikipedia
Other
Imported: Geometry, Imported: Recordnot statedsource-terms-not-recordedWikipedia845b2ef18719c6734d699f2d173513a96aafa76af89d9c775c902c94dd51276a
Factual source record; not the publisher page
DayOne breaks ground on hyperscale data center pioneering Thailand's digital future
Archived copy
Intelligent CIO APAC
Trade publication
Imported: Geometry, Imported: Record, Metric: Investment, Metric: Land Area, Metric: Power Capacity, Milestone: Construction Started, Power Source: Grid, Role: Developersource-terms-not-recordedIntelligent CIO APACb379bc7063f57facd1f7599613052abf1ca7cc488143b9a2c4e417eb2701d75d
Factual source record; not the publisher page
DayOne Data Centers Limited Form F-1 registration statement, filed October 5, 2026 (Internet Archive copy of the EDGAR document)
Archived copy
DayOne Data Centers Limited via SEC EDGAR
Regulatory filing
Physical status, Operator claim, Owner claimsource-terms-not-recordedDayOne Data Centers Limited; U.S. Securities and Exchange Commission EDGAR; archived by the Internet Archive Wayback Machineef2d8312d6f912c7480d5e7a5e54b11c47918e85c16c4ae5a436871445aab2f0
Retained source material; see source provenance
DayOne Launches Inaugural Tech & AI Career Expo in Thailand, Showcasing Commitment to Digital Infrastructure and Talent Development
Archived copy
DayOne Data Centers (via AAP / Cision)
Company disclosure
Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Construction Started, Milestone: First Operational, Milestone: Other, Role: Developersource-terms-not-recordedDayOne Data Centers (via AAP / Cision)004b16f0776a20bfbdbd69c0973fb3982bbc254f7fed2b585324476681e543f4
Factual source record; not the publisher page
DayOne Strengthens Thailand's Digital Hub with Amata as Chonburi Campus Expands Toward the Country's First 1GW Power Platform
Archived copy
DayOne Data Centers
Company disclosure
Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Milestone: Expansion Announced, Milestone: Other, Power Source: Grid, Power Source: Solar, Role: Developer, Role: Power Supplier, Role: Utilitysource-terms-not-recordedDayOne Data Centerse256ab2998bb22ab692e6d9b989e9561d958e57838e38ad130e5054852169ecf
Factual source record; not the publisher page
DayOne, Amata In Deal To Build Thailand's First 1GW Power Platform
Archived copy
Bernama
News
Imported: Record, Metric: Land Area, Metric: Power Capacity, Milestone: Expansion Announced, Power Source: Solar, Role: Power Suppliersource-terms-not-recordedBernamae8ada35cadadbbd1acffd071462972420053729f440a5204c3b2143f4132ce32
Factual source record; not the publisher page
Our markets: Greater Bangkok
Archived copy
DayOne Data Centers
Company disclosure
Imported: Record, Metric: Power Capacity, Milestone: Announced, Milestone: First Operationalnot statedsource-terms-not-recordedDayOne Data Centers2aef33d8937f73038f2ed1cfe20199005d530602fb65e3c65d43b50469af4c9b
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). DayOne Chonburi Tech Park (CTP) data center campus [site vcc-site-b020cba78b5fa2123866]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-b020cba78b5fa2123866/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction