Hexagon Data Center (Riyadh)
Under construction
Saudi Arabia · 1 project · Last reported
Summary
Government data centre being built in Riyadh by the Saudi Data and Artificial Intelligence Authority (SDAIA), billed as the world's largest Tier IV government data centre. The foundation stone was laid in early January 2026 for a facility of up to 480 MW on a site of about 30 million square feet, designed to host more than 290 government systems and to seed a wider national network of centres. Reported project value is about USD 2.7 billion; a project-tracking profile names Albawani as main contractor, says construction was progressing in April 2026 and gives a Q1 2029 completion target.
Source record as of 2026-05-01 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: 24.63300, 46.71700 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Town or locality reference only; the facility position is not established.
Projects (1)
Hexagon Data Center (Riyadh)
Under construction last observed as of · Reported status
Location: Riyadh, Riyadh Province, SA. City coordinates from the Riyadh Wikipedia page; the sources do not name a district. W.Media; Sharikat Mubasher; Wikipedia
Use: Enterprise
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | up to 480 MW | Planned · Campus · Unspecified | 2026-05-01 | Announcement coverage gives capacity of up to 480 MW without a scope; the project-tracking profile labels it IT load capacity. | W.Media; Sharikat Mubasher; Oil & Gas News |
| Investment | about 2,700,000,000 USD | Reported · Campus | 2026-05-01 | W.Media attributes this estimate to Gulf News; the project-tracking profile lists the same project value. No official SDAIA figure was found. | W.Media; Oil & Gas News |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Saudi Data and Artificial Intelligence Authority (SDAIA) | Developer | W.Media; Sharikat Mubasher; Oil & Gas News | |
| Albawani | Builder | Named as main contractor in a trade project-tracking profile; not confirmed by SDAIA in sources reviewed. | Oil & Gas News |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2026-01 | Construction started | Actual | Foundation stone laid at a ceremony at which SDAIA's president received senior officials. | W.Media; Sharikat Mubasher |
| 2029-Q1 | Fully operational | Planned | Completion target given in a trade project-tracking profile. | Oil & Gas News |
Coverage published on 4 and 5 January 2026 reports the foundation stone as already laid without giving the ceremony date, so only the month is recorded. The 30 million square feet is described as the total or site area and is not recorded as a floor area metric. W.Media reports LEED Gold certification and the project-tracking profile mentions direct liquid and hybrid cooling; no source gives power supply details.
Sources for these details
- SDAIA lays foundation stone for 480MW Hexagon government data center in Riyadh — W.Media; 2026-01-05
- Saudi Arabia lays cornerstone for Hexagon data center in Riyadh — Sharikat Mubasher; 2026-01-04
- SDAIA Hexagon Data Centre (project profile) — Oil & Gas News; 2026-05-01 · Archived source
- Riyadh — Wikipedia; publication date not stated
- Companies
- Developer: Saudi Data and Artificial Intelligence Authority (SDAIA) (unknown scope) evidence
- Developer: Saudi Data and Artificial Intelligence Authority (SDAIA) (unknown scope) evidence
- Developer: Saudi Data and Artificial Intelligence Authority (SDAIA) (unknown scope) evidence
- Builder: Albawani (unknown scope) evidence
Source and location review
- Status source
- SDAIA lays foundation stone for 480MW Hexagon government data center in Riyadh evidence row
W.Media · published 2026-01-05 · Trade publication - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 179 days before the data update on 2026-10-27
Location details
- Coordinates
- 24.63300, 46.71700
- Geometry licence
- source-terms-not-recorded
- Use scope
- Locality reference only
- Scope class
- locality
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- City coordinates from the Riyadh Wikipedia page; the sources do not name a district.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 6627618c
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Riyadh Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | ef6234e9111426727c7fe0a752158117e18222ff6c786a6ef124f8266b4cf17eFactual source record; not the publisher page | |
| Saudi Arabia lays cornerstone for Hexagon data center in Riyadh Archived copy | Sharikat Mubasher News | Imported: Geometry, Imported: Record, Metric: Power Capacity, Milestone: Construction Started, Role: Developer | source-terms-not-recorded | Sharikat Mubasher | ff6d01bd8000fc27ad70e3fa2145e0d678dc1a9a623682dbd3b4d1f11857802eFactual source record; not the publisher page | ||
| SDAIA Hexagon Data Centre (project profile) Archived copy | Oil & Gas News Trade publication | Imported: Record, Imported: Status, Metric: Investment, Metric: Power Capacity, Milestone: Fully Operational, Role: Builder, Role: Developer | source-terms-not-recorded | Oil & Gas News | 69a5ee4855530623d960fea98c254f8750036b67b46369e2d1dc71668f2247c3Factual source record; not the publisher page | ||
| SDAIA lays foundation stone for 480MW Hexagon government data center in Riyadh Archived copy | W.Media Trade publication | Imported: Geometry, Imported: Record, Imported: Status, Metric: Investment, Metric: Power Capacity, Milestone: Construction Started, Role: Developer | source-terms-not-recorded | W.Media | 79735620d4c5ae037e0dda29c78a9091f3f6b2abeed8a3039ab1dd68e5d79c02Factual source record; not the publisher page |
Cite this site
Kyars, K. (2026). Hexagon Data Center (Riyadh) [site vcc-site-ba5a5fcafa0e68a3bbc8]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-ba5a5fcafa0e68a3bbc8/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction