STACK MIL05 Data Center Campus, Vignate (Via Galileo Galilei)

Announced

Italy · 1 project · Last reported

Summary

ARPA Lombardia's letter registered by the Ministry on 9 October 2026, in the compliance verification ID_VIP 15187 of condition 6B of VIA decree no. 411 of 30 June 2026, names the project 'Realizzazione di un nuovo Data Center denominato MIL05 ubicato nel comune di Vignate (MI)' of Infrastructure Italia Land 5 S.r.l. and finds the proponent's power-line excavation documents suitable. This dated government record supports announced only. The VIA decree is an environmental-compatibility decision, not a building permit; the conditions being verified are ante-operam measures due before works start, and a second compliance verification (ID_VIP 15251, conditions 3 and 6A) entered technical review on 16 October 2026. No building permit, site work, construction or operation is asserted. evidence

ARPA Lombardia (regional environmental protection agency), published on the MASE VA portal · published 2026-10-12

Location

The interactive map needs JavaScript. Display anchor: 45.50130, 9.36985 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

MIL05 — planned 60 MW IT two-building data-centre campus (MIL05A and MIL05B; VIA decree DM 411/2026, ID_VIP 13497)

Announced last observed as of · Project announcement

The project page names the proponent Infrastructure Italia Land 5 S.r.l., the territory (Lombardia, Milano, Vignate) and three procedures: the VIA ID_VIP 13497 filed 23 December 2024, concluded by decree DM_2026-0000411 of 30 June 2026 (positive with conditions, notified 9 July 2026); a compliance verification ID_VIP 15187 filed 7 August 2026 for condition 6B; and a compliance verification ID_VIP 15251 filed 30 September 2026 for conditions 3 and 6A, whose technical review by the CTVIA started on 16 October 2026. Both compliance verifications are in technical review. evidence

Ministero dell'Ambiente e della Sicurezza Energetica (MASE), Direzione generale Valutazioni ambientali · publication date not stated

The decree, on the application of Infrastructure Italia Land 5 S.r.l. received 23 December 2024, records that the project provides in Vignate (MI) for a new data centre supplied by two 220 kV cables, with 50 emergency generators of 298 MWt in total, diesel storage of 2,083 m3, a dedicated 220 kV substation on the south-east side of the site and photovoltaic plants on the roofs and car-park canopies, and expresses a positive environmental-compatibility judgement with conditions. It is an environmental decision under the VIA procedure, not a building permit. evidence

Ministero dell'Ambiente e della Sicurezza Energetica, in concert with the Ministero della cultura · published 2026-07-01

The proponent's report, headed 'MIL05 Vignate (MI) - Data Center, Via Galileo Galilei SNC, 20052 Vignate (MI)', refers to the conditions of MASE decree 411/2026 for project ID_VIP 13497 and states that this first phase of compliance verification concerns measures to be put in place before the start of works; condition 3 (ante-operam, before the start of works) requires a construction-site traffic study, which is attached. The header and introduction also carry an 'ID_VIP 11245', a 'Decreto MASE 212.10-04-2026' and a 'VIA postuma' wording that match a different STACK procedure (Liscate) and appear to be template carry-overs; the body, the MASE page and the ARPA letter all cite decree 411/2026 for ID_VIP 13497. evidence

Infrastructure Italia Land 5 S.r.l. (filing published on the MASE VA portal) · published 2026-10-05

The air-quality study models 50 standby-generator stacks (E1-E50, 14 m high) and prints their coordinates in UTM 32N WGS84 in Tabella 4.3b: E1-E20 at about 528,817-529,013 E / 5,038,782-5,038,810 N, E21-E39 at about 528,838-529,031 E / 5,038,652-5,038,679 N, and E40-E50 at about 528,630-528,779 E / 5,038,550-5,038,577 N. evidence

Infrastructure Italia Land 5 S.r.l. (filing published on the MASE VA portal) · published 2025-03-10

Georeferenced imagery extract used only to check the WGS84 reading of the filed building outlines: A and B fall on a large cleared plot south of an existing factory complex, C and D on the south-west lot (wooded strip and a small existing building), with no systematic offset. Not a measured accuracy and not a status observation. evidence

Esri · publication date not stated

Companies
  • Operator: STACK Infrastructure (intended) evidence
Source and location review
Status source
ARPA Lombardia response of 9 October 2026 (MASE incoming 0210616) in the compliance verification ID_VIP 15187 for condition 6B of VIA decree DM 411 of 30 June 2026: 'Realizzazione di un nuovo Data Center denominato MIL05 ubicato nel comune di Vignate (MI)' evidence row
ARPA Lombardia (regional environmental protection agency), published on the MASE VA portal · published 2026-10-12 · Government record
Locator
Campus locator · Compiled location reference · official_filing_building_outline_union_centroid evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 18 days before the data update on 2026-10-27

Location details
Coordinates
45.50130, 9.36985
Geometry licence
all-rights-reserved
Use scope
Campus locator
Scope class
official_filing_building_outline_union_centroid
Authority
Compiled location reference
Source entity
Campus
Method
regulatory_filing_utm32n_wgs84_building_vertices_a_b_c_d_union_area_centroid_epsg32632_inverse_projected_to_wgs84
Derivation
coordinate_transform
Precision scope
Area centroid of the union of the four planned building outlines (A, B, C and D, 18,086 m2 in total) printed in UTM 32N WGS84 in the proponent's building-downwash integration to the MIL05 VIA. A and B form the main MIL05A data-hall building; C and D lie on the south-west MIL05B lot, 50 m (D) and 116 m (C) from A+B. The point falls inside outline A, 10.7 m from its edge; the outer vertices are up to 297 m away. The outlines are modelling inputs, not surveyed footprints or parcel boundaries.
Horizontal uncertainty
Not reported

The filing states no positional accuracy; the point is the computed centroid of modelled outlines spread over about 430 by 230 m, and the final design may differ. Decimal places are computation precision, not accuracy.

Geometry evidence
a70b80b2

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for STACK MIL05 Data Center Campus, Vignate (Via Galileo Galilei)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
'Building DownWash e Aggiornamento mappe ricadute' (R001-1670346PPI-V00), integration to the MIL05 VIA (ID_VIP 13497) filed by Infrastructure Italia Land 5 S.r.l.
Archived copy
Infrastructure Italia Land 5 S.r.l. (filing published on the MASE VA portal)
Regulatory filing
Geometryall-rights-reservedInfrastructure Italia Land 5 S.r.l. / MASE Portale Valutazioni e Autorizzazioni Ambientali43f56f7f352ed1808e4de7df776b2054dde7d303a297719f1f30828a3464d804
Retained source material; see source provenance
'Studio degli impatti sulla qualità dell'aria - Nuovo Data Center Vignate' (R002-1669569PPI-V01_2024), Allegato A to the SIA of the MIL05 VIA (ID_VIP 13497), filed by Infrastructure Italia Land 5 S.r.l.
Archived copy
Infrastructure Italia Land 5 S.r.l. (filing published on the MASE VA portal)
Regulatory filing
Site and project identityall-rights-reservedInfrastructure Italia Land 5 S.r.l. / MASE Portale Valutazioni e Autorizzazioni Ambientalie7d611ca40082decefb9ef311e161b2ed9cbdfe28a2ebdf0a12996d805432d27
Retained source material; see source provenance
ARPA Lombardia response of 9 October 2026 (MASE incoming 0210616) in the compliance verification ID_VIP 15187 for condition 6B of VIA decree DM 411 of 30 June 2026: 'Realizzazione di un nuovo Data Center denominato MIL05 ubicato nel comune di Vignate (MI)'
Archived copy
ARPA Lombardia (regional environmental protection agency), published on the MASE VA portal
Government record
Project announcementall-rights-reservedARPA Lombardia / MASE Portale Valutazioni e Autorizzazioni Ambientali9df86260b4c4a8b110029dcabdf3df281932d536753c963c2b969b787d5304c8
Retained source material; see source provenance
Esri World Imagery export: Vignate, Via Galileo Galilei area (EPSG:32632, 528480-529200 E, 5038420-5038950 N)
Archived copy
Esri
Other
Site and project identitynot statedEsri World Imagery terms of use; not redistributedEsri, Maxar, Earthstar Geographics, and the GIS User Community (Esri World Imagery)3eb85de3ddefa994ac6f4d4e7bc2e584a99119931b817070565b9f4a3a9e51ab
Retained source material; see source provenance
Infrastructure Italia Land 5 S.r.l.: compliance report for environmental conditions 3A, 3B and 3C (construction-site traffic), MIL05 Vignate (MI) Data Center, Via Galileo Galilei SNC (document dated 28 September 2026; ID_VIP 15251)
Archived copy
Infrastructure Italia Land 5 S.r.l. (filing published on the MASE VA portal)
Regulatory filing
Site and project identityall-rights-reservedInfrastructure Italia Land 5 S.r.l. / MASE Portale Valutazioni e Autorizzazioni Ambientali9cf2304f29e19c43082aa7c13635cdc6b1c1dcc2a2e6169d09c4c8c218afad67
Retained source material; see source provenance
MASE decree DM_2026-0000411 of 30 June 2026: environmental compatibility decree for 'Realizzazione di un nuovo Data Center denominato "MIL05" ubicato nel comune di Vignate (MI)' (ID_VIP 13497)
Archived copy
Ministero dell'Ambiente e della Sicurezza Energetica, in concert with the Ministero della cultura
Government record
Site and project identityall-rights-reservedMASE MASE Portale Valutazioni e Autorizzazioni Ambientalibdad31a545fda071f0a8ea62948d1893c6245cb126cc002ba30c7bae9966a293
Retained source material; see source provenance
MASE VA portal: object 11494, 'Realizzazione di un nuovo Data Center denominato "MIL05" ubicato nel comune di Vignate (MI)' (procedures 13497, 15187, 15251)
Archived copy
Ministero dell'Ambiente e della Sicurezza Energetica (MASE), Direzione generale Valutazioni ambientali
Government record
Site and project identitynot statedall-rights-reservedMASE MASE Portale Valutazioni e Autorizzazioni Ambientaliac7400685da95eabed37c20912b99fd96a14f7926ebe3ddc1e622f52d8f00f1f
Retained source material; see source provenance
STACK Infrastructure: MIL05 campus page (Milan locations)
Archived copy
STACK Infrastructure
Operator website
Operator claimnot statedall-rights-reservedSTACK Infrastructurebf0d5a85179856a4ceb26a1d3ce14e99168ddbe70ed35517984a45b1eb2a545c
Retained source material; see source provenance