Hofheim-Marxheim Data Center (Rheingaustraße 201)

Announced

Germany · 1 project · Last reported

Summary

Data Center Group announces on 1 October 2026 a new data centre in Hofheim-Marxheim (about 11,000 m2 plot, up to 30 MVA, three phases, operations planned Q1 2028) for an unnamed international operator, with site setup to begin on 5 October. The RP Darmstadt decision of 19 August 2026 permits its 14 emergency generators but records that the data-centre building permit, applied for in September 2025, had not yet been granted. Announced status only; no physical work is established. evidence

Data Center Group · published 2026-10-01

Location

The interactive map needs JavaScript. Display anchor: 50.05735, 8.43446 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Project locator; building footprints are not mapped.

Projects (1)

Rechenzentrum Hofheim-Marxheim — new three-phase data centre

Announced last observed as of · Project announcement

The authority's public-notice page for permits under the Industrial Emissions Directive lists, per decision, the applicant, project, notice date, decision date and file reference, with the decision document attached. In-window entries include A100 ROW GmbH, Liederbach (50 emergency generators for the Rechenzentren Liederbach at Sindlinger Weg 1; decision 14.08.2026; notice 15.10.2026), DCH GmbH, Hofheim am Taunus (14 emergency generators for the Rechenzentrum Hofheim-Marxheim at Rheingaustraße 201; decision 19.08.2026; notice 24.09.2026), Data 4 Germany, Hanau (decision 17.06.2026; notice 28.07.2026), VDC FRA31 GmbH, Raunheim (decision 27.04.2026; notice 12.08.2026) and Equinix Hyperscale 2 (FR16) GmbH (decision 17.04.2025; notice 11.08.2026). evidence

Regierungspräsidium Darmstadt · publication date not stated

Generalised (1:250,000) official municipal boundary of Hofheim am Taunus, AGS 06436007, in EPSG:25832; consistency check of the permit coordinate only. evidence

Bundesamt für Kartographie und Geodäsie (BKG) · publication date not stated

Source and location review
Status source
Data Center Group: Neues Groß-Rechenzentrum in Hofheim (1 October 2026) evidence row
Data Center Group · published 2026-10-01 · Company disclosure
Locator
Project locator · Compiled location reference · official_permit_site_reference_coordinate evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 26 days before the data update on 2026-10-27

Location details
Coordinates
50.05735, 8.43446
Geometry licence
public-record-source-terms
Use scope
Project locator
Scope class
official_permit_site_reference_coordinate
Authority
Compiled location reference
Source entity
Campus
Method
rp_darmstadt_permit_utm32n_rechts_hochwert_32459517_5545160_pyproj_to_wgs84
Derivation
coordinate_transform
Precision scope
Site reference coordinate printed in the generator permit for Gemarkung Marxheim Flur 30 Flurstück 17/3 (building "Rechenzentrum Hofheim-Marxheim", Rheingaustraße 201). It locates the data-centre site, not the building footprint, the generator yard or a works extent.
Horizontal uncertainty
Not reported

The permit does not state what the coordinate represents or its accuracy (printed to 0.1 mm), and the building footprint within the roughly 1.1 ha plot is not published.

Geometry evidence
dd523dee

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Hofheim-Marxheim Data Center (Rheingaustraße 201)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
BKG VG250 WFS: municipality polygon Hofheim am Taunus (AGS 06436007)
Archived copy
Bundesamt für Kartographie und Geodäsie (BKG)
Government record
Site and project identitynot stateddl-de/by-2-0© GeoBasis-DE / BKG (2026), dl-de/by-2-0370c5f7f7f3ae30d92254bf3fea90cf327542bb0ee4b256320e36423a9969f93
Retained source material; see source provenance
Data Center Group: Neues Groß-Rechenzentrum in Hofheim (1 October 2026)
Archived copy
Data Center Group
Company disclosure
Project announcementall-rights-reservedData Center Groupeb9ba65744ffcda9fb74b95e362f022197e2467b3f14d5921cf68cd992fffaea
Retained source material; see source provenance
Regierungspräsidium Darmstadt: Öffentliche Bekanntmachungen — Industrieemissionen (BImSchG/IED permit notices)
Archived copy
Regierungspräsidium Darmstadt
Government record
Site and project identitynot statedpublic-record-source-termsRegierungspräsidium Darmstadtf4019a9484ea8820fbaa3961cb28b547e80787af3126429c295cbacdfa0f13e8
Retained source material; see source provenance
RP Darmstadt Genehmigungsbescheid 19.08.2026, DCH GmbH — 14 emergency generators for the Rechenzentrum Hofheim-Marxheim, Rheingaustraße 201 (GZ 0029-IV-Wi 43.2-53.u.36.07-00002#2025-00001)
Archived copy
Regierungspräsidium Darmstadt, Abteilung Umwelt Wiesbaden
Government record
Site and project identity, Geometrypublic-record-source-termsRegierungspräsidium Darmstadt9973a81b9206af690ad41d5ff56eafb8025be1d2218ffec499df766c7865d29a
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Hofheim-Marxheim Data Center (Rheingaustraße 201) [site vcc-site-ccd3fa0c0268ff3715c1]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-ccd3fa0c0268ff3715c1/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction