Vantage Data Centers Johor campus (JHB1), Sedenak Tech Park
Partially operational
Malaysia · 1 project · Last reported
Summary
Hyperscale campus of nearly 73 acres in Sedenak Tech Park, Johor, inside the Johor-Singapore Special Economic Zone. Developed by Yondr Group with green-loan financing, it is planned for more than 300 MW of IT capacity across three data centers. Vantage Data Centers agreed in September 2025 to buy it, alongside a US$1.6 billion investment in its Asia-Pacific platform that partly funded the deal, and completed the purchase in November 2025. Vantage's campus page, viewed in October 2026, says the first facility is operational and the rest are under development.
Source record as of 2026-10-09 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: 1.71367, 103.52478 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Town or locality reference only; the facility position is not established.
Projects (1)
Vantage Data Centers Johor campus (JHB1), Sedenak Tech Park
Partially operational last observed as of · Reported status
Location: Sedenak (Sedenak Tech Park), Kulai District, Johor, MY. Sources name Sedenak Tech Park in Johor without an address. The point is the Sedenak coordinate from its Wikipedia article (which also gives Kulai District), so it marks the locality rather than the parcel. Vantage Data Centers; W.Media; Vantage Data Centers; Wikipedia
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | more than 300 MW | Planned · Campus · It load | 2025-11-24 | IT capacity across three data centers once fully developed; the campus page gives 300MW+ of critical IT load. | Vantage Data Centers; W.Media; Vantage Data Centers |
| Land area | about 73 acres | Reported · Campus | 2025-11-24 | The campus page gives 73 acres (30 hectares). | Vantage Data Centers; W.Media; Vantage Data Centers |
| Floor area | more than 930,000 sq_ft | Planned · Campus | 2026-10-09 | Given as more than 930,000 square feet (87,000 square metres). | Vantage Data Centers |
| Buildings | 3 count | Planned · Campus | 2025-11-24 | Vantage Data Centers; W.Media; Vantage Data Centers |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Yondr Group | Developer | Original developer, which sold the campus to Vantage in 2025. | Vantage Data Centers; W.Media |
| Vantage Data Centers | Owner | Bought the campus from Yondr; the deal closed in November 2025. | Vantage Data Centers; W.Media |
| Vantage Data Centers | Operator | Vantage Data Centers | |
| Tenaga Nasional Berhad (TNB) | Utility | Vantage Data Centers |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2025-09-10 | Other | Actual | Vantage announced it would acquire the campus from Yondr Group. | Vantage Data Centers |
| 2025-11-24 | Other | Actual | Acquisition completed, with more than 30 Yondr staff joining Vantage. | W.Media |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Supplied by TNB through dedicated dual 275 kV feeds, with multiple 33 kV feeds per building. | Vantage Data Centers |
The partially operational status rests on Vantage's undated campus page (s3), read on 2026-10-09, which says the first facility is operational; no dated source gives when it opened or its capacity. The price paid for the campus was not disclosed. The US$1.6 billion was raised for Vantage's whole Asia-Pacific platform, led by an affiliate of GIC with a subsidiary of the Abu Dhabi Investment Authority, and only part of it went to this acquisition, so it is not a campus figure and those investors are not listed as campus parties. When Yondr began building the campus was not found in the sources opened. Sedenak coordinates and Kulai District come from Wikipedia (s4), used only for the location.
Sources for these details
- Vantage Data Centers Secures $1.6B Investment in APAC Platform from GIC and ADIA — Vantage Data Centers; 2025-09-10
- Vantage Data Centers completes purchase of Yondr's 300MW data center in Johor; closes US$1.6B investment in APAC — W.Media; 2025-11-24
- Johor, Malaysia Data Center Campus — Vantage Data Centers; publication date not stated · Archived source
- Sedenak — Wikipedia; publication date not stated · Archived source
- Companies
- Developer: Yondr Group (unknown scope) evidence
- Developer: Yondr Group (unknown scope) evidence
- Owner: Vantage Data Centers (unknown scope) evidence
- Owner: Vantage Data Centers (unknown scope) evidence
- Operator: Vantage Data Centers (unknown scope) evidence
- Utility: Tenaga Nasional Berhad (TNB) (unknown scope) evidence
Source and location review
- Status source
- Johor, Malaysia Data Center Campus evidence row
Vantage Data Centers · publication date not stated · Company disclosure - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 18 days before the data update on 2026-10-27
Location details
- Coordinates
- 1.71367, 103.52478
- Geometry licence
- source-terms-not-recorded
- Use scope
- Locality reference only
- Scope class
- locality
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- Sources name Sedenak Tech Park in Johor without an address. The point is the Sedenak coordinate from its Wikipedia article (which also gives Kulai District), so it marks the locality rather than the parcel.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 9a802eef
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Johor, Malaysia Data Center Campus Archived copy | Vantage Data Centers Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Buildings, Metric: Floor Area, Metric: Land Area, Metric: Power Capacity, Power Source: Grid, Operator claim, Role: Utility | not stated | source-terms-not-recorded | Vantage Data Centers | 8245dd5e41e67489119803d9ca37fbc79007cb0143c09d96ece37af237ca0461Factual source record; not the publisher page | |
| Sedenak Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | 02d29fa7a6be74f7e8d541e30cd5a29b2fb9ff0acdfb4201d1b815337fbce097Factual source record; not the publisher page | |
| Vantage Data Centers completes purchase of Yondr's 300MW data center in Johor; closes US$1.6B investment in APAC Archived copy | W.Media Trade publication | Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Land Area, Metric: Power Capacity, Milestone: Other, Role: Developer, Owner claim | source-terms-not-recorded | W.Media | edcb5b88de66aeff85977bedf28589f36c3fd571ae9fcc925e3402273dcb479cFactual source record; not the publisher page | ||
| Vantage Data Centers Secures $1.6B Investment in APAC Platform from GIC and ADIA Archived copy | Vantage Data Centers Company disclosure | Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Land Area, Metric: Power Capacity, Milestone: Other, Role: Developer, Owner claim | source-terms-not-recorded | Vantage Data Centers | e484e8d2bb91130eeed43a4bec5ca1c353ca045da4f07c3e75887f35dbde7d26Factual source record; not the publisher page |
Cite this site
Kyars, K. (2026). Vantage Data Centers Johor campus (JHB1), Sedenak Tech Park [site vcc-site-d70371ee13abb96e26fb]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-d70371ee13abb96e26fb/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction