SoftBank Osaka Sakai AI data center

Under construction

Japan · 1 project · Last reported

Summary

SoftBank Corp. is converting part of Sharp's former LCD panel plant in Sakai, Osaka into a large AI data center, reusing the plant's land, buildings, power and cooling infrastructure. SoftBank agreed in March 2025 to buy the land and buildings for about 100 billion yen, targeting operation of an initial phase of roughly 150 MW receiving capacity in 2026 and later expansion beyond 250 MW. In 2026 SoftBank described the site as under construction and as the planned home of GPU cloud and sovereign cloud services, alongside AI server assembly and battery manufacturing.

Source record as of 2026-06-23 · Details and sources

Location

The interactive map needs JavaScript. Display anchor: 34.59600, 135.43330 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Approximate site reference; the exact facility position is unverified.

Projects (1)

SoftBank Osaka Sakai AI data center

Under construction last observed as of · Reported status

Location: Sakai, Sakai-ku, Osaka Prefecture, JP. SoftBank names Sharp's Sakai LCD plant in Sakai City; Sharp gives the plant address as 1 Takumi-cho, Sakai-ku. Coordinates are the OpenStreetMap Nominatim centroid of the Takumi-cho neighbourhood, so they approximate the plant complex rather than the exact SoftBank portion (about 60% of the plant land). SoftBank Corp.; SoftBank Corp.; Sharp Corporation

Use: Ai unspecified, Cloud

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacitymore than 150 MWPlanned · Phase · Unspecified · Initial phase (2024 MoU plan)2024-06-07Initial capacity stated in the June 2024 memorandum announcement.SoftBank Corp.
Power capacitymore than 400 MWPlanned · Campus · Unspecified2024-06-07Long-term figure from the June 2024 announcement; later SoftBank releases cite expansion beyond 250 MW instead.SoftBank Corp.
Power capacityabout 150 MWPlanned · Phase · Grid connection · Initial phase targeted for 20262025-03-14SoftBank describes this as receiving (utility intake) capacity.SoftBank Corp.; SoftBank Corp.
Power capacitymore than 250 MWPlanned · Campus · Grid connection2025-03-14Future receiving capacity. The December 2024 release says the 250 MW-class supply was expected about four years after the purchase is completed and made the purchase conditional on it.SoftBank Corp.; SoftBank Corp.
Power capacitymore than 240 MWPlanned · Campus · Unspecified2025-03-14TechCrunch's eventual figure, which differs slightly from SoftBank's own 250 MW-plus figure.TechCrunch
Power capacity140 MWPlanned · Phase · Unspecified · AX Factory AI computing infrastructure2026-05-12SoftBank's May 2026 growth strategy gives 140 MW as the power assumed for the AI computing infrastructure under development at Sakai.SoftBank Corp. (SoftBank News)
Investmentabout 100,000,000,000 JPYAnnounced · Campus2025-03-14Purchase price for the plant land and buildings only; no total build cost has been published by SoftBank.SoftBank Corp.; SoftBank Corp.; TechCrunch
Land areaabout 44 hectaresPlanned · Campus2024-06-07Reported as about 440,000 square meters, roughly 60% of the plant land, in the 2024 memorandum announcement.SoftBank Corp.
Land areaabout 45 hectaresAcquired · Campus2025-03-14Reported as about 450,000 square meters in the purchase releases.SoftBank Corp.; SoftBank Corp.
Floor areaabout 840,000 sq_mPlanned · Campus2025-03-14Total floor area of the existing plant buildings being acquired; the 2024 memorandum release gave about 750,000.SoftBank Corp.; SoftBank Corp.

Companies and organizations

NameRoleNotesSources
SoftBank Corp.DeveloperSoftBank Corp.; SoftBank Corp.; SoftBank Corp. (SoftBank News)
SoftBank Corp.OwnerSigned a purchase agreement with Sharp Corporation in March 2025 for the land and buildings; Sharp was the seller.SoftBank Corp.; TechCrunch
OpenAITenantTechCrunch cited a Nikkei report that OpenAI intends to use GPUs at the Sakai site to develop models for Japan; OpenAI declined to comment, SoftBank did not confirm, and SoftBank's releases do not name OpenAI as a tenant.TechCrunch

Timeline

DateEventActual or plannedNotesSources
2024-06-07AnnouncedActualMemorandum of understanding with Sharp announced.SoftBank Corp.
2024-12-20OtherActualSoftBank board conditionally approved acquiring the land and buildings.SoftBank Corp.
2025-03-14Site acquiredActualPurchase and sale agreement signed with Sharp; the date of final closing was not found.SoftBank Corp.; TechCrunch
2026First operationalPlannedTarget for the initial roughly 150 MW phase in the December 2024 and March 2025 releases. No 2026 source found confirms that operation has begun.SoftBank Corp.; SoftBank Corp.
2025First operationalPlannedOriginal June 2024 target for full-scale operation; later releases moved the target to 2026.SoftBank Corp.
Sources for these details
Companies
  • Developer: SoftBank Corp. (unknown scope) evidence
  • Developer: SoftBank Corp. (unknown scope) evidence
  • Developer: SoftBank Corp. (unknown scope) evidence
  • Owner: SoftBank Corp. (unknown scope) evidence
  • Owner: SoftBank Corp. (unknown scope) evidence
  • Tenant: OpenAI (unknown scope) evidence
Source and location review
Status source
SoftBank Corp.'s 40th Annual General Meeting of Shareholders: Building on Telecommunications Foundation to Unlock Potential of AI evidence row
SoftBank Corp. (SoftBank News) · published 2026-06-23 · Company disclosure
Locator
Approximate site reference · Compiled location reference · approximate_site evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 126 days before the data update on 2026-10-27

Location details
Coordinates
34.59600, 135.43330
Geometry licence
source-terms-not-recorded
Use scope
Approximate site reference
Scope class
approximate_site
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
SoftBank names Sharp's Sakai LCD plant in Sakai City; Sharp gives the plant address as 1 Takumi-cho, Sakai-ku. Coordinates are the OpenStreetMap Nominatim centroid of the Takumi-cho neighbourhood, so they approximate the plant complex rather than the exact SoftBank portion (about 60% of the plant land).
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
91c22675

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for SoftBank Osaka Sakai AI data center
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Activating AI for Society: SoftBank Corp.'s New Growth Strategy to Continuously Achieve Record-High Profits
Archived copy
SoftBank Corp. (SoftBank News)
Company disclosure
Imported: Record, Metric: Power Capacitysource-terms-not-recordedSoftBank Corp. (SoftBank News)0191950acc0a6bfe31aaa8c353e61ed1296bc046e270b6d0131142e592faf5bb
Factual source record; not the publisher page
AIデータセンターの構築に向けて、シャープ堺工場の土地や建物の取得に関する契約を締結
Archived copy
SoftBank Corp.
Company disclosure
Imported: Geometry, Imported: Record, Metric: Floor Area, Metric: Investment, Metric: Land Area, Metric: Power Capacity, Milestone: First Operational, Milestone: Site Acquired, Role: Developer, Owner claimsource-terms-not-recordedSoftBank Corp.db7f177db0c20804081c18bffa152fb94b4b147e962181a086ec85ab89e3d834
Factual source record; not the publisher page
New LCD Panel Plant under Construction in Sakai City to Start Operations in October 2009
Archived copy
Sharp Corporation
Company disclosure
Imported: Geometry, Imported: Recordsource-terms-not-recordedSharp Corporation948748fd38a0fd7da6f35a1f4fbeed7b577831f3e3428cdcef8f0cc0188c1670
Factual source record; not the publisher page
Resolution on acquisition of land and buildings at Sharp's Sakai Plant for an AI data center (Japanese)
Archived copy
SoftBank Corp.
Company disclosure
Imported: Record, Metric: Floor Area, Metric: Investment, Metric: Land Area, Metric: Power Capacity, Milestone: First Operational, Milestone: Othersource-terms-not-recordedSoftBank Corp.eae25e7fc3f0f5bbb8e950ad72a7896a9e2e75db50f4a225e5fa61963fbbd262
Factual source record; not the publisher page
SoftBank buys $676M old Sharp plant for its OpenAI collab in Japan
Archived copy
TechCrunch
News
Imported: Record, Metric: Investment, Metric: Power Capacity, Milestone: Site Acquired, Owner claim, Tenant claimsource-terms-not-recordedTechCrunch27b7828bbc67c7556285b7045ae7d81e56dc7a8792d1be0d0f57f90dfa9f8def
Factual source record; not the publisher page
SoftBank Corp. to Construct Large-scale AI Data Center that Utilizes Sharp Sakai Plant
Archived copy
SoftBank Corp.
Company disclosure
Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Milestone: Announced, Milestone: First Operational, Role: Developersource-terms-not-recordedSoftBank Corp.a027311fb996964d648166061c9f395937571df0bac3f941a093fea7269f4dae
Factual source record; not the publisher page
SoftBank Corp.'s 40th Annual General Meeting of Shareholders: Building on Telecommunications Foundation to Unlock Potential of AI
Archived copy
SoftBank Corp. (SoftBank News)
Company disclosure
Imported: Record, Imported: Status, Role: Developersource-terms-not-recordedSoftBank Corp. (SoftBank News)8a1fca6db32be607c2e20217307f19256858b311e3aabb645eff29d4ccd23519
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). SoftBank Osaka Sakai AI data center [site vcc-site-d9155165962c78be00da]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-d9155165962c78be00da/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction