Start Campus Sines Data Campus
Partially operational Under construction
Portugal · 2 projects · Last reported
Summary
Start Campus SIN02 Current Facility Build
Start Campus states that construction and development activities are fully underway on the named SIN02 data centre at its SINES Data Campus. evidence
Start Campus · published 2026-06-23
Start Campus SINES data center campus
Start Campus is building a six-building data center campus in Sines, Portugal, on a site with a decommissioned power plant, using seawater cooling. Grid power secured from REN gives the campus about 1.2 GW of IT capacity. The first building (SIN01) is in service and full; the much larger second building (SIN02) is under construction and is to be fully occupied by Nscale, which is deploying Nvidia systems for Microsoft. The full campus is targeted around 2030-2031.
Source record as of 2026-08-03 · Details and sources
Start Campus's release of 21 October 2026 describes a digital-twin pilot focused on Nscale's operations within the SIN01 data center on the 1.2 GW SINES Data Campus, presented as a live AI factory environment. This confirms that the first building, SIN01, is operating on that date while the rest of the campus remains under development, so the campus stays partially operational. It says nothing about the capacity in service, SIN02 progress or the forecast deployment of more than 66,000 NVIDIA Rubin GPUs. evidence
Start Campus · published 2026-10-21
Location
The interactive map needs JavaScript. Display anchor: 37.93843, -8.80555 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Campus reference; individual project footprints are not mapped.
Projects (2)
Start Campus SIN02 Current Facility Build
Under construction last observed as of · Authoritative status update
Source and location review
- Status source
- Start Campus SIN02 construction and development fully underway evidence row
Start Campus · published 2026-06-23 · Company disclosure - Locator
- Campus locator · Official source · official_shared_multi_phase_area_centroid_as_campus_locator evidence
- Source checks
Not reviewed against imagery not_
reviewed_ for_ core_ preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 126 days before the data update on 2026-10-27
Start Campus SINES data center campus
Partially operational last observed as of · Authoritative status update
This record reports partially operational as of 2026-08-03. Start Campus; Capacity
Location: Sines, Setúbal District, PT. Nominatim (OpenStreetMap) geocode of the industrial land-use area tagged Start Campus in Sines; sources name the campus in Sines but give no street address. Start Campus; Capacity
Use: Colocation, Cloud, Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 1,200 MW | Planned · Campus · It load | 2024-08-15 | Secured IT capacity after REN raised the grid allocation from an initial 495 MW (per the company site). | Start Campus; Data Center Frontier |
| Power capacity | 37.5 MW | Operational · Phase · Unspecified · SIN01 | 2026-08-03 | Earlier reports gave 14 MW expanding to 26 MW (2024) and 31 MW (January 2026) for this building. | Start Campus; Capacity |
| Power capacity | about 180 MW | Planned · Phase · It load · SIN02 | 2026-01-13 | Lusa reported about 180 MW of IT load for the second building before its construction began. | Executive Digest (Lusa) |
| Power capacity | 180–240 MW | Under construction · Phase · It load · SIN02 | 2026-08-03 | The article body gives 180-240 MW of IT capacity; its introduction says 180-200 MW and the first suite for Nscale is described as 200 MW. | Capacity |
| Power capacity | 200 MW | Planned · Phase · Unspecified · SIN02 | 2026-10-09 | Company site lists SIN02 as the next planned facility at 200 MW; the page is undated, so as_of is the access date. | Start Campus |
| Investment | about 8,500,000,000 EUR | Announced · Campus | 2026-01-13 | Total for the six-building campus. | Data Center Frontier; Executive Digest (Lusa) |
| Investment | 10,000,000,000 USD | Announced · Campus | 2025-11-11 | Microsoft's announced AI infrastructure spend tied to the Sines campus; separate from and not additive with the developer's figure. | Start Campus; Portal ERP |
| Investment | 465,000,000 EUR | Reported · Phase · SIN02 | 2026-05-05 | Amount the article says is earmarked for SIN02 development, alongside about EUR 230 million that Nscale plans for shared infrastructure; the article does not clearly name who spends the EUR 465 million. | Portal ERP |
| Accelerators | more than 12,600 count | Installed · Phase · SIN01 | 2026-05-05 | Start Campus; Data Center Knowledge (Bloomberg); Portal ERP | |
| Accelerators | about 66,000 count | Planned · Phase · SIN02 | 2026-08-03 | Start Campus; Capacity; Portal ERP | |
| Buildings | 6 count | Planned · Campus | 2026-03-02 | Essential Business; Executive Digest (Lusa) | |
| Jobs construction | about 1,500 count | Planned · Phase · SIN02 | 2026-01-13 | Typical workforce; peaks of about 2,500 expected. | Executive Digest (Lusa) |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Start Campus | Developer | Start Campus; Data Center Frontier | |
| Start Campus | Operator | Start Campus | |
| Davidson Kempner | Owner | Reported as majority owner of the campus; it and Pioneer Point fund the project through private equity vehicles. | Data Center Knowledge (Bloomberg); Executive Digest (Lusa) |
| Pioneer Point Partners | Investor | Data Center Knowledge (Bloomberg); Executive Digest (Lusa) | |
| Nscale | Tenant | Direct customer and build partner for SIN02; also deployed GPUs for Microsoft in SIN01. | Start Campus; Capacity; Portal ERP |
| Microsoft | Tenant | Rents capacity through Nscale; reported to occupy part of SIN01 and all of SIN02. | Data Center Knowledge (Bloomberg); Essential Business; Portal ERP |
| NVIDIA | Hardware supplier | Start Campus; Capacity | |
| REN | Utility | Portuguese transmission operator that awarded the additional grid power. | Start Campus; Data Center Frontier |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2024-08-08 | Other | Actual | REN awarded additional grid power, lifting secured IT capacity to 1.2 GW. | Start Campus; Data Center Frontier |
| 2024-Q4 | First operational | Actual | SIN01 reported operational at the end of 2024; the company lists its inauguration on 2025-04-04. | Capacity |
| 2025-04-04 | Other | Actual | Official inauguration of SIN01. | Start Campus |
| 2025-10-14 | Other | Actual | Microsoft agreed to rent Nscale GPU capacity at the campus. | Data Center Knowledge (Bloomberg) |
| 2026-Q1 | Construction started | Actual | Start of SIN02 construction; preparatory works had run since late 2025. | Essential Business; Executive Digest (Lusa) |
| 2027-Q4 | Other | Planned | Delivery of a first 200 MW SIN02 suite to Nscale; Lusa reported first SIN02 clients expected by mid-2027. | Capacity; Executive Digest (Lusa) |
| 2030 | Fully operational | Planned | 2024 target for all buildings; a 2026 report gives 2031 for project completion. | Data Center Frontier |
| 2031 | Fully operational | Planned | Essential Business |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Grid connection secured from REN; the second-building works include a high-voltage substation and a 400/150 kV substation north of the campus. The company says the site uses 100% renewable energy and has an agreement with EDP on new renewable capacity. | Start Campus; Capacity; Executive Digest (Lusa) |
SIN01 capacity figures differ across sources (14-26 MW in 2024, 31 MW in January 2026, 37.5 MW in 2026). Microsoft's USD 10 billion pledge and the developer's EUR 8.5 billion estimate describe different spenders and should not be summed.
Sources for these details
- SINES Data Campus — Start Campus; publication date not stated
- Fresh Start: SINES DC Eyes Sustainable 1.2 GW IT Capacity as Europe's Largest Colocation Campus — Data Center Frontier; 2024-08-15
- Microsoft to Rent Nscale AI Data Center Capacity in Portugal — Data Center Knowledge (Bloomberg); 2025-10-14 · Archived source
- Start Campus in €2Bn deal to build Microsoft centre in Sines — Essential Business; 2026-03-02
- Data centre of the month: Start Campus SINES development in Portugal — Capacity; 2026-08-03
- Start Campus avança em fevereiro com segundo edifício do centro de dados de Sines — Executive Digest (Lusa); 2026-01-13
- Start Campus reforça posição de Portugal na infraestrutura europeia de IA com expansão em Sines — Portal ERP; 2026-05-05
- Companies
- Developer: Start Campus (unknown scope) evidence
- Developer: Start Campus (unknown scope) evidence
- Operator: Start Campus (unknown scope) evidence
- Owner: Davidson Kempner (unknown scope) evidence
- Owner: Davidson Kempner (unknown scope) evidence
- Investor: Pioneer Point Partners (unknown scope) evidence
- Investor: Pioneer Point Partners (unknown scope) evidence
- Tenant: Nscale (unknown scope) evidence
- Tenant: Nscale (unknown scope) evidence
- Tenant: Nscale (unknown scope) evidence
- Tenant: Microsoft (unknown scope) evidence
- Tenant: Microsoft (unknown scope) evidence
- Tenant: Microsoft (unknown scope) evidence
- Hardware Supplier: NVIDIA (unknown scope) evidence
- Hardware Supplier: NVIDIA (unknown scope) evidence
- Utility: REN (unknown scope) evidence
- Utility: REN (unknown scope) evidence
Source and location review
- Status source
- Start Campus press release: Schneider Electric, Aveva, Nscale and Start Campus bring the NVIDIA Omniverse DSX Blueprint into a live AI factory environment (21 October 2026) evidence row
Start Campus · published 2026-10-21 · Company disclosure - Locator
- Approximate site reference · Compiled location reference · approximate_site evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 6 days before the data update on 2026-10-27
Location details
- Coordinates
- 37.93843, -8.80555
- Geometry licence
- rights-status-uncertain-fact-extraction-only
- Use scope
- Campus locator
- Scope class
- official_shared_multi_phase_area_centroid_as_campus_locator
- Authority
- Official source
- Source entity
- Campus
- Method
- apa_sin02_06_shared_multi_phase_area_centroid_as_campus_locator
- Derivation
- official_georeferenced_drawing_shared_area_centroid_transformed_to_crs84
- Precision scope
- The point is an approximate centroid of the official shared SIN02-06 multi-phase area. It is not the SIN02 facility, an entrance, survey point, parcel, campus boundary, project footprint, building footprint, or current-work point or extent.
- Horizontal uncertainty
- 25 m
- Geometry evidence
- 26d88bed
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| APA AIA 3633 drawing 22045-EP-AMB-DES-001-01-A Archived copy | Agência Portuguesa do Ambiente (APA) Government record | Geometry | rights-status-uncertain-fact-extraction-only | Agência Portuguesa do Ambiente; Start Campus / TPF project drawing | db4ba67fd29a7ef8037d3a53e13940e772b58867e1ebf212dd27b4773f09adb6Retained source material; see source provenance | ||
| Data centre of the month: Start Campus SINES development in Portugal Archived copy | Capacity Trade publication | Imported: Geometry, Imported: Record, Imported: Status, Metric: Accelerators, Metric: Power Capacity, Milestone: First Operational, Milestone: Other, Power Source: Grid, Role: Hardware Supplier, Tenant claim | source-terms-not-recorded | Capacity | 2f465b455f52130e7d7cd93bba02338f92f36e8847825dca3269dad242b369d4Factual source record; not the publisher page | ||
| Fresh Start: SINES DC Eyes Sustainable 1.2 GW IT Capacity as Europe's Largest Colocation Campus Archived copy | Data Center Frontier Trade publication | Imported: Record, Metric: Investment, Metric: Power Capacity, Milestone: Fully Operational, Milestone: Other, Role: Developer, Role: Utility | source-terms-not-recorded | Data Center Frontier | 38be8c2b89c145a589573c5cb4c46a6e9974a6fb8bacb7b6580b8e52cc9cf290Factual source record; not the publisher page | ||
| Microsoft to Rent Nscale AI Data Center Capacity in Portugal Archived copy | Data Center Knowledge (Bloomberg) Trade publication | Imported: Record, Metric: Accelerators, Milestone: Other, Role: Investor, Owner claim, Tenant claim | source-terms-not-recorded | Data Center Knowledge (Bloomberg) | 3c138562e464cc95de7f79f65f3efe9fd1c93a02b17f538dde515039fcb1e907Factual source record; not the publisher page | ||
| SINES Data Campus Archived copy | Start Campus Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Accelerators, Metric: Investment, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Role: Developer, Role: Hardware Supplier, Operator claim, Tenant claim, Role: Utility | not stated | source-terms-not-recorded | Start Campus | a9d1fb41fd712e09ea213786a4577012a898d927360a96f5bec4ca8f16fe0312Factual source record; not the publisher page | |
| Start Campus avança em fevereiro com segundo edifício do centro de dados de Sines Archived copy | Executive Digest (Lusa) News | Imported: Record, Metric: Buildings, Metric: Investment, Metric: Jobs Construction, Metric: Power Capacity, Milestone: Construction Started, Milestone: Other, Power Source: Grid, Role: Investor, Owner claim | source-terms-not-recorded | Executive Digest (Lusa) | 63ccd20ced3e5c7fe65f59807e580494a078a838c305c28a7ff089a8cece5d2eFactual source record; not the publisher page | ||
| Start Campus in €2Bn deal to build Microsoft centre in Sines Archived copy | Essential Business News | Imported: Record, Metric: Buildings, Milestone: Construction Started, Milestone: Fully Operational, Tenant claim | source-terms-not-recorded | Essential Business | 07ee1678d5d0d96b46a8ca82b074ebb715eb66fe3b2b6881caab0f8eccad75acFactual source record; not the publisher page | ||
| Start Campus press release: Schneider Electric, Aveva, Nscale and Start Campus bring the NVIDIA Omniverse DSX Blueprint into a live AI factory environment (21 October 2026) Archived copy | Start Campus Company disclosure | Physical status | all-rights-reserved | Start Campus | 9c4417fda715cd6d16142fcd023c71fffa949dfce034c6a751e0a50b83a0c4ebRetained source material; see source provenance | ||
| Start Campus reforça posição de Portugal na infraestrutura europeia de IA com expansão em Sines Archived copy | Portal ERP Trade publication | Imported: Record, Metric: Accelerators, Metric: Investment, Tenant claim | source-terms-not-recorded | Portal ERP | e4136651b29d8c1e2375171a964cf70aebda9fca3af8b12081e48d3cdfb6d9edFactual source record; not the publisher page | ||
| Start Campus SIN02 construction and development fully underway Archived copy | Start Campus Company disclosure | Source location context, Physical status | all-rights-reserved | Start Campus | 1ea2692bbc2c76ffea74743dc44c64559b7dc95527a3500572158f97174c3d89Retained source material; see source provenance |
Cite this site
Kyars, K. (2026). Start Campus Sines Data Campus [site vcc-site-fdb92bb99c36b43e6162]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-fdb92bb99c36b43e6162/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction