Start Campus Sines Data Campus

Partially operational Under construction

Portugal · 2 projects · Last reported

Summary

Start Campus SIN02 Current Facility Build

Start Campus states that construction and development activities are fully underway on the named SIN02 data centre at its SINES Data Campus. evidence

Start Campus · published 2026-06-23

Start Campus SINES data center campus

Start Campus is building a six-building data center campus in Sines, Portugal, on a site with a decommissioned power plant, using seawater cooling. Grid power secured from REN gives the campus about 1.2 GW of IT capacity. The first building (SIN01) is in service and full; the much larger second building (SIN02) is under construction and is to be fully occupied by Nscale, which is deploying Nvidia systems for Microsoft. The full campus is targeted around 2030-2031.

Source record as of 2026-08-03 · Details and sources

Start Campus's release of 21 October 2026 describes a digital-twin pilot focused on Nscale's operations within the SIN01 data center on the 1.2 GW SINES Data Campus, presented as a live AI factory environment. This confirms that the first building, SIN01, is operating on that date while the rest of the campus remains under development, so the campus stays partially operational. It says nothing about the capacity in service, SIN02 progress or the forecast deployment of more than 66,000 NVIDIA Rubin GPUs. evidence

Start Campus · published 2026-10-21

Location

The interactive map needs JavaScript. Display anchor: 37.93843, -8.80555 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (2)

Start Campus SIN02 Current Facility Build

Under construction last observed as of · Authoritative status update

Source and location review
Status source
Start Campus SIN02 construction and development fully underway evidence row
Start Campus · published 2026-06-23 · Company disclosure
Locator
Campus locator · Official source · official_shared_multi_phase_area_centroid_as_campus_locator evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 126 days before the data update on 2026-10-27

Start Campus SINES data center campus

Partially operational last observed as of · Authoritative status update

This record reports partially operational as of 2026-08-03. Start Campus; Capacity

Location: Sines, Setúbal District, PT. Nominatim (OpenStreetMap) geocode of the industrial land-use area tagged Start Campus in Sines; sources name the campus in Sines but give no street address. Start Campus; Capacity

Use: Colocation, Cloud, Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity1,200 MWPlanned · Campus · It load2024-08-15Secured IT capacity after REN raised the grid allocation from an initial 495 MW (per the company site).Start Campus; Data Center Frontier
Power capacity37.5 MWOperational · Phase · Unspecified · SIN012026-08-03Earlier reports gave 14 MW expanding to 26 MW (2024) and 31 MW (January 2026) for this building.Start Campus; Capacity
Power capacityabout 180 MWPlanned · Phase · It load · SIN022026-01-13Lusa reported about 180 MW of IT load for the second building before its construction began.Executive Digest (Lusa)
Power capacity180–240 MWUnder construction · Phase · It load · SIN022026-08-03The article body gives 180-240 MW of IT capacity; its introduction says 180-200 MW and the first suite for Nscale is described as 200 MW.Capacity
Power capacity200 MWPlanned · Phase · Unspecified · SIN022026-10-09Company site lists SIN02 as the next planned facility at 200 MW; the page is undated, so as_of is the access date.Start Campus
Investmentabout 8,500,000,000 EURAnnounced · Campus2026-01-13Total for the six-building campus.Data Center Frontier; Executive Digest (Lusa)
Investment10,000,000,000 USDAnnounced · Campus2025-11-11Microsoft's announced AI infrastructure spend tied to the Sines campus; separate from and not additive with the developer's figure.Start Campus; Portal ERP
Investment465,000,000 EURReported · Phase · SIN022026-05-05Amount the article says is earmarked for SIN02 development, alongside about EUR 230 million that Nscale plans for shared infrastructure; the article does not clearly name who spends the EUR 465 million.Portal ERP
Acceleratorsmore than 12,600 countInstalled · Phase · SIN012026-05-05Start Campus; Data Center Knowledge (Bloomberg); Portal ERP
Acceleratorsabout 66,000 countPlanned · Phase · SIN022026-08-03Start Campus; Capacity; Portal ERP
Buildings6 countPlanned · Campus2026-03-02Essential Business; Executive Digest (Lusa)
Jobs constructionabout 1,500 countPlanned · Phase · SIN022026-01-13Typical workforce; peaks of about 2,500 expected.Executive Digest (Lusa)

Companies and organizations

NameRoleNotesSources
Start CampusDeveloperStart Campus; Data Center Frontier
Start CampusOperatorStart Campus
Davidson KempnerOwnerReported as majority owner of the campus; it and Pioneer Point fund the project through private equity vehicles.Data Center Knowledge (Bloomberg); Executive Digest (Lusa)
Pioneer Point PartnersInvestorData Center Knowledge (Bloomberg); Executive Digest (Lusa)
NscaleTenantDirect customer and build partner for SIN02; also deployed GPUs for Microsoft in SIN01.Start Campus; Capacity; Portal ERP
MicrosoftTenantRents capacity through Nscale; reported to occupy part of SIN01 and all of SIN02.Data Center Knowledge (Bloomberg); Essential Business; Portal ERP
NVIDIAHardware supplierStart Campus; Capacity
RENUtilityPortuguese transmission operator that awarded the additional grid power.Start Campus; Data Center Frontier

Timeline

DateEventActual or plannedNotesSources
2024-08-08OtherActualREN awarded additional grid power, lifting secured IT capacity to 1.2 GW.Start Campus; Data Center Frontier
2024-Q4First operationalActualSIN01 reported operational at the end of 2024; the company lists its inauguration on 2025-04-04.Capacity
2025-04-04OtherActualOfficial inauguration of SIN01.Start Campus
2025-10-14OtherActualMicrosoft agreed to rent Nscale GPU capacity at the campus.Data Center Knowledge (Bloomberg)
2026-Q1Construction startedActualStart of SIN02 construction; preparatory works had run since late 2025.Essential Business; Executive Digest (Lusa)
2027-Q4OtherPlannedDelivery of a first 200 MW SIN02 suite to Nscale; Lusa reported first SIN02 clients expected by mid-2027.Capacity; Executive Digest (Lusa)
2030Fully operationalPlanned2024 target for all buildings; a 2026 report gives 2031 for project completion.Data Center Frontier
2031Fully operationalPlannedEssential Business

Power supply

TypeDescriptionSources
GridGrid connection secured from REN; the second-building works include a high-voltage substation and a 400/150 kV substation north of the campus. The company says the site uses 100% renewable energy and has an agreement with EDP on new renewable capacity.Start Campus; Capacity; Executive Digest (Lusa)

SIN01 capacity figures differ across sources (14-26 MW in 2024, 31 MW in January 2026, 37.5 MW in 2026). Microsoft's USD 10 billion pledge and the developer's EUR 8.5 billion estimate describe different spenders and should not be summed.

Sources for these details
Companies
  • Developer: Start Campus (unknown scope) evidence
  • Developer: Start Campus (unknown scope) evidence
  • Operator: Start Campus (unknown scope) evidence
  • Owner: Davidson Kempner (unknown scope) evidence
  • Owner: Davidson Kempner (unknown scope) evidence
  • Investor: Pioneer Point Partners (unknown scope) evidence
  • Investor: Pioneer Point Partners (unknown scope) evidence
  • Tenant: Nscale (unknown scope) evidence
  • Tenant: Nscale (unknown scope) evidence
  • Tenant: Nscale (unknown scope) evidence
  • Tenant: Microsoft (unknown scope) evidence
  • Tenant: Microsoft (unknown scope) evidence
  • Tenant: Microsoft (unknown scope) evidence
  • Hardware Supplier: NVIDIA (unknown scope) evidence
  • Hardware Supplier: NVIDIA (unknown scope) evidence
  • Utility: REN (unknown scope) evidence
  • Utility: REN (unknown scope) evidence
Source and location review
Status source
Start Campus press release: Schneider Electric, Aveva, Nscale and Start Campus bring the NVIDIA Omniverse DSX Blueprint into a live AI factory environment (21 October 2026) evidence row
Start Campus · published 2026-10-21 · Company disclosure
Locator
Approximate site reference · Compiled location reference · approximate_site evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 6 days before the data update on 2026-10-27

Location details
Coordinates
37.93843, -8.80555
Geometry licence
rights-status-uncertain-fact-extraction-only
Use scope
Campus locator
Scope class
official_shared_multi_phase_area_centroid_as_campus_locator
Authority
Official source
Source entity
Campus
Method
apa_sin02_06_shared_multi_phase_area_centroid_as_campus_locator
Derivation
official_georeferenced_drawing_shared_area_centroid_transformed_to_crs84
Precision scope
The point is an approximate centroid of the official shared SIN02-06 multi-phase area. It is not the SIN02 facility, an entrance, survey point, parcel, campus boundary, project footprint, building footprint, or current-work point or extent.
Horizontal uncertainty
25 m
Geometry evidence
26d88bed

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Start Campus Sines Data Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
APA AIA 3633 drawing 22045-EP-AMB-DES-001-01-A
Archived copy
Agência Portuguesa do Ambiente (APA)
Government record
Geometryrights-status-uncertain-fact-extraction-onlyAgência Portuguesa do Ambiente; Start Campus / TPF project drawingdb4ba67fd29a7ef8037d3a53e13940e772b58867e1ebf212dd27b4773f09adb6
Retained source material; see source provenance
Data centre of the month: Start Campus SINES development in Portugal
Archived copy
Capacity
Trade publication
Imported: Geometry, Imported: Record, Imported: Status, Metric: Accelerators, Metric: Power Capacity, Milestone: First Operational, Milestone: Other, Power Source: Grid, Role: Hardware Supplier, Tenant claimsource-terms-not-recordedCapacity2f465b455f52130e7d7cd93bba02338f92f36e8847825dca3269dad242b369d4
Factual source record; not the publisher page
Fresh Start: SINES DC Eyes Sustainable 1.2 GW IT Capacity as Europe's Largest Colocation Campus
Archived copy
Data Center Frontier
Trade publication
Imported: Record, Metric: Investment, Metric: Power Capacity, Milestone: Fully Operational, Milestone: Other, Role: Developer, Role: Utilitysource-terms-not-recordedData Center Frontier38be8c2b89c145a589573c5cb4c46a6e9974a6fb8bacb7b6580b8e52cc9cf290
Factual source record; not the publisher page
Microsoft to Rent Nscale AI Data Center Capacity in Portugal
Archived copy
Data Center Knowledge (Bloomberg)
Trade publication
Imported: Record, Metric: Accelerators, Milestone: Other, Role: Investor, Owner claim, Tenant claimsource-terms-not-recordedData Center Knowledge (Bloomberg)3c138562e464cc95de7f79f65f3efe9fd1c93a02b17f538dde515039fcb1e907
Factual source record; not the publisher page
SINES Data Campus
Archived copy
Start Campus
Company disclosure
Imported: Geometry, Imported: Record, Imported: Status, Metric: Accelerators, Metric: Investment, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Role: Developer, Role: Hardware Supplier, Operator claim, Tenant claim, Role: Utilitynot statedsource-terms-not-recordedStart Campusa9d1fb41fd712e09ea213786a4577012a898d927360a96f5bec4ca8f16fe0312
Factual source record; not the publisher page
Start Campus avança em fevereiro com segundo edifício do centro de dados de Sines
Archived copy
Executive Digest (Lusa)
News
Imported: Record, Metric: Buildings, Metric: Investment, Metric: Jobs Construction, Metric: Power Capacity, Milestone: Construction Started, Milestone: Other, Power Source: Grid, Role: Investor, Owner claimsource-terms-not-recordedExecutive Digest (Lusa)63ccd20ced3e5c7fe65f59807e580494a078a838c305c28a7ff089a8cece5d2e
Factual source record; not the publisher page
Start Campus in €2Bn deal to build Microsoft centre in Sines
Archived copy
Essential Business
News
Imported: Record, Metric: Buildings, Milestone: Construction Started, Milestone: Fully Operational, Tenant claimsource-terms-not-recordedEssential Business07ee1678d5d0d96b46a8ca82b074ebb715eb66fe3b2b6881caab0f8eccad75ac
Factual source record; not the publisher page
Start Campus press release: Schneider Electric, Aveva, Nscale and Start Campus bring the NVIDIA Omniverse DSX Blueprint into a live AI factory environment (21 October 2026)
Archived copy
Start Campus
Company disclosure
Physical statusall-rights-reservedStart Campus9c4417fda715cd6d16142fcd023c71fffa949dfce034c6a751e0a50b83a0c4eb
Retained source material; see source provenance
Start Campus reforça posição de Portugal na infraestrutura europeia de IA com expansão em Sines
Archived copy
Portal ERP
Trade publication
Imported: Record, Metric: Accelerators, Metric: Investment, Tenant claimsource-terms-not-recordedPortal ERPe4136651b29d8c1e2375171a964cf70aebda9fca3af8b12081e48d3cdfb6d9ed
Factual source record; not the publisher page
Start Campus SIN02 construction and development fully underway
Archived copy
Start Campus
Company disclosure
Source location context, Physical statusall-rights-reservedStart Campus1ea2692bbc2c76ffea74743dc44c64559b7dc95527a3500572158f97174c3d89
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Start Campus Sines Data Campus [site vcc-site-fdb92bb99c36b43e6162]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-fdb92bb99c36b43e6162/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction