AirTrunk JHB2
Site records
JHB2 is AirTrunk's second hyperscale campus in Malaysia, announced in February 2025 in Iskandar Puteri, Johor, and scalable to more than 270 MW on a site of over 11 hectares. It is designed for high-density AI loads with liquid cooling and a grid connection from Tenaga Nasional Berhad on an accelerated schedule, with AirTrunk providing land for a new substation. In April 2026 AirTrunk said JHB1 and JHB2 were almost fully contracted, and in July 2026 it secured US$2.325 billion of green project financing for JHB2. The cited sources give no opening date.
This record reports announced as of 2026-07-29. AirTrunk; AirTrunk
Location: Iskandar Puteri, Johor Bahru District, Johor, MY. AirTrunk names Iskandar Puteri without an address; coordinates are the OpenStreetMap Nominatim centroid of Iskandar Puteri. AirTrunk
Use: Cloud, Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | more than 270 MW | Planned · Campus · Unspecified | 2025-02-12 | AirTrunk's facility page calls this total capacity without saying whether it is IT load. AirTrunk separately gives more than 420 MW of IT load across JHB1 and JHB2 combined. | AirTrunk; AirTrunk |
| Land area | more than 11 hectares | Reported · Campus | 2026-10 | Undated facility page viewed October 2026. | AirTrunk |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| AirTrunk | Developer | AirTrunk; AirTrunk; AirTrunk; AirTrunk | |
| Tenaga Nasional Berhad | Utility | Providing the grid connection under its Green Lane Pathway; AirTrunk is providing land for a new TNB substation. | AirTrunk |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2025-02-12 | Announced | Actual | AirTrunk said the announcement brought its Malaysia investment to RM 9.7 billion, without a JHB2-specific figure. | AirTrunk |
| 2026-04-30 | Other | Actual | AirTrunk said JHB1 and JHB2 were almost 100% contracted. | AirTrunk |
| 2026-07-29 | Other | Actual | US$2.325 billion (RM 9.5 billion) green project financing from 30 lenders including IFC secured to support JHB2's development. | AirTrunk |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Grid connection from Tenaga Nasional Berhad, targeted on an accelerated 12-month timeframe. | AirTrunk |
Related projects: airtrunk jhb1 johor
Sources for these details
- AirTrunk grows Malaysia platform with second cloud and AI-ready data centre in Johor — AirTrunk; 2025-02-12
- JHB2 Johor Bahru — AirTrunk; publication date not stated
- AirTrunk doubles down in Malaysia with two new hyperscale campuses in Johor Bahru — AirTrunk; 2026-04-30
- AirTrunk secures US$2.325b green financing to support sustainable digital infrastructure growth in Malaysia — AirTrunk; 2026-07-29