AWS Madison County data center project (Canton and Ridgeland campuses)

This record covers several sites. It is not counted as an additional site or project.

Single Amazon Web Services project in Madison County, north of Jackson, announced in January 2024 as one $10 billion investment covering two campuses: one on the Madison County Mega Site near Canton and one in Ridgeland near West County Line Road. It broke ground in May 2024 and Amazon said its first section was running just over 14 months later. In April 2026 Amazon added $11 billion to expand its Madison County operations. By August 2026 five buildings were finished at Canton, while the Ridgeland campus had none complete. Entergy Mississippi supplies power.

This record reports partially operational as of 2026-08-18. Amazon; WLOX; WLBT

Location: Madison County, Mississippi, US. The record covers one project with two campuses announced together: the Canton mega site (off Highway 22 and Nissan Parkway) and the Ridgeland site (Highland Colony Parkway and West County Line Road). Because the campuses are apart, coordinates are the Madison County point from its Wikipedia article. Vicksburg Daily News (press release); Vicksburg Daily News; WLOX

Use: Cloud

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investmentat least 10,000,000,000 USDAnnounced · Phase · Initial 2024 program (both campuses)2024-01-26Described in 2024 as the largest capital investment in Mississippi history; a July 2024 report said it would be spent over 10 years.Vicksburg Daily News (press release); Vicksburg Daily News; Office of Governor Tate Reeves
Investment11,000,000,000 USDAnnounced · Phase · 2026 Madison County expansion2026-04-09Additional amount announced in April 2026 to expand existing Madison County operations; local TV tied the expansion to the Ridgeland site. Not added to the 2024 figure here.Office of Governor Tate Reeves; WLOX
Land area1,713 acresPlanned · Campus2024-07-27927 acres at the Madison County Mega Site plus 786 acres in Ridgeland.Vicksburg Daily News
Buildingsabout 16 countPlanned · Phase · Initial 2024 program (both campuses)2024-07-27The report gives a 200,000 to 300,000 sq ft range without making clear whether it is per building.Vicksburg Daily News
Jobs permanentat least 1,000 countPlanned · Phase · Initial 2024 program (both campuses)2024-01-26Vicksburg Daily News (press release); Office of Governor Tate Reeves
Jobs permanent700 countPlanned · Phase · 2026 Madison County expansion2026-04-09Office of Governor Tate Reeves
Jobs constructionat least 6,000 countPlanned · Campus2024-07-27Governor's estimate; he said the number could be more than double.Vicksburg Daily News

Companies and organizations

NameRoleNotesSources
Amazon Web ServicesDeveloperVicksburg Daily News (press release); Office of Governor Tate Reeves
Entergy MississippiUtilityThe 2026 state release credits Entergy's commitment to long-term power needs; Entergy's chief says Amazon alone covers the substation and transmission upgrade costs.Vicksburg Daily News (press release); Office of Governor Tate Reeves; WLOX
Madison CountyGovernmentAssisting with the 2026 expansion; the project runs under a fee-in-lieu tax agreement that helps repay a $215 million state loan.Office of Governor Tate Reeves; WLBT

Timeline

DateEventActual or plannedNotesSources
2024-01AnnouncedActualVicksburg Daily News (press release)
2024-05-20Construction startedActualGroundbreaking ceremony attended by the governor.Picayune Item
2025First operationalActualAmazon said in an August 2025 update that the first section was running just over 14 months after groundbreaking.Amazon
2026-04-09Expansion announcedActualOffice of Governor Tate Reeves; WLOX
2027Fully operationalPlanned2024 press estimate for completing the sites; in April 2026 an AWS executive said construction at both sites was about halfway and full operation could take another 18 to 24 months.Vicksburg Daily News; WLOX

Power supply

TypeDescriptionSources
GridGrid service from Entergy Mississippi; Entergy says Amazon alone pays for the substations and transmission upgrades serving its sites.WLOX

Sources treat Canton and Ridgeland as one Madison County project: a single 2024 investment, one groundbreaking, and one fee-in-lieu tax agreement. Status: Amazon said the first section was running by August 2025. In April 2026 an AWS executive said construction at both Canton and Ridgeland was about half done. In August 2026 the county tax dispute covered five completed Canton buildings (about 214,500 sq ft each), and Ridgeland had none finished. AWS said in April 2026 that Canton uses recycled water for cooling and Ridgeland would use water only about 30 days a year.