IREN Sweetwater hub

This record covers several sites. It is not counted as an additional site or project.

Two-site, 2 GW data center hub that IREN is developing near Sweetwater in West Texas: 1,400 MW at Sweetwater 1 on 1,700 acres and 600 MW at Sweetwater 2 on 500 acres, both with direct ERCOT connections. IREN markets the hub for AI cloud use and says it could support more than 700,000 liquid-cooled GPUs. Substation energization is targeted for 2026 at Sweetwater 1 and 2027 at Sweetwater 2. IREN reported development progressing in August 2026 but warned that changes to Texas large-load interconnection rules could delay grid connection for the Sweetwater sites.

This record reports under construction as of 2026-10-09. IREN; IREN

Location: Sweetwater, Texas, US. Coordinates of the town of Sweetwater from Wikipedia. IREN names the hub after Sweetwater but does not give addresses, and the two sites may not both be in the same county, so no county is recorded. IREN; U.S. Securities and Exchange Commission (IREN filing); Wikipedia

Use: Ai unspecified, Cloud

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity2,000 MWPlanned · Campus · Facility2026-06-30IREN states a 2,000 MW total for the hub; its 10-K lists the two sites as planned gross capacity.IREN; U.S. Securities and Exchange Commission (IREN filing)
Power capacity1,400 MWPlanned · Phase · Facility · Sweetwater 12026-06-30IREN; U.S. Securities and Exchange Commission (IREN filing)
Power capacity600 MWPlanned · Phase · Facility · Sweetwater 22026-06-30IREN; U.S. Securities and Exchange Commission (IREN filing)
Land area2,200 acresAcquired · Campus2026-06-301,700 acres at Sweetwater 1 and 500 acres at Sweetwater 2.IREN

Companies and organizations

NameRoleNotesSources
IRENDeveloperIREN; U.S. Securities and Exchange Commission (IREN filing); IREN
IRENOwnerIREN states that it develops, owns and operates its data centers, including the associated land, grid connections and substations.U.S. Securities and Exchange Commission (IREN filing)

Timeline

DateEventActual or plannedNotesSources
2026OtherPlannedTargeted substation energization at Sweetwater 1.IREN
2027OtherPlannedTargeted substation energization at Sweetwater 2.IREN

Power supply

TypeDescriptionSources
GridDirect ERCOT connection; procurement and site works were under way for a 1,400 MW 345/138 kV bulk substation and 138/34.5 kV primary substations at Sweetwater 1.IREN

Status date is the access date of IREN's undated Sweetwater page, which labels both sites as under construction. IREN's 10-K cautions that Texas interconnection rule changes and ERCOT's batch study process may delay grid connection for the Sweetwater sites.

Sources for these details