CyrusOne Bosque County data center campus (Thad Hill)

Under construction

United States · 1 project · Last reported

Summary

Hyperscale data center campus that CyrusOne is building next to Calpine's Thad Hill Energy Center in Bosque County, Texas, under a powered land agreement covering power, grid connection and land. Calpine announced a 190 MW first phase in July 2025, when the project was reported as a USD 1.2 billion investment, and added 210 MW in November 2025 for 400 MW in total. Calpine then said the facility was under construction for operation by the fourth quarter of 2026. CyrusOne's campus page now lists five buildings in two phases, with phase 1 due by the third quarter of 2027 and all phases by the fourth quarter of 2027.

Source record as of 2025-11-03 · Details and sources

Location

The interactive map needs JavaScript. Display anchor: 31.90000, -97.63000 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

County or district reference only; the facility position is not established.

Projects (1)

CyrusOne Bosque County data center campus (Thad Hill)

Under construction last observed as of · Reported status

Location: Bosque County, Texas, US. Coordinates are the Wikipedia point for Bosque County (s5). Sources place the campus next to the Thad Hill Energy Center in Bosque County but give no address; the site was not geocoded. American Public Power Association; Calpine; CyrusOne; Wikipedia

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity400 MWContracted · Campus · Unspecified2025-11-03Combined power under the two Calpine agreements.Calpine; CyrusOne
Power capacity190 MWContracted · Phase · Unspecified · Phase 12025-07-31American Public Power Association; Calpine
Power capacity210 MWContracted · Phase · Unspecified · Phase 22025-11-03Calpine
Investment1,200,000,000 USDReported · Campus2025-07-31Investment reported in July 2025, when only the 190 MW first phase had been announced; no updated figure was found after the phase 2 agreement.American Public Power Association
Floor areamore than 190,000 sq_ftUnder construction · Phase · Phase 12025-07-31American Public Power Association
Buildings5 countPlanned · Campus2026-10-09Two buildings in phase 1 and three in phase 2, per CyrusOne's undated campus page.CyrusOne

Companies and organizations

NameRoleNotesSources
CyrusOneDeveloperAmerican Public Power Association; Calpine; CyrusOne
CyrusOneOperatorDescribed as a data center developer and operator; backed by KKR and Global Infrastructure Partners.American Public Power Association; Calpine
CalpinePower supplierSupplies power under the powered land agreement at its Thad Hill Energy Center; by February 2026 Calpine was a business unit of Constellation.American Public Power Association; Calpine; CyrusOne; CyrusOne

Timeline

DateEventActual or plannedNotesSources
2025-07-30AnnouncedActualCalpine announced the 190 MW agreement; the campus was already under construction.American Public Power Association
2025-11-03Expansion announcedActualPhase 2 agreement for another 210 MW.Calpine
2026-Q4First operationalPlannedTarget given by Calpine in 2025.American Public Power Association; Calpine
2027-Q3OtherPlannedLater target for completing phase 1 on CyrusOne's campus page.CyrusOne
2027-Q4Fully operationalPlannedCyrusOne

Power supply

TypeDescriptionSources
GridPowered land agreement with Calpine at its Thad Hill Energy Center, covering power supply, grid connection and land; CyrusOne says it will pay for required transmission upgrades, and the campus is designed to respond during ERCOT grid emergencies.American Public Power Association; Calpine; CyrusOne

Status conflict: Calpine said in July and November 2025 that the facility was under construction, but CyrusOne's undated campus page (it mentions events up to June 2026) labels it in development, refers to a county review process and describes some pre-construction steps as still ahead; its delivery dates are also later than Calpine's target. Status stays at under construction from Calpine's latest statement; no 2026 source confirms any building operating. The page says operating water comes from an on-site well permitted by the Middle Trinity Groundwater Conservation District, about 250,000 gallons per building a year. CyrusOne's Freestone Energy Center campus is a separate record.

Sources for these details
Companies
  • Developer: CyrusOne (unknown scope) evidence
  • Developer: CyrusOne (unknown scope) evidence
  • Developer: CyrusOne (unknown scope) evidence
  • Operator: CyrusOne (unknown scope) evidence
  • Operator: CyrusOne (unknown scope) evidence
  • Power Supplier: Calpine (unknown scope) evidence
  • Power Supplier: Calpine (unknown scope) evidence
  • Power Supplier: Calpine (unknown scope) evidence
  • Power Supplier: Calpine (unknown scope) evidence
Source and location review
Status source
Calpine and CyrusOne Announce Phase 2 of Powered Land Agreement to Support Hyperscale Data Center at Thad Hill Energy Center in Texas evidence row
Calpine · published 2025-11-03 · Company disclosure
Locator
County or district reference only · Compiled location reference · admin2 evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 358 days before the data update on 2026-10-27

Location details
Coordinates
31.90000, -97.63000
Geometry licence
source-terms-not-recorded
Use scope
County or district reference only
Scope class
admin2
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
Coordinates are the Wikipedia point for Bosque County (s5). Sources place the campus next to the Thad Hill Energy Center in Bosque County but give no address; the site was not geocoded.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
5d8d2d25

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for CyrusOne Bosque County data center campus (Thad Hill)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Bosque County Data Center
Archived copy
CyrusOne
Company disclosure
Imported: Geometry, Imported: Record, Metric: Buildings, Milestone: Fully Operational, Milestone: Other, Power Source: Grid, Role: Developer, Role: Power Suppliernot statedsource-terms-not-recordedCyrusOnee391d51c500143affc6ec230f4a9738c071da3822d6450d857bab9434e80f9b1
Factual source record; not the publisher page
Bosque County, Texas
Archived copy
Wikipedia
Other
Imported: Geometry, Imported: Recordnot statedsource-terms-not-recordedWikipedia3d35812efdf6bf0b0c532b77c730e17369daf46795b4307321878c1e6e6f4a5d
Factual source record; not the publisher page
Calpine and CyrusOne Announce Phase 2 of Powered Land Agreement to Support Hyperscale Data Center at Thad Hill Energy Center in Texas
Archived copy
Calpine
Company disclosure
Imported: Geometry, Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Expansion Announced, Milestone: First Operational, Power Source: Grid, Role: Developer, Operator claim, Role: Power Suppliersource-terms-not-recordedCalpine59d78410f5b913a6ac2c4c22e820b70e05de7037ceb3915bacd07f1f30e43860
Factual source record; not the publisher page
Calpine Unveils 190-MW Agreement to Serve New Texas Data Center
Archived copy
American Public Power Association
Trade publication
Imported: Geometry, Imported: Record, Metric: Floor Area, Metric: Investment, Metric: Power Capacity, Milestone: Announced, Milestone: First Operational, Power Source: Grid, Role: Developer, Operator claim, Role: Power Suppliersource-terms-not-recordedAmerican Public Power Associationae438b44408c84fae1c3c87390ef2865541c973d820ea474e94df5cf5535c16c
Factual source record; not the publisher page
Constellation and CyrusOne Announce Agreement to Support New Data Center Facility at Freestone Energy Center in Texas
Archived copy
CyrusOne
Company disclosure
Imported: Record, Metric: Power Capacity, Role: Power Suppliersource-terms-not-recordedCyrusOned8be7e783fd6e0bbff3e46a1555abc5f49a55f97773ad8f03b1aa021947d375d
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). CyrusOne Bosque County data center campus (Thad Hill) [site vcc-site-119a6992bb6bb25cc011]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-119a6992bb6bb25cc011/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction