The Barn Stargate Data Center Campus
Under construction
United States · 1 project · Last reported
Summary
Related Digital is building The Barn, a 250-acre campus of three single-story buildings in Saline Township, Michigan, exclusively for Oracle, serving OpenAI under the Oracle-OpenAI Stargate expansion. Announced in October 2025 at more than 1 GW, it is described in later coverage as 1.4 GW. DTE Energy is to supply all power, alongside new battery storage paid for by the project. State regulators approved DTE's contracts for the campus in December 2025. In June 2026 the partners marked construction with all buildings under way and the first nearing completion. Walbridge is general contractor; financing mixes Related Digital and Blackstone-affiliated equity with PIMCO-anchored debt.
Source record as of 2026-08-02 · Details and sources
Oracle reports more than2000 skilled tradespeople currently building The Barn and one million craft hours reached recently. Precise anniversary/milestone day is unspecified; current construction statement is datedSeptember28. evidence
Oracle · published 2026-09-28
Location
The interactive map needs JavaScript. Display anchor: 42.12393, -83.88209 (Polygon locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Campus reference; individual project footprints are not mapped.
Projects (1)
The Barn Stargate Current Data Center Build
Under construction last observed as of · Authoritative status update
This record reports under construction as of 2026-08-02. Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire); Spectrum News
Location: Saline Township, Washtenaw County, Michigan, US. Sources place the site entrance off Michigan Avenue, and news photos show the campus from West Michigan Avenue and from Braun Road on its back side. The point lies on West Michigan Avenue in Saline Township near the line of Braun Road, derived from OpenStreetMap Nominatim road geometry; the county is named in the June 2026 release. It is not a surveyed parcel location. Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire); Spectrum News
Use: Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | more than 1,000 MW | Planned · Campus · Unspecified | 2025-10-30 | Figure given at announcement. | Related Companies |
| Power capacity | 1,400 MW | Planned · Campus · Unspecified | 2026-08-02 | Figure used in news coverage of the DTE contract approval and later construction; the articles do not say whether it is IT load or total demand. | Spectrum News; Spectrum News |
| Power capacity | about 1,400 MW | Planned · Campus · Facility | 2026-04-17 | Analyst estimate, not a company disclosure: Epoch AI's projection of total facility power. | Epoch AI |
| Investment | more than 5,000,000,000 USD | Announced · Campus | 2026-06-01 | Planned site construction spending cited by the project team; the overall project is described only as multi-billion-dollar. | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| Investment | more than 43,000,000,000 USD | Reported · Campus | 2026-08-02 | Spectrum News reported that an original $4.8 billion cost estimate had risen and the project was now valued at more than $43 billion; the article does not attribute the figure to a named source, and no company source opened here confirms it. | Spectrum News |
| Land area | about 250 acres | Planned · Campus | 2025-10-30 | Related Digital also plans to preserve more than 750 adjacent acres as open space, farmland and wetlands. | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| Buildings | 3 count | Under construction · Campus | 2026-06-01 | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) | |
| Floor area | about 550,000 sq_ft | Under construction · Phase · Each of the three buildings | 2026-06-01 | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) | |
| Jobs construction | more than 2,500 count | Planned · Campus | 2025-10-30 | Union construction jobs; more than 700 Michigan tradespeople were on site in June 2026. | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| Jobs permanent | more than 450 count | Planned · Campus | 2025-10-30 | On-site jobs; the developers also project more than 1,500 county-wide jobs. | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Related Digital | Developer | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) | |
| Related Digital | Investor | Provides equity alongside Blackstone-affiliated funds. | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| Oracle | Tenant | The campus is being developed exclusively for Oracle, and the first buildings are slated for delivery to Oracle. | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| OpenAI | Tenant | Oracle's Stargate partner; the campus is described as purpose-built for Oracle and OpenAI. | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| Walbridge | Builder | General contractor. | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| Blackstone | Investor | Equity through affiliated funds. | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| PIMCO | Investor | PIMCO-managed funds and accounts anchor the fixed-rate, long-term debt financing. | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| DTE Energy | Utility | Related Companies; Spectrum News | |
| Michigan Public Service Commission | Government | Approved DTE's energy contracts to serve the campus. | Spectrum News |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2025-10-30 | Announced | Actual | Related Companies | |
| 2025-12-18 | Other | Actual | The Michigan Public Service Commission unanimously approved DTE's energy contracts to serve the campus, reviewing them on an ex parte basis. | Spectrum News |
| 2025-Q4 | Construction started | Actual | Analyst estimate from imagery by Epoch AI, not a company disclosure; the developer had said construction would begin in early 2026 after regulatory approval. | Related Companies; Epoch AI |
| 2026-06-01 | Other | Actual | Construction celebration with the governor; all buildings under construction and the first nearing completion. | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| 2028-Q4 | Fully operational | Planned | Analyst estimate by Epoch AI, not a company date. | Epoch AI |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | DTE Energy is to supply all of the campus's electricity from existing resources under long-term contracts approved by state regulators. | Related Companies; Spectrum News; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
| Battery storage | New battery storage financed entirely by the project supplements DTE's supply. | Related Companies; Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) |
Local residents have continued to oppose the project at township and state regulator meetings. Cost figures in the record differ widely and may reflect different scopes. Epoch AI figures and dates are analyst estimates, not company disclosures.
Sources for these details
- OpenAI, Oracle and Related Digital announce Stargate data center site in Michigan — Related Companies; 2025-10-30 · Archived source
- Michigan Public Service Commission approves DTE contracts for proposed Saline Township data center — Spectrum News; 2025-12-20
- Oracle, Related Digital, Blackstone, OpenAI, Walbridge and Governor Whitmer Celebrate Construction of Stargate Campus in Saline Township — Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire); 2026-06-02 · Archived source
- PHOTOS: Construction continues on Related Digital's Saline Township data center — Spectrum News; 2026-08-02
- OpenAI Stargate: where the US sites stand — Epoch AI; 2026-04-17 · Archived source
- Companies
- Customer: OpenAI (intended) evidence
- Customer: Oracle (intended) evidence
- Developer: Related Digital (unknown scope) evidence
- Developer: Related Digital (unknown scope) evidence
- Investor: Related Digital (unknown scope) evidence
- Tenant: Oracle (unknown scope) evidence
- Tenant: Oracle (unknown scope) evidence
- Tenant: OpenAI (unknown scope) evidence
- Builder: Walbridge (unknown scope) evidence
- Builder: Walbridge (unknown scope) evidence
- Investor: Blackstone (unknown scope) evidence
- Investor: PIMCO (unknown scope) evidence
- Utility: DTE Energy (unknown scope) evidence
- Utility: DTE Energy (unknown scope) evidence
- Government: Michigan Public Service Commission (unknown scope) evidence
- Workloads
- AI (unspecified) (intended; company disclosure, as of 2026-06-01) evidence
Source and location review
- Status source
- Oracle: current construction at The Barn, September28,2026 evidence row
Oracle · published 2026-09-28 · Company disclosure - Locator
- Campus locator · Community mapped · reviewed_openstreetmap_named_website_tagged_barn_construction_site_polygon evidence
- Source checks
Imagery review: visible change, follow-up only tracked_
identity_ bound_ visible_ change_ followup_ only_ no_ construction_ claim
An imagery review bound to this project saw visible change. It is kept for follow-up only and is not used as evidence of construction. No construction, completion or progress claim is made from imagery. · no independent imagery verificationStatus age at review: 29 days before the data update on 2026-10-27
Location details
- Coordinates
- 42.12393, -83.88209
- Geometry licence
- ODbL-1.0
- Use scope
- Campus locator
- Scope class
- reviewed_openstreetmap_named_website_tagged_barn_construction_site_polygon
- Authority
- Community mapped
- Source entity
- Campus
- Method
- openstreetmap_named_website_tagged_construction_site_polygon_as_campus_locator
- Derivation
- cross_source_overlay
- Precision scope
- The frozen global-open-v3 Polygon is a contributor-mapped construction-site locator for the named Barn data-center campus, inherited by the current-build project through the explicit v14 project_targets relationship. It is not an official, cadastral, or survey boundary; a verified complete 250-acre campus extent; a building or project footprint; a construction extent; or a source of lifecycle, capacity, energy, operating-status, or imagery claims.
- Horizontal uncertainty
Not reported
OpenStreetMap does not state horizontal positional accuracy; community-mapped geometry is not a cadastral or survey product.
- Geometry evidence
- 2c1a0857
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Michigan Public Service Commission approves DTE contracts for proposed Saline Township data center Archived copy | Spectrum News News | Imported: Record, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Role: Government, Role: Utility | source-terms-not-recorded | Spectrum News | 3ac20b743ccc1b3056cea1256b9b82da9a09f14967dfb690678837a79786be9bFactual source record; not the publisher page | ||
| OpenAI Stargate: where the US sites stand Archived copy | Epoch AI Analyst report | Imported: Record, Metric: Power Capacity, Milestone: Construction Started, Milestone: Fully Operational | source-terms-not-recorded | Epoch AI | cf36d5202ce72167b03d124b9e519142b5925e48ae4571f0a9f0a14298189445Factual source record; not the publisher page | ||
| OpenAI, Oracle and Related Digital announce Stargate data center site in Michigan Archived copy | Related Companies Company disclosure | Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Floor Area, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Land Area, Metric: Power Capacity, Milestone: Announced, Milestone: Construction Started, Power Source: Battery Storage, Power Source: Grid, Role: Builder, Role: Developer, Tenant claim, Role: Utility | source-terms-not-recorded | Related Companies | 2b355251b9b0808782bbfddf549391ee64205b47cccb6166e033ae721f6e28a0Factual source record; not the publisher page | ||
| OpenStreetMap way 1528327802: The Barn Data Center Archived copy | OpenStreetMap contributors OpenStreetMap | Geometry | ODbL-1.0 | © OpenStreetMap contributors | 04f03a496617fcc7159f1762127d29f861002822d76203c2cceda97689a309e7Retained source material; see source provenance | ||
| Oracle, Related Digital, Blackstone, OpenAI, Walbridge and Governor Whitmer Celebrate Construction of Stargate Campus in Saline Township Archived copy | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Buildings, Metric: Floor Area, Metric: Investment, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Land Area, Milestone: Other, Power Source: Battery Storage, Power Source: Grid, Role: Builder, Role: Developer, Role: Investor, Tenant claim | source-terms-not-recorded | Oracle, Related Digital, Blackstone, OpenAI and Walbridge (via WebWire) | a2b265531a1b33e2cb7523d4f172cffb4969de5ec4dbaaa708748dcffd918cdfFactual source record; not the publisher page | ||
| Oracle: current construction at The Barn, September28,2026 Archived copy | Oracle Company disclosure | Physical status | all-rights-reserved | Oracle | b8b074eef24186566d2fdb50c7fff36d211ff0f0ada123157fc1cf4c474e262bRetained source material; see source provenance | ||
| PHOTOS: Construction continues on Related Digital's Saline Township data center Archived copy | Spectrum News News | Imported: Geometry, Imported: Record, Imported: Status, Metric: Investment, Metric: Power Capacity | source-terms-not-recorded | Spectrum News | 3161c6b160e251c938240be8b48c27ffd0ace84e40abadda8ae9e0ac4e0a2524Factual source record; not the publisher page | ||
| Related Digital, Blackstone, Oracle, OpenAI, Walbridge and Governor Whitmer celebrate construction of Stargate campus in Saline Township Archived copy | Related Digital Company disclosure | Physical status, Customer claim, Workload, Intended workload | all-rights-reserved | Related Digital | a887982bd207937237fb61986c2343680ff963c9826660a5ca37e649347b2bdaRetained source material; see source provenance |