Project Bedrock Data Center (Carmen Avenue, Inver Grove Heights)

Permitted

United States · 1 project · Last reported

Summary

On 28 September 2026 the Inver Grove Heights City Council adopted Resolution 2026-209 (4-1), approving a Major Site Plan for a 54,070 sq ft data-center building at 5890 Carmen Avenue (PID 20-74900-01-010, Lot 1, Block 1, Taylor Addition; 13.9 acres zoned I-1, where a data center is a permitted use). The approved development is 5 MW at full build-out with a 3 MW initial phase and closed-loop cooling. Conditions require a Site Improvement Performance Agreement before site work, a building permit before building construction, compliance with the declaration of covenants and restrictions, and separate storm systems on any future subdivision. No building permit, site work, construction, completion or operation is established. evidence

City of Inver Grove Heights, Minnesota · published 2026-10-08

Location

The interactive map needs JavaScript. Display anchor: 44.86266, -93.03799 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Project Bedrock — 54,070 sq ft data center building (Major Site Plan, Resolution 2026-209, 5890 Carmen Avenue)

Permitted last observed as of · Development consent

Item 7C's request for council action asks the council to adopt a resolution approving a Major Site Plan Review to construct a data center at 5890 Carmen Avenue and to approve the Site Improvement Performance Agreement, as recommended by the Planning Commission after its 7 April 2026 public hearing. The draft resolution identifies the subject property as PID 20-74900-01-010, Lot 1, Block 1, Taylor Addition, zoned I-1 and guided Industrial Office Park, and approves a 54,070 sq ft data-center building subject to four conditions. The attached site development plans are titled 'Project Bedrock, 5842 Carmen Ave E.'; the site improvement agreement names Qlevr, LLC (a Florida limited liability company) as developer constructing the 54,070 sq ft 'Project Bedrock' data center and FIG Ion Timber, LLC as owner of the 13.9-acre parcel. The ALTA/NSPS survey sheet lists T5 Data Centers, LLC among its certification parties without stating a project role. Item 7D proposes the moratorium study plan, which records that the interim ordinance was revised on 14 September 2026 to exclude this 54,070 sq ft Carmen Avenue proposal. evidence

City of Inver Grove Heights, Minnesota · published 2026-09-24

The draft minutes of 12 October 2026 record consent-agenda approval (5-0) of the minutes of the 28 September 2026 meeting and the hiring of a consultant for the data-center moratorium study. The 26 October agenda contains no item on the Carmen Avenue data center (no development contract, permit, appeal or reconsideration). evidence

City of Inver Grove Heights, Minnesota · published 2026-10-22

The city's running update page states that at the 28 September 2026 meeting the City Council approved the major site application for the proposed data center project and began the data-center moratorium study, and that on 12 October it hired a consultant for that study. Earlier recaps record that the project at 5842 Carmen Avenue East was removed from the one-year moratorium by an ordinance read a third time on 14 September 2026, that after site-plan approval the developer needs a development contract and a city building permit, that the residents' EAW petition was found exempt on 27 July 2026, and that the developer had sued the city over the moratorium. evidence

City of Inver Grove Heights, Minnesota · publication date not stated

The city explains that the developer's lawsuit over the moratorium had been served, that the moratorium amendment would exempt only the current data-center application as proposed (a larger or amended application would be denied under the moratorium), that the statutory decision deadline was 4 October 2026, and that the developer receives no city or state financial assistance. evidence

City of Inver Grove Heights, Minnesota · publication date not stated

The EQB Monitor lists 'Inver Grove Heights Data Center' (Inver Grove Heights, Dakota County; process Petition; step Petition exempt from review): on 28 July 2026 EQB received notice from the City of Inver Grove Heights, the responsible governmental unit, that the petition will not be considered under Minn. R. 4410.4600 subp. 2 E. evidence

Minnesota Environmental Quality Board · published 2026-08-04

Companies
  • Owner: FIG Ion Timber, LLC (current) evidence
Source and location review
Status source
Inver Grove Heights City Council regular meeting of 12 October 2026: agenda packet, including the minutes of the 28 September 2026 meeting evidence row
City of Inver Grove Heights, Minnesota · published 2026-10-08 · Government record
Locator
Campus locator · Official source · official_tax_parcel_centroid evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 29 days before the data update on 2026-10-27

Location details
Coordinates
44.86266, -93.03799
Geometry licence
public-record-source-terms
Use scope
Campus locator
Scope class
official_tax_parcel_centroid
Authority
Official source
Source entity
Campus
Method
official_county_cadastral_parcel_centroid
Derivation
direct_geometry
Precision scope
Planar centroid of Dakota County tax parcel 20-74900-01-010 (13.90 geodesic acres, about 284 by 243 m), the single parcel named in Resolution 2026-209. It locates the whole data-centre site, not the building footprint or the works extent.
Horizontal uncertainty
Not reported

The county publishes no positional accuracy for its parcel polygons; the centroid represents a 13.9-acre parcel.

Geometry evidence
f85bb7d6

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Project Bedrock Data Center (Carmen Avenue, Inver Grove Heights)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
City of Inver Grove Heights News Flash: Data Center Information (running updates through the 12 October 2026 meeting recap)
Archived copy
City of Inver Grove Heights, Minnesota
Government record
Site and project identitynot statedpublic-record-source-termsCity of Inver Grove Heights, Minnesotae8d8f578e74369331f369bcfc285a6ffb6c4fac187ea12feaba8120b28e7dde6
Retained source material; see source provenance
City of Inver Grove Heights: Frequently Asked Questions on Proposed Data Center Project, updated for the 14 September 2026 City Council regular meeting
Archived copy
City of Inver Grove Heights, Minnesota
Government record
Site and project identitynot statedpublic-record-source-termsCity of Inver Grove Heights, Minnesota2214380f27db0e58992b6a477f05fcd55be9cc4b696d7b2b8fbba69800faa952
Retained source material; see source provenance
Dakota County tax parcel 037-207490001010 (20-74900-01-010), 5842 Carmen Ave, Inver Grove Heights (Taylor Addition)
Archived copy
Dakota County, Minnesota (Office of GIS)
Government record
Geometry, Owner claimnot statedpublic-record-source-termsDakota County, Minnesota8f9a4595c4083fab361fca053c6ef2f5853050439e6b0994334d48db638dd56a
Retained source material; see source provenance
EQB Monitor, Volume 50, Number 31 (4 August 2026): Inver Grove Heights Data Center petition notice
Archived copy
Minnesota Environmental Quality Board
Government record
Site and project identitypublic-record-source-termsMinnesota Environmental Quality Board40e762ee62872aadb603a508141d48947f410e6a2cc5389929725f3884d098f0
Retained source material; see source provenance
Inver Grove Heights City Council regular meeting of 12 October 2026: agenda packet, including the minutes of the 28 September 2026 meeting
Archived copy
City of Inver Grove Heights, Minnesota
Government record
Development consentpublic-record-source-termsCity of Inver Grove Heights, Minnesotae870b791ea81216715cde4a0229d63e361223e72d10d7182dbefefc69cf3643f
Retained source material; see source provenance
Inver Grove Heights City Council regular meeting of 26 October 2026: agenda packet, including the minutes of the 12 October 2026 meeting
Archived copy
City of Inver Grove Heights, Minnesota
Government record
Site and project identitypublic-record-source-termsCity of Inver Grove Heights, Minnesotae5b552e7587f2386b11f205ea7c77f3f9f6865c59e71abd084e3b83765af4f28
Retained source material; see source provenance
Inver Grove Heights City Council regular meeting of 28 September 2026: agenda packet (item 7C, Major Site Plan Review for a data center at 5890 Carmen Avenue)
Archived copy
City of Inver Grove Heights, Minnesota
Government record
Site and project identitypublic-record-source-termsCity of Inver Grove Heights, Minnesota0cb30f23bec506365b1aa5282bc606636dcf8dbb4ff3ba6177f996e6984d4155
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Project Bedrock Data Center (Carmen Avenue, Inver Grove Heights) [site vcc-site-2f87e5bd268fd4e684db]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-2f87e5bd268fd4e684db/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction