Colovore RNO01 Data Center Campus
Operational Under construction
United States · 2 projects · Last reported
Summary
Colovore RNO01 — first data center
Colovore's release of 9 September 2026 says it has officially opened the first liquid-cooled AI data center on its RNO01 campus in Sparks, Nevada (Reno metro), that this data center is fully leased by customers and that it provides 6 MW of liquid-cooled infrastructure. This supports operation of the first data center on the release date. It does not establish customer load, utilisation or the opening of the campus's second data center, which the same release says is under construction with projected completion in February 2027. evidence
Colovore · published 2026-09-09
Colovore RNO01 — second data center
Colovore's release dated 9 September 2026 states that 'A second data center is under construction on the RNO01 campus with projected completion in February 2027.' This supports the second RNO01 data center being under construction on the release date. February 2027 is a forecast completion, not an observation; the building's position on the campus, capacity, start date and tenancy are not stated, and the 6 MW and 'fully leased' statements in the release apply to the first data center only. evidence
Colovore · published 2026-09-09
Location
The interactive map needs JavaScript. Display anchor: 39.53142, -119.48094 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Campus reference; individual project footprints are not mapped.
Projects (2)
Colovore RNO01 — first data center
Operational last observed as of · Authoritative status update
Storey County's notice of a possible quorum of its Board of Commissioners at the Colovore Data Center ribbon cutting, Wednesday 9 September 2026 at 11:00 a.m., at Colovore Data Center, 100 Italy Dr., McCarran, NV 89437. The clerk's certification states the notice was posted on or before 4 September 2026 at the courthouse and three fire stations. evidence
Storey County, Nevada · publication date not stated
GOED's board packet for Colovore Reno 1 LLC (summary page dated 5 August 2026; item 5 C) presents an application for the data-center sales and use tax and personal property tax abatements for a computer data center in Storey County (NAICS 518210, new application). The application form gives the proposed/actual Nevada facility address as 100 Italy Drive, McCarran, Storey County 89437, an expected new operation date of Q4 2026, USD 30 million of capital equipment, ten jobs, about USD 80 million of construction cost and a 75,000 sq ft building under a lease, and says the project is the company's first Nevada data-centre presence. The company timeline in the packet lists the groundbreaking of its first Reno facility (RNO01) and says the first Reno site (16 MW in RNO01) is fully committed ahead of delivery. The packet does not itself record a board decision. evidence
Nevada Governor’s Office of Economic Development (GOED) · publication date not stated
Colovore's Reno market page lists two Reno-area sites: RNO01, location Sparks, NV, 16 MW total in Hall 1 (8 MW) and Hall 2 (8 MW), marked sold out; and RNO02, location Reno, NV, 16 MW, pre-leasing for 2026-2027. No street address or map coordinate is given. evidence
Colovore · publication date not stated
- Companies
- Operator: Colovore (current) evidence
Source and location review
- Status source
- Colovore: Colovore completes first liquid-cooled AI data center in Reno metro area to support companies deploying high-density computing (September 9, 2026) evidence row
Colovore · published 2026-09-09 · Company disclosure - Locator
- Campus locator · Official source · official_tax_parcel_centroid evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 48 days before the data update on 2026-10-27
Colovore RNO01 — second data center
Under construction last observed as of · Authoritative status update
Colovore's Reno market page lists RNO01 (Sparks, NV) with 16 MW in Hall 1 (8 MW) and Hall 2 (8 MW), marked sold out, and RNO02 (Reno, NV) as pre-leasing. No street address, building dates or per-building status are given. evidence
Colovore · publication date not stated
- Companies
- Operator: Colovore (intended) evidence
Source and location review
- Status source
- Colovore: Colovore completes first liquid-cooled AI data center in Reno metro area to support companies deploying high-density computing (September 9, 2026) evidence row
Colovore · published 2026-09-09 · Company disclosure - Locator
- Campus locator · Official source · official_tax_parcel_centroid evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 48 days before the data update on 2026-10-27
Location details
- Coordinates
- 39.53142, -119.48094
- Geometry licence
- no-open-redistribution-license-asserted
- Use scope
- Campus locator
- Scope class
- official_tax_parcel_centroid
- Authority
- Official source
- Source entity
- Campus
- Method
- official_statewide_parcel_service_parcel_centroid_of_application_facility_address
- Derivation
- direct_geometry
- Precision scope
- Centroid of the Storey County parcel at situs 100 Italy Dr (listed APN 509110, 7.73 geodesic acres, about 226 by 249 m) in the Nevada statewide parcel layer compiled to 31 December 2018 (county source date 9 July 2018). It locates the RNO01 property named by Colovore Reno 1 LLC's facility address, not either data-center building, a surveyed boundary or the works extent; the parcel may have been re-platted since 2018.
- Horizontal uncertainty
Not reported
The statewide layer publishes no positional accuracy and the parcel is a 2018 snapshot; the centroid represents a property of about 226 by 249 m whose buildings are not separately located.
- Geometry evidence
- 59c2f205
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Colovore: Colovore completes first liquid-cooled AI data center in Reno metro area to support companies deploying high-density computing (September 9, 2026) Archived copy | Colovore Company disclosure | Physical status, Operator claim | all-rights-reserved | Colovore | 1a3045b420e70b3adb04e568550e202b9934ab168f901cdc455d0c1e66e74fb9Retained source material; see source provenance | ||
| Colovore: Reno market page (RNO01 Sparks and RNO02 Reno) Archived copy | Colovore Company disclosure | Site and project identity | not stated | all-rights-reserved | Colovore | 2c73b13e1f37c8b1d1746bc6da4bff2caf7a807bd0ad76be196a6e4399628dfdRetained source material; see source provenance | |
| Nevada DOT GIS, Reference/Statewide_Parcels layer 0 (All Parcels 2018-12-31): Storey County parcel at situs 100 ITALY DR Archived copy | Nevada Department of Transportation GIS (data: Nevada Division of State Lands, from county assessors) Government record | Geometry | not stated | no-open-redistribution-license-asserted | Nevada Division of State Lands; Nevada Department of Transportation GIS | ef10a60df42903a32eeef4fc099d42de6342b5a897096dd875c983e01496eb9cRetained source material; see source provenance | |
| Nevada Governor’s Office of Economic Development: 5 C. Colovore Reno 1 LLC Board Packet (data center sales and use tax and personal property tax abatements) Archived copy | Nevada Governor’s Office of Economic Development (GOED) Government record | Site and project identity | not stated | public-record-source-terms | State of Nevada, Governor’s Office of Economic Development | 49650f426cc4ca50262a0d3e93e900a68fd564809c0a6208d52cfe15ea9a6c7aRetained source material; see source provenance | |
| Storey County Board of County Commissioners: Notice of a Possible Quorum, Colovore Data Center Ribbon Cutting, Wednesday September 9, 2026, 100 Italy Dr., McCarran, NV 89437 Archived copy | Storey County, Nevada Government record | Site and project identity | not stated | public-record-source-terms | Storey County Board of County Commissioners, Nevada | 85ceac2596050278469ab37633361c336e79a288f03ec6bdb0a3e1f25c4fe06aRetained source material; see source provenance |