QTS Calatorao data center campus
Announced
Spain · 1 project · Last reported
Summary
Blackstone, through its data center company QTS, proposes a 224-hectare data center campus on industrial land beside the A-2 motorway near Calatorao in Zaragoza province, Aragon. Announced in October 2024 at up to EUR 7.5 billion and reported at 300 MW of electrical capacity at full build-out, it received a regional general-interest declaration (DIGA) in October 2024 and initial approval of its regional general-interest plan (PIGA) in August 2025. QTS describes it as a proposed development and has not published a construction schedule.
Source record as of 2025-08-27 · Details and sources
The Government of Aragón approved part of the Plan of General Interest for Proyecto Rhodes, the data-centre campus planned on 223.4 ha of industrial land beside the A-2 in Calatorao, on 28 September 2026 (published 30 September). The approval covers the planning documents, reparcelling, urbanisation and external power, water and drainage connections, which become executable. The phase 1 data-centre project of eight buildings is not approved while its integrated environmental authorisation is pending. The campus remains announced; no data-centre development consent or physical work is established. evidence
Boletín Oficial de Aragón (Gobierno de Aragón) · published 2026-09-30
Location
The interactive map needs JavaScript. Display anchor: 41.52220, -1.34640 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Town or locality reference only; the facility position is not established.
Projects (1)
QTS Calatorao data center campus
Announced last observed as of · Project announcement
This record reports announced as of 2025-08-27. elDiario.es; QTS Data Centers
Location: Calatorao, Zaragoza, Aragón, ES. Nominatim centroid of the municipality of Calatorao; sources place the site on industrial land beside the A-2 about 7 km from the town centre, without a parcel. Brainsre.news; Investment Monitor; QTS Data Centers
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Investment | up to 7,500,000,000 EUR | Announced · Campus | 2024-10-14 | Investment Monitor, citing Reuters, reported that half the site would be developed first and a further EUR 7.5 billion invested later for the remainder; that second tranche is not added here. | Brainsre.news; Investment Monitor; Merca2 |
| Power capacity | 300 MW | Planned · Campus · Unspecified | 2024-10-16 | Reported electrical capacity when fully operational; not confirmed on the QTS page. | Investment Monitor |
| Land area | 224 hectares | Planned · Campus | 2024-10-14 | Brainsre.news; Investment Monitor; Merca2; QTS Data Centers |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| QTS Data Centers | Developer | QTS Data Centers; QTS Data Centers | |
| QTS Data Centers | Operator | QTS Data Centers; QTS Data Centers | |
| Blackstone | Investor | Funds managed by Blackstone affiliates finance the project; QTS is a Blackstone portfolio company. | Brainsre.news; Investment Monitor; QTS Data Centers; QTS Data Centers |
| Gobierno de Aragón | Government | Granted the DIGA declaration and the initial PIGA approval. | Brainsre.news; elDiario.es |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2024-10-14 | Announced | Actual | Announced by Aragon's regional president. | Brainsre.news |
| 2024-10 | Other | Actual | Aragon's cabinet approved a declaration of regional general interest (DIGA), starting the planning process. | Brainsre.news; Merca2 |
| 2025-08 | Other | Actual | Initial (not final) approval of the regional general-interest plan (PIGA), published in the Boletín Oficial de Aragón in late August 2025. | elDiario.es |
Aragon cites up to 1,400 direct jobs in technology, construction and other sectors, and QTS about 1,400 direct plus up to 2,000 indirect jobs; these are not split by phase, so no jobs metric is recorded. No 2026 status update could be found; QTS's undated pages describe a proposed development worth several billion euros.
Sources for these details
- Blackstone invertirá hasta 7.500 millones en un data center en Aragón — Brainsre.news; 2024-10-14 · Archived source
- Blackstone to make $8.2bn data centre investment in Spain — Investment Monitor; 2024-10-16 · Archived source
- Aragón, la mina de oro española de los centros de datos: Microsoft, AWS, Meta y Blackstone — Merca2; 2024-10-15 · Archived source
- La explosión de los centros de datos en Aragón: entre la opacidad, el choque institucional y el riesgo de colapso — elDiario.es; 2025-08-27 · Archived source
- Calatorao data centre campus — QTS Data Centers; publication date not stated
- Campus de centros de datos de Calatorao — QTS Data Centers; publication date not stated · Archived source
- Companies
- Developer: QTS Data Centers (unknown scope) evidence
- Developer: QTS Data Centers (unknown scope) evidence
- Operator: QTS Data Centers (unknown scope) evidence
- Operator: QTS Data Centers (unknown scope) evidence
- Investor: Blackstone (unknown scope) evidence
- Investor: Blackstone (unknown scope) evidence
- Investor: Blackstone (unknown scope) evidence
- Investor: Blackstone (unknown scope) evidence
- Government: Gobierno de Aragón (unknown scope) evidence
- Government: Gobierno de Aragón (unknown scope) evidence
Source and location review
- Status source
- ORDEN VFL/1400/2026: partial definitive approval of the PIGA "Proyecto Rhodes" data-centre campus, Calatorao evidence row
Boletín Oficial de Aragón (Gobierno de Aragón) · published 2026-09-30 · Government record - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 27 days before the data update on 2026-10-27
Location details
- Coordinates
- 41.52220, -1.34640
- Geometry licence
- source-terms-not-recorded
- Use scope
- Locality reference only
- Scope class
- locality
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- Nominatim centroid of the municipality of Calatorao; sources place the site on industrial land beside the A-2 about 7 km from the town centre, without a parcel.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 1503cf45
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Aragón, la mina de oro española de los centros de datos: Microsoft, AWS, Meta y Blackstone Archived copy | Merca2 News | Imported: Record, Metric: Investment, Metric: Land Area, Milestone: Other | source-terms-not-recorded | Merca2 | e2893c6bc0ea3b1da5d22bad654b0920a0921f1f7099e9f937eeb01f7820d980Factual source record; not the publisher page | ||
| Blackstone invertirá hasta 7.500 millones en un data center en Aragón Archived copy | Brainsre.news Trade publication | Imported: Geometry, Imported: Record, Metric: Investment, Metric: Land Area, Milestone: Announced, Milestone: Other, Role: Government, Role: Investor | source-terms-not-recorded | Brainsre.news | 512ccaab5844e5f631756c99eee4584b808c9293061728b19c3b49f117ead5a5Factual source record; not the publisher page | ||
| Blackstone to make $8.2bn data centre investment in Spain Archived copy | Investment Monitor Trade publication | Imported: Geometry, Imported: Record, Metric: Investment, Metric: Land Area, Metric: Power Capacity, Role: Investor | source-terms-not-recorded | Investment Monitor | 1d5b05f5eddbb80a9414e1f0ce366722769f9148f6bd85a759f1f8f2b3aa53efFactual source record; not the publisher page | ||
| Calatorao data centre campus Archived copy | QTS Data Centers Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Land Area, Role: Developer, Role: Investor, Operator claim | not stated | source-terms-not-recorded | QTS Data Centers | 63885ea623d5e050b5bc8150d851787bb0c638549d2bc10c60bc8393a295c56eFactual source record; not the publisher page | |
| Campus de centros de datos de Calatorao Archived copy | QTS Data Centers Company disclosure | Imported: Record, Role: Developer, Role: Investor, Operator claim | not stated | source-terms-not-recorded | QTS Data Centers | 37f890869b1119e3a64e55b3ccde618ba9b8a2334308f01ef3ffc6123efc2134Factual source record; not the publisher page | |
| La explosión de los centros de datos en Aragón: entre la opacidad, el choque institucional y el riesgo de colapso Archived copy | elDiario.es News | Imported: Record, Imported: Status, Milestone: Other, Role: Government | source-terms-not-recorded | elDiario.es | e34407249b0c908201fe9fcd4e1bfd82f6aad85305bf4f1a5d2b80bb096d093bFactual source record; not the publisher page | ||
| ORDEN VFL/1400/2026: partial definitive approval of the PIGA "Proyecto Rhodes" data-centre campus, Calatorao Archived copy | Boletín Oficial de Aragón (Gobierno de Aragón) Government record | Project announcement | public-sector-information | Gobierno de Aragón, Boletín Oficial de Aragón | c31b1cf617ac05bcaca6658f2d5f8c5e0e514f4fa477bf3cafffb31fef82c898Retained source material; see source provenance |
Cite this site
Kyars, K. (2026). QTS Calatorao data center campus [site vcc-site-62511f2ff7c107b083ea]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-62511f2ff7c107b083ea/