Meta New Albany data center campus (Prometheus)

Partially operational

United States · 1 project · Last reported

Summary

Meta's campus in New Albany, Ohio, where ground was first broken in 2017, is being expanded to host Prometheus, an AI cluster that Meta says delivers more than 1 GW of compute across several buildings. Meta announced Prometheus in July 2025, and it was expected to come online in 2026. Meta planned the campus's energy needs with AEP, behind-the-meter gas plants are being built by Will-Power OH for a Meta affiliate, and Meta signed nuclear power deals in January 2026 tied to the cluster. Drone imagery reported in September 2026 indicated the southern part of the cluster was running while the northern part was not yet energized.

Source record as of 2026-09-16 · Details and sources

The City of New Albany's data-center site, in its version modified on 26 October 2026, lists Meta's New Albany campus as one of 'two active data center sites' and says that in July 2026 the City was notified about periodic noise from 'Meta's New Albany data center campus south of SR-161', reported after a temporary sound wall was removed 'as construction neared completion'; Meta's mitigation includes 'changes to current operations' and 'a temporary sound wall along Morse Road while construction continues'. This government statement, republished in the 26 October version, records Meta's New Albany campus as operating while construction continues, so the record's partially_operational status (Meta's own statement of 19 October 2026) is refreshed with this newer observation of the same status on 26 October 2026, the modification day of the captured version. It does not establish which buildings operate, completion of the remaining construction, capacity or the Prometheus cluster's own extent; operational is not claimed. evidence

City of New Albany, Ohio · published 2026-10-26

Location

The interactive map needs JavaScript. Display anchor: 40.08120, -82.80880 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Town or locality reference only; the facility position is not established.

Projects (1)

Meta New Albany data center campus (Prometheus)

Partially operational last observed as of · Authoritative status update

This record reports partially operational as of 2026-09-16. SynMax

Location: New Albany, Ohio, US. City point from OpenStreetMap Nominatim; the cited sources name New Albany but give no site address for the data center buildings. Meta Platforms; Spectrum News 1 (Associated Press)

Use: Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacitymore than 1,000 MWPlanned · Campus · Unspecified2026-10-09Meta's undated fact sheet, read 2026-10-09, describes over 1 GW of compute capacity for the Prometheus cluster; the January 2026 AP report calls it a 1 GW cluster. Neither says whether this is IT or facility load.Meta Platforms; Spectrum News 1 (Associated Press)
Power capacity480 MWPlanned · Phase · Unspecified · Prometheus South2026-09-16Analyst unit table listing six 80 MW units. IIR Energy, cited for status, lists five of six halls operational; August 2026 imagery showed five halls structurally complete.SynMax
Power capacity500 MWPlanned · Phase · Unspecified · Prometheus North2026-09-16Analyst unit table listing five 100 MW units. August 2026 drone imagery showed the five shells complete but not energized, although IIR Energy lists them as operational.SynMax
Power capacity200 MWPermitted · Phase · Onsite generation · Socrates North gas plant2025-09-19Behind-the-meter gas plant approved by the Ohio Power Siting Board for the Meta affiliate Sidecat; Williams lists a matching 200 MW Socrates South plant, for 400 MW combined.Mount Vernon News; Williams Companies
Investmentmore than 1,500,000,000 USDAnnounced · Campus2026-10-09Meta's cumulative investment figure for the New Albany data center, from its undated fact sheet.Meta Platforms
Jobs construction1,200 countReported · Campus2026-10-09Skilled trade workers on site at peak construction, from Meta's undated fact sheet.Meta Platforms
Jobs permanentmore than 300 countReported · Campus2026-10-09Meta Platforms

Companies and organizations

NameRoleNotesSources
Meta PlatformsDeveloperMeta Platforms; Spectrum News 1 (Associated Press)
American Electric Power (AEP)UtilityMeta says it planned its energy needs with AEP.Meta Platforms
Will-Power OHPower supplierBuilds and operates behind-the-meter gas plants in New Albany whose output goes to Sidecat, described as a Meta affiliate.Mount Vernon News; American Public Power Association; Williams Companies
Williams CompaniesPower supplierLists the two 200 MW Socrates gas plants in New Albany as Will-Power projects; its page does not name the customer, but Socrates North is the plant approved to serve the Meta affiliate.Williams Companies
VistraPower supplier20-year nuclear power purchase agreements announced in January 2026 as supporting Prometheus; the plants stay connected to the wider grid.Spectrum News 1 (Associated Press)
TerraPowerPower supplierAgreement to fund new Natrium reactor units, with first delivery as early as 2032; announced alongside the Prometheus deals.Spectrum News 1 (Associated Press)
OkloPower supplierAgreement to help develop a 1.2 GW power campus in Pike County, Ohio, to support Meta's data centers in the region.Spectrum News 1 (Associated Press)

Timeline

DateEventActual or plannedNotesSources
2017Construction startedActualGroundbreaking of the original New Albany campus.Meta Platforms
2025-07Expansion announcedActualMeta announced the 1 GW Prometheus cluster spanning multiple buildings.Spectrum News 1 (Associated Press)
2026-06Permit approvedActualIn late June the Ohio Power Siting Board approved a further 250 MW behind-the-meter gas plant with 116 MW of batteries (Socrates the Younger) for the Meta affiliate; the report does not name the data center it serves.American Public Power Association
2026-08-31OtherActualDrone flight indicated Prometheus South and its gas plant operating; an August 19 flight showed Prometheus North not yet energized.SynMax
2026OtherPlannedTarget for the Prometheus cluster to come online, as reported in January 2026.Spectrum News 1 (Associated Press)

Power supply

TypeDescriptionSources
GridMeta says it planned the campus's energy needs with AEP and pays the full cost of the energy used.Meta Platforms
Natural gas onsiteWilliams lists two 200 MW Will-Power gas plants in New Albany, Socrates North and South, targeting service in the third and fourth quarters of 2026; Socrates North is approved to run behind the meter for a Meta affiliate, and a further 250 MW plant was approved in June 2026. New Albany's mayor said Meta was building two gas plants on its site. Drone imagery in late August 2026 showed the Prometheus South gas plant running and the Prometheus North plant still under construction.Spectrum News 1; Mount Vernon News; American Public Power Association; Williams Companies; SynMax
Battery storageThe 250 MW Socrates the Younger gas plant approved in June 2026 includes 116 MW of battery storage.American Public Power Association
NuclearNuclear agreements with Vistra (more than 2,600 MW from existing plants and uprates), TerraPower and Oklo were announced in January 2026 in support of Prometheus; the existing plants keep supplying the grid.Spectrum News 1 (Associated Press)

Meta's fact sheet (s1) is an undated PDF; its embedded file creation date is 2026-09-02. Figures taken only from it carry the date it was read (2026-10-09).

Sources for these details
Companies
  • Developer: Meta Platforms (unknown scope) evidence
  • Developer: Meta Platforms (unknown scope) evidence
  • Utility: American Electric Power (AEP) (unknown scope) evidence
  • Power Supplier: Will-Power OH (unknown scope) evidence
  • Power Supplier: Will-Power OH (unknown scope) evidence
  • Power Supplier: Will-Power OH (unknown scope) evidence
  • Power Supplier: Williams Companies (unknown scope) evidence
  • Power Supplier: Vistra (unknown scope) evidence
  • Power Supplier: TerraPower (unknown scope) evidence
  • Power Supplier: Oklo (unknown scope) evidence
Source and location review
Status source
City of New Albany, Ohio: data-center information site home page (version modified 26 October 2026) evidence row
City of New Albany, Ohio · published 2026-10-26 · Government record
Locator
Locality reference only · Compiled location reference · locality evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 1 days before the data update on 2026-10-27

Location details
Coordinates
40.08120, -82.80880
Geometry licence
source-terms-not-recorded
Use scope
Locality reference only
Scope class
locality
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
City point from OpenStreetMap Nominatim; the cited sources name New Albany but give no site address for the data center buildings.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
f777e6f8

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Meta New Albany data center campus (Prometheus)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
City of New Albany, Ohio: data-center information site home page (version modified 26 October 2026)
Archived copy
City of New Albany, Ohio
Government record
Physical statuspublic-record-source-termsCity of New Albany, Ohioad7315984638f31e4f4ca2782ec7c97ef5f3c8049c11f247869854568c9bf4d6
Retained source material; see source provenance
Drone Imagery Confirms Meta's Prometheus South Operating, Prometheus North Still Under Construction
Archived copy
SynMax
Analyst report
Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Other, Power Source: Natural Gas Onsitesource-terms-not-recordedSynMax2023647d89426b32ad0f1e133dc9132fc1b381b2fb0a43ee4857049982120bad
Factual source record; not the publisher page
Meta lines up massive supply of nuclear power to energize AI data centers
Archived copy
Spectrum News 1 (Associated Press)
News
Imported: Geometry, Imported: Record, Metric: Power Capacity, Milestone: Expansion Announced, Milestone: Other, Power Source: Nuclear, Role: Developer, Role: Power Suppliersource-terms-not-recordedSpectrum News 1 (Associated Press)6b01477fc38b6ed1eff7e8e18a3a181e794e4767134f464df9baaf3fce448d81
Factual source record; not the publisher page
Meta New Albany Data Center fact sheet
Archived copy
Meta Platforms
Company disclosure
Imported: Geometry, Imported: Record, Metric: Investment, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Power Capacity, Milestone: Construction Started, Power Source: Grid, Role: Developer, Role: Utilitynot statedsource-terms-not-recordedMeta Platforms8f71e90507f6524299caaea994d2fe3aa53cc42854020c496c490c678f89b324
Factual source record; not the publisher page
Meta's next massive build could become the world's first gigawatt-scale data center
Archived copy
Spectrum News 1
News
Imported: Record, Power Source: Natural Gas Onsitesource-terms-not-recordedSpectrum News 1c3cb9becef2240956d0efcab35b61ffb3f4c7c3f78402b4054e5609f8cf47b9b
Factual source record; not the publisher page
Meta: New Albany - where Ohio's community spirit meets the frontier of AI
Archived copy
Meta
Company disclosure
Physical statusall-rights-reservedMeta Platforms, Inc.c65eaac3f13bf2c4072eb4cc3a7b58da5f3ec2537ecc1c011afc2297e3a460a4
Retained source material; see source provenance
Ohio approves new natural gas power plant for data center
Archived copy
Mount Vernon News
News
Imported: Record, Metric: Power Capacity, Power Source: Natural Gas Onsite, Role: Power Suppliersource-terms-not-recordedMount Vernon News923a238255fe4b832d7dd3cb69901e303f6d6c8920db48e8e62e356ee9f89c2c
Factual source record; not the publisher page
Ohio Power Siting Board Approves Construction of Power Plant to Serve Load of Adjacent Data Center
Archived copy
American Public Power Association
Trade publication
Imported: Record, Milestone: Permit Approved, Power Source: Battery Storage, Power Source: Natural Gas Onsite, Role: Power Suppliersource-terms-not-recordedAmerican Public Power Associationffbbcea90ff427ecdcd7f37d3aeaae32a9511cd2258e84d2c2b0411836fba2a7
Factual source record; not the publisher page
Socrates Power Solution Facilities
Archived copy
Williams Companies
Company disclosure
Imported: Record, Metric: Power Capacity, Power Source: Natural Gas Onsite, Role: Power Suppliernot statedsource-terms-not-recordedWilliams Companiesa486b46bfe34df0a0d23753d2188c9ec3d092f579f6dff4b2a39c21415148146
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). Meta New Albany data center campus (Prometheus) [site vcc-site-66e95eb80a122bb2ee32]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-66e95eb80a122bb2ee32/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction