Core Scientific Hunt County data center site

Announced

United States · 1 project · Last reported

Summary

Greenfield data center site in Hunt County, Texas, that Core Scientific bought in 2026 for about USD 233 million, with land and power expected to support about 430 MW of gross utility capacity on an approved ERCOT interconnection ramp schedule. In July 2026 Core Scientific listed it as an AMD site with about 110 MW leased under AMD's 15-year agreements, which cover roughly 530 MW across five Core Scientific sites, and estimated initial delivery in the first half of 2028.

Source record as of 2026-07-28 · Details and sources

Location

The interactive map needs JavaScript. Display anchor: 33.12000, -96.09000 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

County or district reference only; the facility position is not established.

Projects (1)

Core Scientific Hunt County data center site

Announced last observed as of · Reported status

Location: Hunt County, Texas, US. Core Scientific names Hunt County only. Coordinates are the Hunt County point from its Wikipedia article, not the site. Core Scientific; Core Scientific, Inc. via SEC EDGAR; Wikipedia

Use: Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacityabout 430 MWPlanned · Campus · Grid connection2026-07-28Gross utility power capacity that the related electric service agreement is expected to support, per the 10-Q; the Q1 release cites an approved ERCOT interconnection ramp schedule.Core Scientific; Core Scientific, Inc. via SEC EDGAR
Power capacityabout 110 MWContracted · Phase · Unspecified · AMD lease2026-07-28Leased capacity; the presentation does not say whether this is critical IT load. It also lists about 192 MW of further power pipeline at the site.Core Scientific
Investmentabout 233,000,000 USDReported · Campus2026-07-28Aggregate purchase price for the land and development rights, most of it allocated to development rights; not a construction budget.Core Scientific, Inc. via SEC EDGAR

Companies and organizations

NameRoleNotesSources
Core ScientificDeveloperCore Scientific; Core Scientific, Inc. via SEC EDGAR
Core ScientificOwnerCompleted the land acquisition in 2026.Core Scientific, Inc. via SEC EDGAR
AMDTenantNamed for this site only in Core Scientific's Q2 2026 earnings presentation (s3), which lists Hunt County as an AMD direct site with about 110 MW leased. The Q2 release (s4) gives the 15-year term for about 530 MW across five sites without naming them.Core Scientific; Core Scientific

Timeline

DateEventActual or plannedNotesSources
2026-05-05Site acquiredActualThe 10-Q dates completion of the land acquisition, with a related electric service agreement, to 5 May 2026; the Q1 release the next day reported the purchase of land and power as closed.Core Scientific, Inc. via SEC EDGAR; Core Scientific
2026-07-28OtherActualCore Scientific announced its AMD partnership and listed Hunt County as an AMD site with about 110 MW leased.Core Scientific; Core Scientific
2028-H1First operationalPlannedEstimated initial delivery of the AMD capacity.Core Scientific

Power supply

TypeDescriptionSources
GridGrid supply on the ERCOT system under an approved interconnection ramp schedule.Core Scientific

Status is announced because no source opened reports construction at the site; the 10-Q says Core Scientific intends to develop the land as a future data center site.

Sources for these details
Companies
  • Developer: Core Scientific (unknown scope) evidence
  • Developer: Core Scientific (unknown scope) evidence
  • Owner: Core Scientific (unknown scope) evidence
  • Tenant: AMD (unknown scope) evidence
  • Tenant: AMD (unknown scope) evidence
Source and location review
Status source
Core Scientific, Inc. quarterly report on Form 10-Q for the period ended June 30, 2026 evidence row
Core Scientific, Inc. via SEC EDGAR · published 2026-07-28 · Regulatory filing
Locator
County or district reference only · Compiled location reference · admin2 evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 91 days before the data update on 2026-10-27

Location details
Coordinates
33.12000, -96.09000
Geometry licence
source-terms-not-recorded
Use scope
County or district reference only
Scope class
admin2
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
Core Scientific names Hunt County only. Coordinates are the Hunt County point from its Wikipedia article, not the site.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
2fce484d

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Core Scientific Hunt County data center site
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Core Scientific announces first quarter fiscal year 2026 results
Archived copy
Core Scientific
Company disclosure
Imported: Geometry, Imported: Record, Metric: Power Capacity, Milestone: Site Acquired, Power Source: Grid, Role: Developersource-terms-not-recordedCore Scientific42ef3d1263fc2f39182e6f9ac03c2db8de3fd2f8d9862b6082429b74baee581d
Factual source record; not the publisher page
Core Scientific announces second quarter 2026 results
Archived copy
Core Scientific
Company disclosure
Imported: Record, Milestone: Other, Tenant claimsource-terms-not-recordedCore Scientificb97d99a2a3a4796490ac273fc28ec2d0522f582db609eb202f0e0ebada245bd7
Factual source record; not the publisher page
Core Scientific Q2 2026 earnings presentation (Form 8-K, Exhibit 99.2)
Archived copy
Core Scientific
Regulatory filing
Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: First Operational, Milestone: Other, Tenant claimsource-terms-not-recordedCore Scientific2979ca9805a0120ce59a068aaa14add9820a62c714bd19b78ecf364571f3376f
Factual source record; not the publisher page
Core Scientific, Inc. quarterly report on Form 10-Q for the period ended June 30, 2026
Archived copy
Core Scientific, Inc. via SEC EDGAR
Regulatory filing
Imported: Geometry, Imported: Record, Imported: Status, Metric: Investment, Metric: Power Capacity, Milestone: Site Acquired, Role: Developer, Owner claimsource-terms-not-recordedCore Scientific, Inc. via SEC EDGARc4846487e88cf1d5c468d06b73c2667891c63fc80c4004a71dc7391fe866fdba
Factual source record; not the publisher page
Hunt County, Texas
Archived copy
Wikipedia
Other
Imported: Geometry, Imported: Recordnot statedsource-terms-not-recordedWikipedia7e14da5e5c8a7a234b70453269b96e64b9d52fc343fb873315434be8b6a4c425
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). Core Scientific Hunt County data center site [site vcc-site-684f1565a0f48756e238]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-684f1565a0f48756e238/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction