Horizon 1 Kearney Data Center Campus (Tech One, Kearney, Nebraska)

Permitted

United States · 1 project · Last reported

Summary

On 8 September 2026 the Kearney City Council passed Ordinance No. 8823 (5-0), granting Conditional Use Permit 2026-04 to Horizon 1 Kearney Owner, LP to locate a data center on Lot 1, Tech One Third Subdivision and Lot 1, Tech One Fifth Subdivision (about 69 acres zoned BP Business Park, east of Antelope Avenue and south of Tech One Boulevard/Global Drive, around the existing cryptocurrency-mining operation). The development is described as two initial principal phases with possible further expansions and closed-loop chilled-water cooling. The same meeting approved the Tech One Fifth Subdivision plat, the BP rezoning and a Community Benefit Agreement for the project. Building permits follow the conditional use permit; no site work, construction, completion or operation of the data center is established. evidence

City of Kearney, Nebraska (City Clerk) · published 2026-09-22

Location

The interactive map needs JavaScript. Display anchor: 40.72462, -99.04200 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Horizon 1 Kearney data center — Conditional Use Permit 2026-04 (Ordinance No. 8823), Lot 1 Tech One Third and Lot 1 Tech One Fifth Subdivisions

Permitted last observed as of · Development consent

The consent agenda approved the minutes of the 8 September 2026 regular meeting (5-0). Ordinance No. 8827 authorized the warranty deed of Lot 1, Tech One Fifth Subdivision (57.64 acres), Lot 1, Block 1, Tech One First Subdivision (5.64 acres) and Lot 1, Tech One Second Subdivision (9.05 acres), part of the NW quarter of Section 29, T9N R15W, to Horizon 1 Kearney Owner LP, a Delaware limited partnership; it passed 5-0. evidence

City of Kearney, Nebraska (City Clerk) · publication date not stated

The agenda contains no item on the Horizon 1 data center, its conditional use permit, a referendum or a reconsideration; its consent agenda approves the 22 September minutes. evidence

City of Kearney, Nebraska (City Clerk) · publication date not stated

The national PLSS layer returns the section polygons for T9N R15W sections 20, 29 and 30; the NW corner of section 29 (shared with sections 20 and 30) is at -99.045742, 40.728456 and its SW corner at -99.045854, 40.713931 (west line about 5,292 ft). These corners georeference the Tech One Fifth Subdivision description. evidence

U.S. Bureau of Land Management (National PLSS CadNSDI) · publication date not stated

Companies
  • Owner: Horizon 1 Kearney Owner, LP (current) evidence
Source and location review
Status source
Kearney City Council minutes, regular meeting of 8 September 2026 (Conditional Use Permit 2026-04 for a data center, Ordinance No. 8823; Tech One Fifth Subdivision, Resolution No. 2026-99) evidence row
City of Kearney, Nebraska (City Clerk) · published 2026-09-22 · Government record
Locator
Campus locator · Compiled location reference · official_plat_description_cogo_centroid evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 49 days before the data update on 2026-10-27

Location details
Coordinates
40.72462, -99.04200
Geometry licence
public-record-source-terms
Use scope
Campus locator
Scope class
official_plat_description_cogo_centroid
Authority
Compiled location reference
Source entity
Campus
Method
metes_and_bounds_traverse_from_blm_plss_corner_centroid
Derivation
coordinate_transform
Precision scope
Area centroid of Lot 1, Tech One Fifth Subdivision (58.77 acres; about 720 by 510 m), computed from the plat's metes-and-bounds description in Resolution No. 2026-99, which closes to 0.01 ft and reproduces the stated 58.77 acres, and placed from the BLM CadNSDI northwest corner of Section 29 with the bearings rotated onto the BLM west line. It locates the larger of the two lots in the conditional-use-permit site (the adjoining Lot 1, Tech One Third Subdivision of about 11 acres holds the existing mining operation), not a building, footprint or works extent.
Horizontal uncertainty
Not reported

The BLM CadNSDI corner carries no stated positional accuracy in the query response, and the plat traverse is georeferenced from that single corner and the section west line; the centroid represents a 58.77-acre lot within a site of about 69 acres.

Geometry evidence
38138b95

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Horizon 1 Kearney Data Center Campus (Tech One, Kearney, Nebraska)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
BLM CadNSDI PLSS sections 20, 29 and 30, Township 9 North, Range 15 West, 6th Principal Meridian (NE060090N0150W0)
Archived copy
U.S. Bureau of Land Management (National PLSS CadNSDI)
Government record
Site and project identitynot statedpublic-domain-us-governmentU.S. Department of the Interior, Bureau of Land Management7cb957cfc04aa466ada9f94e9a7d68c9b41c4ca9b60063ae4d8cdc4e13cdbd8a
Retained source material; see source provenance
Kearney City Council agenda, regular meeting of 13 October 2026
Archived copy
City of Kearney, Nebraska (City Clerk)
Government record
Site and project identitynot statedpublic-record-source-termsCity of Kearney, Nebraska6034160b86ddd0d62473681bb24cc16eaf4a13c56455b58e12046941e9c9cedf
Retained source material; see source provenance
Kearney City Council minutes, regular meeting of 22 September 2026
Archived copy
City of Kearney, Nebraska (City Clerk)
Government record
Site and project identitynot statedpublic-record-source-termsCity of Kearney, Nebraska191d5c67a0d59abe6ebdfaf056e7bdfb1b0f5f3a41c4e193fc381435f90da592
Retained source material; see source provenance
Kearney City Council minutes, regular meeting of 8 September 2026 (Conditional Use Permit 2026-04 for a data center, Ordinance No. 8823; Tech One Fifth Subdivision, Resolution No. 2026-99)
Archived copy
City of Kearney, Nebraska (City Clerk)
Government record
Geometry, Development consent, Owner claimpublic-record-source-termsCity of Kearney, Nebraska8b1298f9f7a3ca2cc1a2b95f941b5d8f1e7d0b2d68b7df2431a5344a8bd220f2
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Horizon 1 Kearney Data Center Campus (Tech One, Kearney, Nebraska) [site vcc-site-6f469fef389a90fb70b5]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-6f469fef389a90fb70b5/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction