Agricultural Bank of China Horinger Data Center (Data Centre Third Branch)

Operational

China · 1 project · Last reported

Summary

On 31 August 2026 the Horinger New Area public affairs service bureau (emergency bureau) reported a safety inspection of the Agricultural Bank of China data centre as a newly put-into-production operating unit (新投产运营单位) in its initial production period, checking its fire control room, machine rooms, fire alarm linkage and gas suppression systems, emergency power and equipment-room environmental monitoring, and noting that the data centre carries the safe operation of financial business systems. The record covers the data centre's operation as of the publication date; the commissioning date, the buildings in service and any capacity are not stated, and the EIA's Phase 1 and Phase 2 building programmes and 366 MW load are planned figures that are not asserted. evidence

Public Affairs Service Bureau (Emergency Management Bureau) of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区公共事业服务局(应急局)) · published 2026-08-31

Location

The interactive map needs JavaScript. Display anchor: 40.53655, 111.79787 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Agricultural Bank of China Horinger Data Center — newly commissioned data-centre operations

Operational last observed as of · Authoritative status update

Approval decision text attached to the department's approval-result publicity of 15 March 2023 (local nmg-abc-horinger-2x110kv-20230320.html). It approves in principle two new 110 kV substations (each 2 x 63 MVA, two 110 kV incoming circuits) for the Agricultural Bank of China Horinger data centre in Horinger New Area, requires completion environmental acceptance before formal operation, and delegates construction-period supervision to the Hohhot Ecology and Environment Bureau. The published text carries no reference number or signing date. It approves ancillary grid works, not the data-centre buildings. evidence

Inner Mongolia Autonomous Region Department of Ecology and Environment · published 2023-03-15

Companies
  • Owner: Agricultural Bank of China Limited Inner Mongolia Branch (中国农业银行股份有限公司内蒙古自治区分行) (current) evidence
  • Operator: Agricultural Bank of China (中国农业银行) (current) evidence
Source and location review
Status source
Horinger New Area news item: 'Serving new projects in advance, building a safety firewall' (靠前服务新项目 筑牢安全“防火墙”), 31 August 2026 evidence row
Public Affairs Service Bureau (Emergency Management Bureau) of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区公共事业服务局(应急局)) · published 2026-08-31 · Government record
Locator
Campus locator · Compiled location reference · official_eia_on_campus_substation_locator evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 57 days before the data update on 2026-10-27

Location details
Coordinates
40.53655, 111.79787
Geometry licence
all-rights-reserved
Use scope
Campus locator
Scope class
official_eia_on_campus_substation_locator
Authority
Compiled location reference
Source entity
Campus
Method
official_eia_dms_point_inferred_gcj02_converted_to_wgs84
Derivation
coordinate_transform
Precision scope
The campus's Data 1# 110 kV substation, which the EIA places inside the data-centre campus on its south side, west of the south main gate and about 20 m north of Yungu Heng 44 Road; converted from the printed GCJ-02-frame value. Locates the campus through on-campus power infrastructure at its south edge; not a machine-room building, entrance or parcel centroid. The Phase 1 machine-room buildings lie roughly 100-300 m north-east of the point.
Horizontal uncertainty
Not reported

No datum or positional accuracy is stated; the GCJ-02 frame is inferred from the fit of the report's site plan to independent Esri imagery of unstated accuracy and date (manual visual comparison, agreement within about 30 m), and the printed value may itself have been read from a web map. The point marks a substation at the campus's south edge. Decimal places are computational precision, not accuracy.

Geometry evidence
3e1f0a7d

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Agricultural Bank of China Horinger Data Center (Data Centre Third Branch)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Environmental impact report form: Agricultural Bank of China Horinger Data Centre two 110 kV substations (Inner Mongolia Department of Ecology and Environment radiation-EIA approval-result publicity, 15 March 2023)
Archived copy
Inner Mongolia Autonomous Region Department of Ecology and Environment
Environmental assessment document
Geometry, Owner claimall-rights-reservedInner Mongolia Autonomous Region Department of Ecology and Environment; report form prepared for 中国农业银行股份有限公司内蒙古自治区分行6e3ed5a57984e82840a28dcb6420091e23373894180759646a739dd06fc6990a
Retained source material; see source provenance
Esri World Imagery EPSG:4326 export across the Agricultural Bank of China Horinger data-centre campus and its neighbours (111.785-111.813E, 40.531-40.545N)
Archived copy
Esri
Map feature
Site and project identitynot statedall-rights-reservedEsri, Maxar, Earthstar Geographics and the GIS user community (World Imagery)6deb33c87e683cfbebbe50345356a9d5e88ebb267ffcd429eb01623b1f414c0e
Retained source material; see source provenance
Horinger New Area news item: 'Serving new projects in advance, building a safety firewall' (靠前服务新项目 筑牢安全“防火墙”), 31 August 2026
Archived copy
Public Affairs Service Bureau (Emergency Management Bureau) of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区公共事业服务局(应急局))
Government record
Physical status, Operator claimall-rights-reserved自贸试验区呼和浩特片区、和林格尔新区公共事业服务局, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn)c3208158aad7854cf547ffff5eef7e4b62d6ac90cb94deaad373d7babf931c0e
Retained source material; see source provenance
Inner Mongolia Department of Ecology and Environment approval of the EIA report form for the Agricultural Bank of China Horinger Data Centre two 110 kV substations (published with the approval-result publicity of 15 March 2023)
Archived copy
Inner Mongolia Autonomous Region Department of Ecology and Environment
Government record
Site and project identityall-rights-reservedInner Mongolia Autonomous Region Department of Ecology and Environment20567bdc8abddf0ac2d820e7c6702fa3b6076855e1ea20a34667efa1c628e9be
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Agricultural Bank of China Horinger Data Center (Data Centre Third Branch) [site vcc-site-7311a9ab273caa85afc2]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-7311a9ab273caa85afc2/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction