PowerHouse Grand Prairie campus (PowerHouse and Provident)
Announced
United States · 1 project · Last reported
Summary
Hyperscale data center campus planned by a PowerHouse Data Centers and Provident Data Centers joint venture on 768 to 810 acres just outside Grand Prairie in northern Ellis County, Texas. The partners plan an on-site 1.8 GW switchyard, with a first 500 MW tranche approved through ERCOT, and 24 buildings in three phases at announcement. A state accessibility filing registered in April 2026 covers Data Center Building 1, a two-story 224,152 sq ft core and shell at 881 Miller Road with an estimated cost of about USD 72.6 million and a scheduled April 2026 to April 2028 build window.
Source record as of 2026-04-02 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: 32.50690, -97.00690 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Town or locality reference only; the facility position is not established.
Projects (1)
PowerHouse Grand Prairie campus (PowerHouse and Provident)
Announced last observed as of · Reported status
Location: Midlothian, Ellis County, Texas, US. Coordinates are the Wikipedia centroid of Midlothian (s5), the mailing city in the state filing for Building 1 at 881 Miller Road (s4). The developers describe the site as just outside Grand Prairie in northern Ellis County. The street address was not geocoded. PowerHouse Data Centers; Texas Department of Licensing and Regulation; Wikipedia
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 1,800 MW | Planned · Campus · Grid connection | 2025-02-25 | Planned on-site switchyard capacity; the campus page calls it the maximum utility power. | PowerHouse Data Centers; Dallas Innovates; PowerHouse Data Centers |
| Power capacity | 500 MW | Planned · Phase · Grid connection · First power tranche | 2025-02-25 | Described as already approved through ERCOT at announcement. | PowerHouse Data Centers; Dallas Innovates |
| Land area | 768 acres | Reported · Campus | 2025-02-25 | PowerHouse Data Centers; Dallas Innovates | |
| Land area | 810 acres | Reported · Campus | 2026-10-09 | Figure on PowerHouse's undated campus page, which is larger than the 768 acres announced in 2025. | PowerHouse Data Centers |
| Buildings | 24 count | Planned · Campus | 2025-02-25 | Planned across three phases at announcement. The later campus page instead lists four building phases (10 buildings in each of the first two, 4 in each of the last two). | PowerHouse Data Centers; Dallas Innovates |
| Floor area | about 8,500,000 sq_ft | Planned · Campus | 2026-10-09 | Developable area stated on the undated campus page. | PowerHouse Data Centers |
| Floor area | 224,152 sq_ft | Planned · Phase · Data Center Building 1 | 2026-04-02 | Texas Department of Licensing and Regulation | |
| Investment | 72,590,278 USD | Reported · Phase · Data Center Building 1 | 2026-04-02 | Estimated construction cost of the core and shell in a Texas Department of Licensing and Regulation accessibility registration; excludes fit-out and IT equipment. | Texas Department of Licensing and Regulation |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| PowerHouse Data Centers | Developer | A division of American Real Estate Partners (AREP). | PowerHouse Data Centers; Dallas Innovates; PowerHouse Data Centers |
| Provident Data Centers | Developer | Dallas-based joint venture partner; this was the first project of the partnership. | PowerHouse Data Centers; Dallas Innovates |
| Prairie Ridge Phase 1 Owner LP | Owner | Owner entity named in the April 2026 state filing for Data Center Building 1. | Texas Department of Licensing and Regulation |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2025-02-25 | Announced | Actual | The developers said the site had been rezoned and that all required approvals and permits were in hand. | PowerHouse Data Centers; Dallas Innovates |
| 2026-04-01 | Construction started | Planned | Scheduled start of Building 1 in the state filing, with completion scheduled for 1 April 2028. No report confirming work under way was found. | Texas Department of Licensing and Regulation |
| 2026-05 | First operational | Planned | Original target for energizing the first building, given at announcement. | PowerHouse Data Centers |
| 2027-Q1 | First operational | Planned | Later target on the campus page, which lists delivery in Q1 2027 alongside power delivery and construction delivery in Q4 2026. | PowerHouse Data Centers |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Planned on-site 1.8 GW switchyard on the ERCOT grid, with a first 500 MW tranche approved through ERCOT. | PowerHouse Data Centers; Dallas Innovates |
Status is kept at announced because the only 2026 evidence is a state registration with scheduled dates; no report of construction under way, energization or a tenant was found. The campus page is undated (its footer and image file names point to 2025), so its figures carry the access date. Acreage and building counts differ between the 2025 announcement and the campus page.
Sources for these details
- PowerHouse and Provident Rewrite the Data Center Playbook with New Texas Hyperscale Campus — PowerHouse Data Centers; 2025-02-25
- Dallas' Provident Data Centers, Virginia's PowerHouse Partner on 'Hyperscale' North Texas Campus — Dallas Innovates; 2025-02-25
- PowerHouse Grand Prairie — PowerHouse Data Centers; publication date not stated
- TABS2026016734: AREP Power House Grand Prairie, Data Center Building 1 — Texas Department of Licensing and Regulation; 2026-04-02
- Midlothian, Texas — Wikipedia; publication date not stated
- Companies
- Developer: PowerHouse Data Centers (unknown scope) evidence
- Developer: PowerHouse Data Centers (unknown scope) evidence
- Developer: PowerHouse Data Centers (unknown scope) evidence
- Developer: Provident Data Centers (unknown scope) evidence
- Developer: Provident Data Centers (unknown scope) evidence
- Owner: Prairie Ridge Phase 1 Owner LP (unknown scope) evidence
Source and location review
- Status source
- TABS2026016734: AREP Power House Grand Prairie, Data Center Building 1 evidence row
Texas Department of Licensing and Regulation · published 2026-04-02 · Regulatory filing - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 208 days before the data update on 2026-10-27
Location details
- Coordinates
- 32.50690, -97.00690
- Geometry licence
- source-terms-not-recorded
- Use scope
- Locality reference only
- Scope class
- locality
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- Coordinates are the Wikipedia centroid of Midlothian (s5), the mailing city in the state filing for Building 1 at 881 Miller Road (s4). The developers describe the site as just outside Grand Prairie in northern Ellis County. The street address was not geocoded.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 8199ea4f
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Dallas' Provident Data Centers, Virginia's PowerHouse Partner on 'Hyperscale' North Texas Campus Archived copy | Dallas Innovates News | Imported: Record, Metric: Buildings, Metric: Land Area, Metric: Power Capacity, Milestone: Announced, Power Source: Grid, Role: Developer | source-terms-not-recorded | Dallas Innovates | 7fa1f957c83711c2859e4157bf8cd9a5e2328392f3ab5ac1e70e609773e5a450Factual source record; not the publisher page | ||
| Midlothian, Texas Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | 262784da66f9ba25764017cb0fcbbdee5cb3613641c9f7420ecc2c8117d49520Factual source record; not the publisher page | |
| PowerHouse and Provident Rewrite the Data Center Playbook with New Texas Hyperscale Campus Archived copy | PowerHouse Data Centers Company disclosure | Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Land Area, Metric: Power Capacity, Milestone: Announced, Milestone: First Operational, Power Source: Grid, Role: Developer | source-terms-not-recorded | PowerHouse Data Centers | aa1a77f917f36199b41d608882f9f5dbc147b53e8baf90e0414832a50b99e398Factual source record; not the publisher page | ||
| PowerHouse Grand Prairie Archived copy | PowerHouse Data Centers Company disclosure | Imported: Record, Metric: Floor Area, Metric: Land Area, Metric: Power Capacity, Milestone: First Operational, Role: Developer | not stated | source-terms-not-recorded | PowerHouse Data Centers | 0fc1eca981eb87512f58620690ada1010a4aeb3725d1cbb44426b45e78e97de6Factual source record; not the publisher page | |
| TABS2026016734: AREP Power House Grand Prairie, Data Center Building 1 Archived copy | Texas Department of Licensing and Regulation Regulatory filing | Imported: Geometry, Imported: Record, Imported: Status, Metric: Floor Area, Metric: Investment, Milestone: Construction Started, Owner claim | source-terms-not-recorded | Texas Department of Licensing and Regulation | 28a939c1aff8fa36fd1e0e71d902fead1f3611751ed9184628aaa3e5437102feFactual source record; not the publisher page |
Cite this site
Kyars, K. (2026). PowerHouse Grand Prairie campus (PowerHouse and Provident) [site vcc-site-910b8939869a2f993425]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-910b8939869a2f993425/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction