Spruce Lake AI Data Centre

Announced

Canada · 1 project · Last reported

Summary

Beacon New Brunswick and VoltaGrid propose a 390 MW AI data centre with four data halls in the Spruce Lake Industrial Park, Lorneville, Saint John. It would be paired with a 190 MW on-site natural-gas plant and supplied with additional grid power. On September 15, 2026, the federal Impact Assessment Agency reported that it had received a request to designate the project for federal assessment and was analysing it. The provincial environmental review, registered in April, was still in progress at the end of September. Construction in 2026 and operation in mid-2028 are forecasts. evidence

Impact Assessment Agency of Canada · published 2026-09-15

Location

The interactive map needs JavaScript. Display anchor: 45.18371, -66.17632 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Project locator; building footprints are not mapped.

Projects (1)

Spruce Lake AI Data Centre — proposed campus and on-site generation

Announced last observed as of · Project announcement

A public request asks the federal minister to designate the project. It summarises the proposal as a 390 MW hyperscale data centre with 190 MW of behind-the-meter gas generation, two 345 kV lines drawing about 200 MW from the NB Power grid, and two 4.5 km gas laterals. The site is about 120 ha, and investment of up to $2 billion has been reported. The request says construction is expected to begin in 2026, with operation targeted for 2028, and that the provincial EIA (project 1663) is in determination review. evidence

Impact Assessment Agency of Canada (registry copy of a public request) · published 2026-08-16

The provincial registry lists project 1663, registered on April 14, 2026 by Beacon New Brunswick Inc. and VoltaGrid LLC. It describes a 390 MW data centre and a 190 MW behind-the-meter gas generation facility in the Spruce Lake Industrial Park, Saint John (Kings / Saint John counties). Its status is "Determination review in progress". The listed documents are the registration, an updated site plan and pipeline-routing addendum, and the Round 1 TRC and proponent response report. evidence

New Brunswick Department of Environment and Local Government · publication date not stated

The April 28 addendum gives measured site plans for the Data Centre PDA (the lot) at the TRC's request, and an alternative gas-pipeline route west of the data-centre facility. Lot coverage is estimated at 20.8% for power generation, data halls, data hut and substation (37.5% with ancillary areas), within the 65% maximum for the Spruce Lake Industrial zone. The data-centre site itself is not relocated. evidence

Beacon New Brunswick Inc. and VoltaGrid LLC (prepared by Stantec) · published 2026-04-28

Companies
  • Operator: Beacon New Brunswick Inc. (Beacon AI Centers) (intended) evidence
Source and location review
Status source
Canadian Impact Assessment Registry: Spruce Lake AI Data Centre Project (reference 90762) evidence row
Impact Assessment Agency of Canada · published 2026-09-15 · Government record
Locator
Project locator · Compiled location reference · mean_of_proponent_declared_onsite_stack_coordinates_in_eia_registration evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 42 days before the data update on 2026-10-27

Location details
Coordinates
45.18371, -66.17632
Geometry licence
all-rights-reserved
Use scope
Project locator
Scope class
mean_of_proponent_declared_onsite_stack_coordinates_in_eia_registration
Authority
Compiled location reference
Source entity
Campus
Method
arithmetic_mean_of_58_generator_and_boiler_stack_utm_nad83_zone19_coordinates_table_3_3_transformed_epsg26919_to_epsg4326_with_pyproj_3_7_1
Derivation
coordinate_transform
Precision scope
Mean of the 58 modelled on-site stack positions (50 gas-engine and 8 boiler stacks) inside the roughly 89 ha Data Centre Project Development Area. It locates the proposed campus, not a building footprint or surveyed boundary. The stacks lie up to 459 m from this point. The point is 198 m from IAAC's stated-approximate registry marker.
Horizontal uncertainty
Not reported

The machine-readable Data Centre PDA outline was not published; the modelled stack coordinates span up to about 459 m around the mean, and no surveyed accuracy is given.

Geometry evidence
77516a5d

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Spruce Lake AI Data Centre
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Canadian Impact Assessment Registry: Spruce Lake AI Data Centre Project (reference 90762)
Archived copy
Impact Assessment Agency of Canada
Government record
Project announcementCrown copyright; Canada.ca terms and conditionsImpact Assessment Agency of Canada5e818d883f3404453c6fe06de508c0d1f6c9b2ce85ec7810d1ec71f01bc1b32f
Retained source material; see source provenance
New Brunswick EIA registrations and determinations (1657–most recent), Internet Archive copy of 30 September 2026
Archived copy
New Brunswick Department of Environment and Local Government
Government record
Site and project identitynot statedall-rights-reservedNew Brunswick Department of Environment and Local Government; Internet Archive27ff0c6ba98206331f4e194dfe89da3293ef53c68c9545321d88d23d0167332b
Retained source material; see source provenance
Request for designation of the Spruce Lake AI Data Centre Project (IAAC registry document 1)
Archived copy
Impact Assessment Agency of Canada (registry copy of a public request)
Regulatory filing
Site and project identityCrown copyright registry copy of third-party content; Canada.ca terms and conditionsImpact Assessment Agency of Canada; requesterac50e9782a8100093618bb83a49e7e2cb74f87f15e1f228c1bebcace00e43210
Retained source material; see source provenance
Spruce Lake AI Data Centre Project — EIA Registration (NB project 1663), Internet Archive copy of 18 September 2026
Archived copy
Beacon New Brunswick Inc. and VoltaGrid LLC (prepared by Stantec), filed with NB Department of Environment and Local Government
Regulatory filing
Geometry, Operator claimall-rights-reservedBeacon New Brunswick Inc.; VoltaGrid LLC; Stantec; NB Department of Environment and Local Government; Internet Archive0eae875d14f01ffc17370e9a67accb9144a53606a18c5b9954d84a6bd6080543
Retained source material; see source provenance
Spruce Lake AI Data Centre — Updated Site Plans and Alternate Pipeline Route (EIA 1663 addendum, 28 April 2026), Internet Archive copy
Archived copy
Beacon New Brunswick Inc. and VoltaGrid LLC (prepared by Stantec)
Regulatory filing
Site and project identityall-rights-reservedBeacon New Brunswick Inc.; VoltaGrid LLC; Stantec; Internet Archive7451a12ff25299f91f5f32a1cf75b7b06e4cd8a47a1158a0a02a8f719ecaf35d
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Spruce Lake AI Data Centre [site vcc-site-bea6bf727e581e987a62]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-bea6bf727e581e987a62/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction