Core Scientific Muskogee data center campus
Partially operational
United States · 1 project · Last reported
Summary
Core Scientific high-density colocation campus at 1525 West 43rd Street South in Muskogee, Oklahoma, served by Oklahoma Gas & Electric. A 70 MW building designed for Nvidia GB300 systems is leased to CoreWeave and was billing by mid-July 2026, and a second building of about 82 MW, now leased to AMD, is under construction for delivery from the second half of 2027. In May 2026 Core Scientific announced plans to grow the campus to about 1.5 GW of gross power, about 1.0 GW leasable, on about 250 acres, and in August 2026 it closed the purchase of Polaris DS, which holds about 440 MW of in-service OG&E grid capacity.
Source record as of 2026-07-28 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: 35.74330, -95.35670 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Town or locality reference only; the facility position is not established.
Projects (1)
Core Scientific Muskogee data center campus
Partially operational last observed as of · Reported status
Location: Muskogee, Muskogee County, Oklahoma, US. Core Scientific gives the street address 1525 West 43rd Street South, Muskogee. No geocoder was used, so coordinates are the Muskogee city point from its Wikipedia article, which also names the county. Core Scientific; Core Scientific; Wikipedia
Use: Ai unspecified, Hpc
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 100 MW | Contracted · Phase · Grid connection · Original Muskogee 1 site | 2026-03-02 | Gross utility power capacity from OG&E listed in the 10-K; the company site page also describes a 100 MW development with a substation able to support more than 500 MW. | Core Scientific; Core Scientific, Inc. via SEC EDGAR |
| Power capacity | about 70 MW | Operational · Phase · Unspecified · Building 1 (CoreWeave) | 2026-07-28 | Leased capacity reported as billing by mid-July 2026. Core Scientific does not say whether the figure is critical IT load. | Core Scientific; Core Scientific |
| Power capacity | about 82 MW | Contracted · Phase · Unspecified · Building 2 (AMD) | 2026-07-28 | Building under construction since at least May 2026, when it was described as an unleased 82.5 MW building; leased to AMD in July 2026. | Core Scientific; Core Scientific; Core Scientific |
| Power capacity | about 440 MW | Operational · Phase · Grid connection · Polaris DS capacity | 2026-08-14 | In-service gross grid capacity held by Polaris DS LLC under electric service agreements with OG&E, acquired by Core Scientific to support the expansion. | Core Scientific; Core Scientific |
| Power capacity | about 1,500 MW | Planned · Campus · Unspecified | 2026-08-14 | Planned gross power from a mix of grid and behind-the-meter supply, which the company equates to about 1.0 GW of leasable power. Gross power is not defined as IT or facility load. | Core Scientific; Core Scientific; Data Center Knowledge |
| Land area | 65 acres | Reported · Phase · Muskogee 1 campus footprint | 2026-10-09 | From the undated company site page, accessed 2026-10-09. | Core Scientific |
| Land area | about 250 acres | Reported · Phase · Land secured for planned expansion | 2026-05-06 | Described as secured to support the planned expansion; the sources do not say whether it is owned or held under option. | Core Scientific; Data Center Knowledge |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Core Scientific | Developer | Core Scientific; Core Scientific; Core Scientific | |
| Core Scientific | Operator | Core Scientific; Core Scientific, Inc. via SEC EDGAR | |
| CoreWeave | Tenant | Named as tenant of the roughly 70 MW first building only in the Q2 2026 earnings presentation (s4). The May 2026 release (s3) describes that leased building, designed for the Nvidia GB300 platform, without naming the customer. | Core Scientific; Core Scientific |
| AMD | Tenant | Named for Muskogee only in the Q2 2026 earnings presentation (s4), which lists about 82 MW at this AMD direct site. The Q2 release (s8) gives the 15-year term for about 530 MW across five sites without naming them. | Core Scientific; Core Scientific |
| Oklahoma Gas & Electric | Utility | Core Scientific, Inc. via SEC EDGAR; Core Scientific; Core Scientific |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2026 | First operational | Actual | The 70 MW CoreWeave building was in final testing in May 2026 with delivery targeted for Q2 2026, and was billing by mid-July 2026. | Core Scientific; Core Scientific |
| 2026-05-06 | Expansion announced | Actual | Plan to scale the campus to about 1.5 GW of gross power and agreement to buy Polaris DS. | Core Scientific; Data Center Knowledge |
| 2026-07-28 | Other | Actual | Core Scientific disclosed AMD leases including about 82 MW at Muskogee. | Core Scientific |
| 2026-08-14 | Other | Actual | Acquisition of Polaris DS completed for about USD 444 million in cash. | Core Scientific |
| 2027-H2 | Other | Planned | Target for initial delivery of the roughly 82 MW AMD building; the May 2026 release gave Q4 2027. | Core Scientific; Core Scientific; Core Scientific |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Grid power from Oklahoma Gas & Electric, including about 440 MW of in-service capacity under Polaris DS service agreements; load studies for more grid capacity were due to finish in 2026. | Core Scientific, Inc. via SEC EDGAR; Core Scientific; Core Scientific |
| Other | Core Scientific says it has a plan for a scalable behind-the-meter power solution to supplement grid supply, without naming the fuel or size. | Core Scientific |
Core Scientific's Q2 2026 presentation lists about 917 MW of further power pipeline at Muskogee in two entries without saying how much is grid or behind-the-meter. The AMD agreements are 15-year leases for about 530 MW across five Core Scientific sites; per-site splits come from the company's earnings presentation.
Sources for these details
- Muskogee 1 high-density data center — Core Scientific; publication date not stated · Archived source
- Core Scientific, Inc. Form 10-K for the fiscal year ended December 31, 2025 — Core Scientific, Inc. via SEC EDGAR; 2026-03-02 · Archived source
- Core Scientific plans expansion to 1.5 gigawatts of gross power at Muskogee, Oklahoma campus — Core Scientific; 2026-05-06 · Archived source
- Core Scientific Q2 2026 earnings presentation (Form 8-K, Exhibit 99.2) — Core Scientific; 2026-07-28 · Archived source
- Core Scientific completes acquisition of Polaris DS, advancing planned Muskogee expansion to 1.5 GW of gross power — Core Scientific; 2026-08-14 · Archived source
- Core Scientific's Muskogee bet: can crypto-era infrastructure fuel AI? — Data Center Knowledge; 2026-05-07
- Muskogee, Oklahoma — Wikipedia; publication date not stated · Archived source
- Core Scientific announces second quarter 2026 results — Core Scientific; 2026-07-28
- Companies
- Developer: Core Scientific (unknown scope) evidence
- Developer: Core Scientific (unknown scope) evidence
- Developer: Core Scientific (unknown scope) evidence
- Operator: Core Scientific (unknown scope) evidence
- Operator: Core Scientific (unknown scope) evidence
- Tenant: CoreWeave (unknown scope) evidence
- Tenant: CoreWeave (unknown scope) evidence
- Tenant: AMD (unknown scope) evidence
- Tenant: AMD (unknown scope) evidence
- Utility: Oklahoma Gas & Electric (unknown scope) evidence
- Utility: Oklahoma Gas & Electric (unknown scope) evidence
- Utility: Oklahoma Gas & Electric (unknown scope) evidence
Source and location review
- Status source
- Core Scientific Q2 2026 earnings presentation (Form 8-K, Exhibit 99.2) evidence row
Core Scientific · published 2026-07-28 · Regulatory filing - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 91 days before the data update on 2026-10-27
Location details
- Coordinates
- 35.74330, -95.35670
- Geometry licence
- source-terms-not-recorded
- Use scope
- Locality reference only
- Scope class
- locality
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- Core Scientific gives the street address 1525 West 43rd Street South, Muskogee. No geocoder was used, so coordinates are the Muskogee city point from its Wikipedia article, which also names the county.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- cfd03805
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Core Scientific announces second quarter 2026 results Archived copy | Core Scientific Company disclosure | Imported: Record, Tenant claim | source-terms-not-recorded | Core Scientific | b70ec1a285588315094bb4c9fa71ad598c095bae8feb80f667d38aa11d7f73d3Factual source record; not the publisher page | ||
| Core Scientific completes acquisition of Polaris DS, advancing planned Muskogee expansion to 1.5 GW of gross power Archived copy | Core Scientific Company disclosure | Imported: Record, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Role: Developer, Role: Utility | source-terms-not-recorded | Core Scientific | 9d5b5910345d55f30d58a56f885a0a85fadbb437462648b444972c0568ad3737Factual source record; not the publisher page | ||
| Core Scientific plans expansion to 1.5 gigawatts of gross power at Muskogee, Oklahoma campus Archived copy | Core Scientific Company disclosure | Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Milestone: Expansion Announced, Milestone: First Operational, Milestone: Other, Power Source: Grid, Power Source: Other, Role: Developer, Tenant claim, Role: Utility | source-terms-not-recorded | Core Scientific | 5fc27f1f872ac1555ea6d636e357f49f7f86e4155b50b88f5cbb4ed1a01e2e6aFactual source record; not the publisher page | ||
| Core Scientific Q2 2026 earnings presentation (Form 8-K, Exhibit 99.2) Archived copy | Core Scientific Regulatory filing | Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: First Operational, Milestone: Other, Tenant claim | source-terms-not-recorded | Core Scientific | 7679598ab1cebc84c61e67b73e9fa454afe44ca5b45263f83714594f3a8127d0Factual source record; not the publisher page | ||
| Core Scientific's Muskogee bet: can crypto-era infrastructure fuel AI? Archived copy | Data Center Knowledge Trade publication | Imported: Record, Metric: Land Area, Metric: Power Capacity, Milestone: Expansion Announced | source-terms-not-recorded | Data Center Knowledge | c172d899d588a3e2d848fd8d400d54fff19511baaa18c7e84d2f07021911ae94Factual source record; not the publisher page | ||
| Core Scientific, Inc. Form 10-K for the fiscal year ended December 31, 2025 Archived copy | Core Scientific, Inc. via SEC EDGAR Regulatory filing | Imported: Record, Metric: Power Capacity, Power Source: Grid, Operator claim, Role: Utility | source-terms-not-recorded | Core Scientific, Inc. via SEC EDGAR | a75005b81dcd522ad3f042c7f25ce3807c03b796bea0edf597ff3035d32c7e5dFactual source record; not the publisher page | ||
| Muskogee 1 high-density data center Archived copy | Core Scientific Company disclosure | Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Role: Developer, Operator claim | not stated | source-terms-not-recorded | Core Scientific | 9a3c84a018d9e79cefeb08989cef5b3ac1393ee52178dc9cdfeb802f691a6acbFactual source record; not the publisher page | |
| Muskogee, Oklahoma Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | 8a6a895d53c5e5cdc8aed41747c25ddcc990aeeb263a3b6678430b8bab32a5c3Factual source record; not the publisher page |
Cite this site
Kyars, K. (2026). Core Scientific Muskogee data center campus [site vcc-site-bf829ea21a9d7386fb5f]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-bf829ea21a9d7386fb5f/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction