Digi Power X Columbiana AI Data Center Campus

Under construction

United States · 1 project · Last reported

Summary

Digi Power X's 13 October 2026 release on a US$200 million debt-financing commitment for its 40 MW AI data center in Columbiana, Alabama states that construction at the 40 MW Alabama campus remains on target, and its chief executive says that construction is on schedule in Alabama. The record moves to the general construction stage as of the release date. The release names no specific stage, so the July 7 building-shell stage is not carried forward and no mechanical, electrical, commissioning or completion stage is inferred. The Phase 1 (December 2026) and Phase 2 (March 2027) completion dates are forecasts. evidence

Digi Power X Inc. (distributed by ACCESS Newswire) · published 2026-10-13

Location

The interactive map needs JavaScript. Display anchor: 33.18279, -86.61848 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Digi Power X Columbiana Purpose-Built Flagship Vertical Build

Under construction last observed as of · Authoritative status update

Source and location review
Status source
Digi Power X Inc.: "Digi Power X Announces $200 Million Debt Financing Commitment to Support Completion of Alabama AI Data Center and Provides Expansion Update", 13 October 2026 (ACCESS Newswire release as hosted by TT) evidence row
Digi Power X Inc. (distributed by ACCESS Newswire) · published 2026-10-13 · Company disclosure
Locator
Campus locator · Official source · address_range_geocode evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 14 days before the data update on 2026-10-27

Location details
Coordinates
33.18279, -86.61848
Geometry licence
US-federal-public-domain
Use scope
Campus locator
Scope class
address_range_geocode
Authority
Official source
Source entity
Campus
Method
official_address_geocode
Derivation
official_address_geocode
Precision scope
Exact returned Census coordinate for the project-linked street address; digits are not positional accuracy and the point is not parcel, rooftop, building, or work-area geometry.
Horizontal uncertainty
Not reported

Census supplies an address-range geocode without a bounded horizontal error for this match.

Geometry evidence
8e34c085

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Digi Power X Columbiana AI Data Center Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Digi Power X Inc.: "Digi Power X Announces $200 Million Debt Financing Commitment to Support Completion of Alabama AI Data Center and Provides Expansion Update", 13 October 2026 (ACCESS Newswire release as hosted by TT)
Archived copy
Digi Power X Inc. (distributed by ACCESS Newswire)
Company disclosure
Physical statusall-rights-reservedDigi Power X Inc.; ACCESS Newswireb21934b35f6beb078e89dc64d52e46eac9b18df53b11ef2ae4bdd35c47fbf293
Retained source material; see source provenance
Digi Power X Provides Operations and Financial Update
Archived copy
Digi Power X Inc.
Company disclosure
Source location context, Physical statusall-rights-reservedDigi Power X Inc.ebcddc3bc3e8d35325e56fe7b81803a90a3a69938d1451401051f8eea135f734
Retained source material; see source provenance
U.S. Census geocode for 130 Industrial Parkway, Columbiana
Archived copy
United States Census Bureau
Government record
Geometrynot statedUS-federal-public-domainUnited States Census Bureaueff57c2bf59f9541f2f0bf4fddd221b89ecc05db93fdf67d60d39ea984b3c096
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Digi Power X Columbiana AI Data Center Campus [site vcc-site-c1a0f58564147c78c139]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-c1a0f58564147c78c139/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction