Vantage Lighthouse Port Washington Data Center Campus
Under construction
United States · 1 project · Last reported
Summary
Vantage Data Centers is building Lighthouse, a four-building campus on 672 acres on Port Washington's north side in Wisconsin, for Oracle and OpenAI under the Stargate program. OpenAI, Oracle and Vantage announced it as a Stargate site in October 2025, with close to 1 GW of capacity and completion targeted for 2028. Vantage now lists 902 MW, while local reporting and analyst Epoch AI cite 1.3 GW. The investment is reported at about $15 billion. Two buildings had topped out by mid-2026. We Energies supplies power; an Oracle subsidiary sued state regulators in June 2026 over financial-security rules, and in October 2026 We Energies proposed an Oracle share of nuclear output, pending approval.
Source record as of 2026-09-11 · Details and sources
Vantage's Lighthouse campus construction-updates page, in its version modified on 19 October 2026 and headed 'October Summary', says: 'The campus includes four single-story data center buildings. Two data center buildings are fully enclosed and have transitioned to the interior construction phase. The remaining two buildings continue through the structural construction phase, with crews actively installing building frameworks.' It also gives the data-centre campus construction hours and construction-traffic advisories on County Road LL. This records the four-building Port Washington campus as under construction on 19 October 2026. It does not establish the completion, commissioning or operation of any building, and the enclosed buildings' interior work is not treated as completion of the campus. evidence
Vantage Data Centers (Vantage Lighthouse Campus website) · published 2026-10-19
Location
The interactive map needs JavaScript. Display anchor: 43.43073, -87.86149 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Project locator; building footprints are not mapped.
Projects (1)
Vantage Lighthouse Port Washington Current Campus Build
Under construction last observed as of · Authoritative status update
This record reports under construction as of 2026-09-11. Ozaukee Press; FOX 11 News
Location: Port Washington, Ozaukee County, Wisconsin, US. Port Washington city centroid from OpenStreetMap Nominatim. Sources place the campus on the city's north side, just west of Interstate 43, without giving an address or parcel. Ozaukee Press; FOX 11 News; Wisconsin Watch
Use: Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | about 1,000 MW | Planned · Campus · Unspecified | 2025-10-23 | Announced as close to a gigawatt of AI capacity across four data centers. | W.Media |
| Power capacity | 902 MW | Planned · Campus · Unspecified | 2026-10-09 | Vantage's locations page lists the campus at 902 MW total without saying whether this is IT or facility power. | Vantage Data Centers |
| Power capacity | about 1,300 MW | Planned · Campus · Unspecified | 2025-08-20 | Local reporting on the 2025 city approval said the campus would use 1.3 GW of power; it does not reconcile this with the 902 MW figure. | Ozaukee Press |
| Power capacity | about 1,300 MW | Planned · Campus · Facility | 2026-04-17 | Analyst estimate, not a company disclosure: Epoch AI's projection of total facility power. | Epoch AI |
| Investment | at least 8,000,000,000 USD | Announced · Campus | 2025-08-20 | Figure given by Vantage when the city approved the developer's agreement; Vantage said it was likely to grow. | Ozaukee Press |
| Investment | about 15,000,000,000 USD | Reported · Campus | 2026-09-11 | Wisconsin Public Radio; Ozaukee Press; FOX 11 News | |
| Land area | about 1,900 acres | Acquired · Campus | 2025-08-20 | Total land Vantage bought on the city's north side; only the southern 672 acres are being developed. | Ozaukee Press |
| Land area | about 672 acres | Planned · Campus | 2026-07-01 | Ozaukee Press; Ozaukee Press | |
| Buildings | 4 count | Planned · Campus | 2025-10-23 | Ozaukee Press; W.Media; Ozaukee Press | |
| Floor area | about 2,500,000 sq_ft | Planned · Campus | 2026-07-01 | The 2025 plan described two buildings of about 560,000 sq ft and two of about 719,000 sq ft. | Ozaukee Press; Ozaukee Press; FOX 11 News |
| Jobs construction | more than 4,000 count | Planned · Campus | 2025-10-23 | Mostly union jobs. In mid-2026 about 1,700 workers were on site, expected to reach about 5,000 going into winter. | W.Media; Ozaukee Press |
| Jobs permanent | more than 1,000 count | Planned · Campus | 2025-10-23 | Figure from the October 2025 announcement and repeated in September 2026 coverage; in August 2025 Vantage spoke of about 300 long-term employees. | Ozaukee Press; W.Media; FOX 11 News |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Vantage Data Centers | Developer | Ozaukee Press; W.Media | |
| Vantage Data Centers | Owner | Ozaukee Press | |
| Oracle | Tenant | Named as a tenant with OpenAI, providing Oracle Cloud Infrastructure capacity for the project. Wisconsin Watch describes Oracle as co-developing the campus with OpenAI, and an Oracle subsidiary challenged state utility financial-security rules in court. | W.Media; Ozaukee Press; Wisconsin Watch |
| OpenAI | Tenant | End user under the Stargate program. | W.Media; Ozaukee Press |
| We Energies | Utility | Ozaukee Press; Wisconsin Watch | |
| Whiting-Turner Contracting | Builder | Contractor on the second building to top out. | Ozaukee Press |
| The Weitz Co. | Builder | Contractor on another of the data center buildings. | Ozaukee Press |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2025-08 | Other | Actual | Port Washington approved a developer's agreement with Vantage for the campus. | Ozaukee Press |
| 2025-10 | Announced | Actual | OpenAI, Oracle and Vantage announced the campus as a Stargate site. | W.Media |
| 2026-Q1 | Construction started | Actual | Analyst estimate, not a company disclosure: Epoch AI dates the start from satellite imagery showing foundation work by February 2026; ground preparation may have begun earlier. | Epoch AI |
| 2026-06 | Other | Actual | An Oracle subsidiary sued Wisconsin utility regulators in Ozaukee County court over tightened financial-security requirements for data center customers of We Energies. | Wisconsin Public Radio |
| 2026-06 | Other | Actual | Second of four buildings topped out; the project was reported to be about 12 to 15 percent complete. | Ozaukee Press |
| 2026-10-02 | Other | Actual | We Energies proposed letting Oracle subscribe to 10 to 20 percent of Point Beach nuclear plant output to help serve the campus, pending regulatory approval. | Wisconsin Watch |
| 2028 | Fully operational | Planned | W.Media; FOX 11 News |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Supplied by We Energies, with Vantage saying no cost of acquiring the energy will be passed on to other utility customers. | Ozaukee Press; Wisconsin Watch |
| Solar | Roughly 70 percent of the campus supply is to come from zero-emission sources, which analyst Epoch AI lists as solar, wind and battery storage, with the rest offset through purchased credits. | Ozaukee Press; Epoch AI |
| Wind | Wind is part of the 70 percent clean supply mix described for the campus by analyst Epoch AI. | Epoch AI |
| Battery storage | Battery storage is part of the 70 percent clean supply mix described for the campus by analyst Epoch AI. | Epoch AI |
| Nuclear | Proposed subscription by Oracle to 10 to 20 percent of Point Beach nuclear plant generation through We Energies, awaiting Public Service Commission approval. | Wisconsin Watch |
Capacity figures differ by source and basis: close to 1 GW at announcement, 902 MW on Vantage's site, 1.3 GW of power in local reporting, and a 1.3 GW facility-power projection from analyst Epoch AI that is not a company disclosure. Reported investment rose from at least $8 billion in August 2025 to about $15 billion by mid-2026. Related-story headlines on news pages suggest Oracle later dropped its lawsuit, but no article opened here reports that.
Sources for these details
- Vantage chief calls complex large even by its standards — Ozaukee Press; 2025-08-20 · Archived source
- OpenAI, Oracle and Vantage Data Centers announce Stargate data center site in Wisconsin — W.Media; 2025-10-23 · Archived source
- Data Center Locations - North America — Vantage Data Centers; publication date not stated
- OpenAI Stargate: where the US sites stand — Epoch AI; 2026-04-17 · Archived source
- Oracle sues Wisconsin utility regulators over financial requirements for data centers — Wisconsin Public Radio; 2026-06-24
- Another data center tops out — Ozaukee Press; 2026-07-01 · Archived source
- Companies behind Port Washington data centers meet with neighbors — FOX 11 News; 2026-09-11
- We Energies strikes deal to power Oracle data center with nuclear energy — Wisconsin Watch; 2026-10-02
ATC, the transmission owner, says it has filed a revised application with the Public Service Commission of Wisconsin (PSCW) for approval of the Ozaukee County Distribution Interconnection Project, which it says is 'needed to support increased electric load in the Port Washington area'. The release states that 'The customer at the Lighthouse campus is committed to paying its own way when it comes to the energy needed to power its facilities' and to fully funding the cost of the transmission infrastructure built to serve it. ATC first applied in September 2025; after the PSCW revoked the completeness determination for that application, ATC prepared the revised application, which designates the South East route as preferred in the southern portion, removes the east-west route through the towns of Trenton and Saukville, adds an E-STATCOM next to the proposed Decker Substation and includes up to five new substations with new and rebuilt power lines across Calumet, Fond du Lac, Manitowoc, Sheboygan, Ozaukee and Washington counties. After the PSCW finds the application complete it will announce public-comment opportunities; the project also needs Wisconsin DNR review. The grid works are proposed and unapproved. evidence
American Transmission Co. (ATC) · published 2026-09-15
Project status: 'Filed a revised application with the Public Service Commission of Wisconsin in September 2026.' Project need: 'The proposed project will support growing electric demand in the region, including the Port Washington data center project'. The PSCW docket is 137-CE-229. The southern portion would build two new dual-circuit 345-kV power lines connecting the proposed Decker Substation in Port Washington to the existing system and rebuild lines between the proposed Mullet River Junction (Sheboygan County) and Cedar Creek Junction (Washington County) substations; the northern portion would build a 345-kV connection from Forest Junction (Calumet County) to the proposed Sheboygan River Substation (Fond du Lac County); the Decker, Sheboygan River, Mullet River Junction and Cedar Creek Junction substations (and Adell, if the South East route is chosen) would be built. Milestones: approval 'TBD'; construction anticipated 31 days after the PSCW's written order; in service about 17 months after construction begins (forecasts). Contact names and telephone numbers on the page are not copied. evidence
American Transmission Co. (ATC) · publication date not stated
Lists ATC's 14 project pages with their last-modified times, including the Ozaukee County Distribution Interconnection project page at 2026-09-17T14:59:57-05:00. evidence
American Transmission Co. (ATC) · publication date not stated
Oracle, the campus customer, says it is 'partnering closely with American Transmission Co. on its revised certificate of public convenience and necessity application for the Ozaukee County Distribution Interconnection Project', that it is 'committed to paying 100 percent of our energy costs' under the PSCW's VLC (very large customer) tariff approval order, and that 'More than 50 percent of the power capacity to serve the campus will come from carbon-free energy such as wind, solar, and batteries', with the rest matched by renewable purchases. It repeats Project Lighthouse's expected economic impact and job figures and says 'Our commitment to completing Project Lighthouse remains unchanged.' No capacity, energisation date or construction stage is given. evidence
Oracle Corporation · published 2026-09-16
- Companies
- Developer: Vantage Data Centers (unknown scope) evidence
- Developer: Vantage Data Centers (unknown scope) evidence
- Owner: Vantage Data Centers (unknown scope) evidence
- Tenant: Oracle (unknown scope) evidence
- Tenant: Oracle (unknown scope) evidence
- Tenant: Oracle (unknown scope) evidence
- Tenant: OpenAI (unknown scope) evidence
- Tenant: OpenAI (unknown scope) evidence
- Utility: We Energies (unknown scope) evidence
- Utility: We Energies (unknown scope) evidence
- Builder: Whiting-Turner Contracting (unknown scope) evidence
- Builder: The Weitz Co. (unknown scope) evidence
Source and location review
- Status source
- Vantage Lighthouse Campus (lighthousewisconsin.com): 'Construction Updates - Building Progress and Timelines', version modified 19 October 2026 ('October Summary') evidence row
Vantage Data Centers (Vantage Lighthouse Campus website) · published 2026-10-19 · Company disclosure - Locator
- Project locator · Official source · environmental_review_project_point evidence
- Source checks
Not reviewed against imagery not_
reviewed_ for_ core_ preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 8 days before the data update on 2026-10-27
Location details
- Coordinates
- 43.43073, -87.86149
- Geometry licence
- public-government-record-fact-extraction-only
- Use scope
- Project locator
- Scope class
- environmental_review_project_point
- Authority
- Official source
- Source entity
- Project
- Method
- official_project_coordinate
- Derivation
- coordinates_to_point
- Precision scope
- Exact sign-and-decimal parsing of the DNR project coordinate; not a parcel, building, or construction footprint.
- Horizontal uncertainty
Not reported
Wisconsin DNR publishes no bounded accuracy for the project coordinate.
- Geometry evidence
- 40f1c2ae
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Another data center tops out Archived copy | Ozaukee Press News | Imported: Record, Imported: Status, Metric: Buildings, Metric: Floor Area, Metric: Investment, Metric: Jobs Construction, Metric: Land Area, Milestone: Other, Role: Builder, Owner claim, Tenant claim | source-terms-not-recorded | Ozaukee Press | 9bfdd0f0af8523145679670db3c8e7a5d238d0ad2b77b8716e2f34064afa7b0fFactual source record; not the publisher page | ||
| ATC news release: 'ATC files revised application for the Ozaukee County Distribution Interconnection Project' (posted 15 September 2026) Archived copy | American Transmission Co. (ATC) Utility record | Grid connection context | all-rights-reserved | American Transmission Co. LLC | 1776034b93949e4ea71fdd8699934434033ebaf1a9a1ca76485e9a61e5c4ed96Retained source material; see source provenance | ||
| ATC project page: Ozaukee County Distribution Interconnection Project (PSCW docket 137-CE-229), captured 27 October 2026 Archived copy | American Transmission Co. (ATC) Utility record | Grid connection context | not stated | all-rights-reserved | American Transmission Co. LLC | d2680a9cb7a79f7cea2ced4824c684f726b65d40300402ff5ad4f797445ea77aRetained source material; see source provenance | |
| ATC website project sitemap (wp-sitemap-posts-project-1.xml), captured 27 October 2026 Archived copy | American Transmission Co. (ATC) Utility record | Grid connection context | not stated | all-rights-reserved | American Transmission Co. LLC | 07d2eb602dce31eb1bb3144ffa37c2e79932f2dd876822cd10a1bd8601771e54Retained source material; see source provenance | |
| Companies behind Port Washington data centers meet with neighbors Archived copy | FOX 11 News News | Imported: Geometry, Imported: Record, Imported: Status, Metric: Floor Area, Metric: Investment, Metric: Jobs Permanent, Milestone: Fully Operational | source-terms-not-recorded | FOX 11 News | 35d4a2023820879b257989b3426a59e4148c23b219a227c9fad116cfbbd25f26Factual source record; not the publisher page | ||
| Data Center Locations - North America Archived copy | Vantage Data Centers Company disclosure | Imported: Record, Metric: Power Capacity | not stated | source-terms-not-recorded | Vantage Data Centers | fa2b7ef32d7889c0002293c5c0809882894e975fb1a781d897b73b35f46563ebFactual source record; not the publisher page | |
| OpenAI Stargate: where the US sites stand Archived copy | Epoch AI Analyst report | Imported: Record, Metric: Power Capacity, Milestone: Construction Started, Power Source: Battery Storage, Power Source: Solar, Power Source: Wind | source-terms-not-recorded | Epoch AI | 254040191fa014eb1b57eababe019d7f91a21d98418824d3d665f627a563575dFactual source record; not the publisher page | ||
| OpenAI, Oracle and Vantage Data Centers announce Stargate data center site in Wisconsin Archived copy | W.Media Trade publication | Imported: Record, Metric: Buildings, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Power Capacity, Milestone: Announced, Milestone: Fully Operational, Role: Developer, Tenant claim | source-terms-not-recorded | W.Media | ff502a263e64f1b06af6ba795f6d0eecb34208746bd2ab3de60f27fd0fdf0db7Factual source record; not the publisher page | ||
| Oracle AI data-center locations page: dated construction media captions (captured 16 October 2026) Archived copy | Oracle Company disclosure | Physical status | not stated | all-rights-reserved | Oracle | 35da74fdde71efad4d88d252b0d91ffd7fb4f72e89dc3699afdbae1cec5e6eb7Retained source material; see source provenance | |
| Oracle blog: 'A Responsible Path Forward for Project Lighthouse' (16 September 2026) Archived copy | Oracle Corporation Company disclosure | Grid connection context | all-rights-reserved | Oracle Corporation | 3646d158464b0d89d823fe1bef81ffacd48222b9046496c510cbe292057a2471Retained source material; see source provenance | ||
| Oracle sues Wisconsin utility regulators over financial requirements for data centers Archived copy | Wisconsin Public Radio News | Imported: Record, Metric: Investment, Milestone: Other | source-terms-not-recorded | Wisconsin Public Radio | 6c244224df38405e26c80f45759809fba4f691cc1273aa66361eb5a4f88b40a5Factual source record; not the publisher page | ||
| Port Washington (Lighthouse) Data Center Campus Archived copy | Vantage Data Centers Company disclosure | Source location context | not stated | all-rights-reserved | Vantage Data Centers | 7eed1e19447c03d97e3da15684de3eb7a1ceb12e61dbec110e3ecb638ecebec3Retained source material; see source provenance | |
| Port Washington Data Center Proposal Archived copy | Wisconsin Department of Natural Resources Government record | Physical status | not stated | public-government-record | Wisconsin Department of Natural Resources | 4502f68999eb5a1b3e0cdb70084e588798f7d2960271642691db62faddd6a396Retained source material; see source provenance | |
| Vantage chief calls complex large even by its standards Archived copy | Ozaukee Press News | Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Floor Area, Metric: Investment, Metric: Jobs Permanent, Metric: Land Area, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Power Source: Solar, Role: Developer, Role: Utility | source-terms-not-recorded | Ozaukee Press | ff1710f2aeb5f871c1fbde22d4ea04d79faaabe3b687730f295b46eb567260ceFactual source record; not the publisher page | ||
| Vantage Lighthouse Campus (lighthousewisconsin.com): 'Construction Updates - Building Progress and Timelines', version modified 19 October 2026 ('October Summary') Archived copy | Vantage Data Centers (Vantage Lighthouse Campus website) Company disclosure | Physical status | all-rights-reserved | Vantage | 1ecb96ff62970b11b8d008f4ea8c1e048cd9717cc01eabf4ec2f9a214ac38223Retained source material; see source provenance | ||
| We Energies strikes deal to power Oracle data center with nuclear energy Archived copy | Wisconsin Watch News | Imported: Geometry, Imported: Record, Milestone: Other, Power Source: Grid, Power Source: Nuclear, Tenant claim, Role: Utility | source-terms-not-recorded | Wisconsin Watch | e5d7433e92a84d2de46a8b5530b9cc1da6c374ac6dfc7d9370219c78aad99a31Factual source record; not the publisher page | ||
| Wisconsin DNR Lighthouse Data Center environmental review page Archived copy | Wisconsin Department of Natural Resources Government record | Geometry | not stated | public-government-record-fact-extraction-only | Wisconsin Department of Natural Resources | 7452e95750d278a03a1e803d08280b325cc0013f9e842d52da8e637e5f9ca679Retained source material; see source provenance |