Vantage Lighthouse Port Washington Data Center Campus

Under construction

United States · 1 project · Last reported

Summary

Vantage Data Centers is building Lighthouse, a four-building campus on 672 acres on Port Washington's north side in Wisconsin, for Oracle and OpenAI under the Stargate program. OpenAI, Oracle and Vantage announced it as a Stargate site in October 2025, with close to 1 GW of capacity and completion targeted for 2028. Vantage now lists 902 MW, while local reporting and analyst Epoch AI cite 1.3 GW. The investment is reported at about $15 billion. Two buildings had topped out by mid-2026. We Energies supplies power; an Oracle subsidiary sued state regulators in June 2026 over financial-security rules, and in October 2026 We Energies proposed an Oracle share of nuclear output, pending approval.

Source record as of 2026-09-11 · Details and sources

Vantage's Lighthouse campus construction-updates page, in its version modified on 19 October 2026 and headed 'October Summary', says: 'The campus includes four single-story data center buildings. Two data center buildings are fully enclosed and have transitioned to the interior construction phase. The remaining two buildings continue through the structural construction phase, with crews actively installing building frameworks.' It also gives the data-centre campus construction hours and construction-traffic advisories on County Road LL. This records the four-building Port Washington campus as under construction on 19 October 2026. It does not establish the completion, commissioning or operation of any building, and the enclosed buildings' interior work is not treated as completion of the campus. evidence

Vantage Data Centers (Vantage Lighthouse Campus website) · published 2026-10-19

Location

The interactive map needs JavaScript. Display anchor: 43.43073, -87.86149 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Project locator; building footprints are not mapped.

Projects (1)

Vantage Lighthouse Port Washington Current Campus Build

Under construction last observed as of · Authoritative status update

This record reports under construction as of 2026-09-11. Ozaukee Press; FOX 11 News

Location: Port Washington, Ozaukee County, Wisconsin, US. Port Washington city centroid from OpenStreetMap Nominatim. Sources place the campus on the city's north side, just west of Interstate 43, without giving an address or parcel. Ozaukee Press; FOX 11 News; Wisconsin Watch

Use: Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacityabout 1,000 MWPlanned · Campus · Unspecified2025-10-23Announced as close to a gigawatt of AI capacity across four data centers.W.Media
Power capacity902 MWPlanned · Campus · Unspecified2026-10-09Vantage's locations page lists the campus at 902 MW total without saying whether this is IT or facility power.Vantage Data Centers
Power capacityabout 1,300 MWPlanned · Campus · Unspecified2025-08-20Local reporting on the 2025 city approval said the campus would use 1.3 GW of power; it does not reconcile this with the 902 MW figure.Ozaukee Press
Power capacityabout 1,300 MWPlanned · Campus · Facility2026-04-17Analyst estimate, not a company disclosure: Epoch AI's projection of total facility power.Epoch AI
Investmentat least 8,000,000,000 USDAnnounced · Campus2025-08-20Figure given by Vantage when the city approved the developer's agreement; Vantage said it was likely to grow.Ozaukee Press
Investmentabout 15,000,000,000 USDReported · Campus2026-09-11Wisconsin Public Radio; Ozaukee Press; FOX 11 News
Land areaabout 1,900 acresAcquired · Campus2025-08-20Total land Vantage bought on the city's north side; only the southern 672 acres are being developed.Ozaukee Press
Land areaabout 672 acresPlanned · Campus2026-07-01Ozaukee Press; Ozaukee Press
Buildings4 countPlanned · Campus2025-10-23Ozaukee Press; W.Media; Ozaukee Press
Floor areaabout 2,500,000 sq_ftPlanned · Campus2026-07-01The 2025 plan described two buildings of about 560,000 sq ft and two of about 719,000 sq ft.Ozaukee Press; Ozaukee Press; FOX 11 News
Jobs constructionmore than 4,000 countPlanned · Campus2025-10-23Mostly union jobs. In mid-2026 about 1,700 workers were on site, expected to reach about 5,000 going into winter.W.Media; Ozaukee Press
Jobs permanentmore than 1,000 countPlanned · Campus2025-10-23Figure from the October 2025 announcement and repeated in September 2026 coverage; in August 2025 Vantage spoke of about 300 long-term employees.Ozaukee Press; W.Media; FOX 11 News

Companies and organizations

NameRoleNotesSources
Vantage Data CentersDeveloperOzaukee Press; W.Media
Vantage Data CentersOwnerOzaukee Press
OracleTenantNamed as a tenant with OpenAI, providing Oracle Cloud Infrastructure capacity for the project. Wisconsin Watch describes Oracle as co-developing the campus with OpenAI, and an Oracle subsidiary challenged state utility financial-security rules in court.W.Media; Ozaukee Press; Wisconsin Watch
OpenAITenantEnd user under the Stargate program.W.Media; Ozaukee Press
We EnergiesUtilityOzaukee Press; Wisconsin Watch
Whiting-Turner ContractingBuilderContractor on the second building to top out.Ozaukee Press
The Weitz Co.BuilderContractor on another of the data center buildings.Ozaukee Press

Timeline

DateEventActual or plannedNotesSources
2025-08OtherActualPort Washington approved a developer's agreement with Vantage for the campus.Ozaukee Press
2025-10AnnouncedActualOpenAI, Oracle and Vantage announced the campus as a Stargate site.W.Media
2026-Q1Construction startedActualAnalyst estimate, not a company disclosure: Epoch AI dates the start from satellite imagery showing foundation work by February 2026; ground preparation may have begun earlier.Epoch AI
2026-06OtherActualAn Oracle subsidiary sued Wisconsin utility regulators in Ozaukee County court over tightened financial-security requirements for data center customers of We Energies.Wisconsin Public Radio
2026-06OtherActualSecond of four buildings topped out; the project was reported to be about 12 to 15 percent complete.Ozaukee Press
2026-10-02OtherActualWe Energies proposed letting Oracle subscribe to 10 to 20 percent of Point Beach nuclear plant output to help serve the campus, pending regulatory approval.Wisconsin Watch
2028Fully operationalPlannedW.Media; FOX 11 News

Power supply

TypeDescriptionSources
GridSupplied by We Energies, with Vantage saying no cost of acquiring the energy will be passed on to other utility customers.Ozaukee Press; Wisconsin Watch
SolarRoughly 70 percent of the campus supply is to come from zero-emission sources, which analyst Epoch AI lists as solar, wind and battery storage, with the rest offset through purchased credits.Ozaukee Press; Epoch AI
WindWind is part of the 70 percent clean supply mix described for the campus by analyst Epoch AI.Epoch AI
Battery storageBattery storage is part of the 70 percent clean supply mix described for the campus by analyst Epoch AI.Epoch AI
NuclearProposed subscription by Oracle to 10 to 20 percent of Point Beach nuclear plant generation through We Energies, awaiting Public Service Commission approval.Wisconsin Watch

Capacity figures differ by source and basis: close to 1 GW at announcement, 902 MW on Vantage's site, 1.3 GW of power in local reporting, and a 1.3 GW facility-power projection from analyst Epoch AI that is not a company disclosure. Reported investment rose from at least $8 billion in August 2025 to about $15 billion by mid-2026. Related-story headlines on news pages suggest Oracle later dropped its lawsuit, but no article opened here reports that.

Sources for these details

ATC, the transmission owner, says it has filed a revised application with the Public Service Commission of Wisconsin (PSCW) for approval of the Ozaukee County Distribution Interconnection Project, which it says is 'needed to support increased electric load in the Port Washington area'. The release states that 'The customer at the Lighthouse campus is committed to paying its own way when it comes to the energy needed to power its facilities' and to fully funding the cost of the transmission infrastructure built to serve it. ATC first applied in September 2025; after the PSCW revoked the completeness determination for that application, ATC prepared the revised application, which designates the South East route as preferred in the southern portion, removes the east-west route through the towns of Trenton and Saukville, adds an E-STATCOM next to the proposed Decker Substation and includes up to five new substations with new and rebuilt power lines across Calumet, Fond du Lac, Manitowoc, Sheboygan, Ozaukee and Washington counties. After the PSCW finds the application complete it will announce public-comment opportunities; the project also needs Wisconsin DNR review. The grid works are proposed and unapproved. evidence

American Transmission Co. (ATC) · published 2026-09-15

Project status: 'Filed a revised application with the Public Service Commission of Wisconsin in September 2026.' Project need: 'The proposed project will support growing electric demand in the region, including the Port Washington data center project'. The PSCW docket is 137-CE-229. The southern portion would build two new dual-circuit 345-kV power lines connecting the proposed Decker Substation in Port Washington to the existing system and rebuild lines between the proposed Mullet River Junction (Sheboygan County) and Cedar Creek Junction (Washington County) substations; the northern portion would build a 345-kV connection from Forest Junction (Calumet County) to the proposed Sheboygan River Substation (Fond du Lac County); the Decker, Sheboygan River, Mullet River Junction and Cedar Creek Junction substations (and Adell, if the South East route is chosen) would be built. Milestones: approval 'TBD'; construction anticipated 31 days after the PSCW's written order; in service about 17 months after construction begins (forecasts). Contact names and telephone numbers on the page are not copied. evidence

American Transmission Co. (ATC) · publication date not stated

Lists ATC's 14 project pages with their last-modified times, including the Ozaukee County Distribution Interconnection project page at 2026-09-17T14:59:57-05:00. evidence

American Transmission Co. (ATC) · publication date not stated

Oracle, the campus customer, says it is 'partnering closely with American Transmission Co. on its revised certificate of public convenience and necessity application for the Ozaukee County Distribution Interconnection Project', that it is 'committed to paying 100 percent of our energy costs' under the PSCW's VLC (very large customer) tariff approval order, and that 'More than 50 percent of the power capacity to serve the campus will come from carbon-free energy such as wind, solar, and batteries', with the rest matched by renewable purchases. It repeats Project Lighthouse's expected economic impact and job figures and says 'Our commitment to completing Project Lighthouse remains unchanged.' No capacity, energisation date or construction stage is given. evidence

Oracle Corporation · published 2026-09-16

Companies
  • Developer: Vantage Data Centers (unknown scope) evidence
  • Developer: Vantage Data Centers (unknown scope) evidence
  • Owner: Vantage Data Centers (unknown scope) evidence
  • Tenant: Oracle (unknown scope) evidence
  • Tenant: Oracle (unknown scope) evidence
  • Tenant: Oracle (unknown scope) evidence
  • Tenant: OpenAI (unknown scope) evidence
  • Tenant: OpenAI (unknown scope) evidence
  • Utility: We Energies (unknown scope) evidence
  • Utility: We Energies (unknown scope) evidence
  • Builder: Whiting-Turner Contracting (unknown scope) evidence
  • Builder: The Weitz Co. (unknown scope) evidence
Source and location review
Status source
Vantage Lighthouse Campus (lighthousewisconsin.com): 'Construction Updates - Building Progress and Timelines', version modified 19 October 2026 ('October Summary') evidence row
Vantage Data Centers (Vantage Lighthouse Campus website) · published 2026-10-19 · Company disclosure
Locator
Project locator · Official source · environmental_review_project_point evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 8 days before the data update on 2026-10-27

Location details
Coordinates
43.43073, -87.86149
Geometry licence
public-government-record-fact-extraction-only
Use scope
Project locator
Scope class
environmental_review_project_point
Authority
Official source
Source entity
Project
Method
official_project_coordinate
Derivation
coordinates_to_point
Precision scope
Exact sign-and-decimal parsing of the DNR project coordinate; not a parcel, building, or construction footprint.
Horizontal uncertainty
Not reported

Wisconsin DNR publishes no bounded accuracy for the project coordinate.

Geometry evidence
40f1c2ae

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Vantage Lighthouse Port Washington Data Center Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Another data center tops out
Archived copy
Ozaukee Press
News
Imported: Record, Imported: Status, Metric: Buildings, Metric: Floor Area, Metric: Investment, Metric: Jobs Construction, Metric: Land Area, Milestone: Other, Role: Builder, Owner claim, Tenant claimsource-terms-not-recordedOzaukee Press9bfdd0f0af8523145679670db3c8e7a5d238d0ad2b77b8716e2f34064afa7b0f
Factual source record; not the publisher page
ATC news release: 'ATC files revised application for the Ozaukee County Distribution Interconnection Project' (posted 15 September 2026)
Archived copy
American Transmission Co. (ATC)
Utility record
Grid connection contextall-rights-reservedAmerican Transmission Co. LLC1776034b93949e4ea71fdd8699934434033ebaf1a9a1ca76485e9a61e5c4ed96
Retained source material; see source provenance
ATC project page: Ozaukee County Distribution Interconnection Project (PSCW docket 137-CE-229), captured 27 October 2026
Archived copy
American Transmission Co. (ATC)
Utility record
Grid connection contextnot statedall-rights-reservedAmerican Transmission Co. LLCd2680a9cb7a79f7cea2ced4824c684f726b65d40300402ff5ad4f797445ea77a
Retained source material; see source provenance
ATC website project sitemap (wp-sitemap-posts-project-1.xml), captured 27 October 2026
Archived copy
American Transmission Co. (ATC)
Utility record
Grid connection contextnot statedall-rights-reservedAmerican Transmission Co. LLC07d2eb602dce31eb1bb3144ffa37c2e79932f2dd876822cd10a1bd8601771e54
Retained source material; see source provenance
Companies behind Port Washington data centers meet with neighbors
Archived copy
FOX 11 News
News
Imported: Geometry, Imported: Record, Imported: Status, Metric: Floor Area, Metric: Investment, Metric: Jobs Permanent, Milestone: Fully Operationalsource-terms-not-recordedFOX 11 News35d4a2023820879b257989b3426a59e4148c23b219a227c9fad116cfbbd25f26
Factual source record; not the publisher page
Data Center Locations - North America
Archived copy
Vantage Data Centers
Company disclosure
Imported: Record, Metric: Power Capacitynot statedsource-terms-not-recordedVantage Data Centersfa2b7ef32d7889c0002293c5c0809882894e975fb1a781d897b73b35f46563eb
Factual source record; not the publisher page
OpenAI Stargate: where the US sites stand
Archived copy
Epoch AI
Analyst report
Imported: Record, Metric: Power Capacity, Milestone: Construction Started, Power Source: Battery Storage, Power Source: Solar, Power Source: Windsource-terms-not-recordedEpoch AI254040191fa014eb1b57eababe019d7f91a21d98418824d3d665f627a563575d
Factual source record; not the publisher page
OpenAI, Oracle and Vantage Data Centers announce Stargate data center site in Wisconsin
Archived copy
W.Media
Trade publication
Imported: Record, Metric: Buildings, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Power Capacity, Milestone: Announced, Milestone: Fully Operational, Role: Developer, Tenant claimsource-terms-not-recordedW.Mediaff502a263e64f1b06af6ba795f6d0eecb34208746bd2ab3de60f27fd0fdf0db7
Factual source record; not the publisher page
Oracle AI data-center locations page: dated construction media captions (captured 16 October 2026)
Archived copy
Oracle
Company disclosure
Physical statusnot statedall-rights-reservedOracle35da74fdde71efad4d88d252b0d91ffd7fb4f72e89dc3699afdbae1cec5e6eb7
Retained source material; see source provenance
Oracle blog: 'A Responsible Path Forward for Project Lighthouse' (16 September 2026)
Archived copy
Oracle Corporation
Company disclosure
Grid connection contextall-rights-reservedOracle Corporation3646d158464b0d89d823fe1bef81ffacd48222b9046496c510cbe292057a2471
Retained source material; see source provenance
Oracle sues Wisconsin utility regulators over financial requirements for data centers
Archived copy
Wisconsin Public Radio
News
Imported: Record, Metric: Investment, Milestone: Othersource-terms-not-recordedWisconsin Public Radio6c244224df38405e26c80f45759809fba4f691cc1273aa66361eb5a4f88b40a5
Factual source record; not the publisher page
Port Washington (Lighthouse) Data Center Campus
Archived copy
Vantage Data Centers
Company disclosure
Source location contextnot statedall-rights-reservedVantage Data Centers7eed1e19447c03d97e3da15684de3eb7a1ceb12e61dbec110e3ecb638ecebec3
Retained source material; see source provenance
Port Washington Data Center Proposal
Archived copy
Wisconsin Department of Natural Resources
Government record
Physical statusnot statedpublic-government-recordWisconsin Department of Natural Resources4502f68999eb5a1b3e0cdb70084e588798f7d2960271642691db62faddd6a396
Retained source material; see source provenance
Vantage chief calls complex large even by its standards
Archived copy
Ozaukee Press
News
Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Floor Area, Metric: Investment, Metric: Jobs Permanent, Metric: Land Area, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Power Source: Solar, Role: Developer, Role: Utilitysource-terms-not-recordedOzaukee Pressff1710f2aeb5f871c1fbde22d4ea04d79faaabe3b687730f295b46eb567260ce
Factual source record; not the publisher page
Vantage Lighthouse Campus (lighthousewisconsin.com): 'Construction Updates - Building Progress and Timelines', version modified 19 October 2026 ('October Summary')
Archived copy
Vantage Data Centers (Vantage Lighthouse Campus website)
Company disclosure
Physical statusall-rights-reservedVantage1ecb96ff62970b11b8d008f4ea8c1e048cd9717cc01eabf4ec2f9a214ac38223
Retained source material; see source provenance
We Energies strikes deal to power Oracle data center with nuclear energy
Archived copy
Wisconsin Watch
News
Imported: Geometry, Imported: Record, Milestone: Other, Power Source: Grid, Power Source: Nuclear, Tenant claim, Role: Utilitysource-terms-not-recordedWisconsin Watche5d7433e92a84d2de46a8b5530b9cc1da6c374ac6dfc7d9370219c78aad99a31
Factual source record; not the publisher page
Wisconsin DNR Lighthouse Data Center environmental review page
Archived copy
Wisconsin Department of Natural Resources
Government record
Geometrynot statedpublic-government-record-fact-extraction-onlyWisconsin Department of Natural Resources7452e95750d278a03a1e803d08280b325cc0013f9e842d52da8e637e5f9ca679
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Vantage Lighthouse Port Washington Data Center Campus [site vcc-site-d272a722ca415c1be654]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-d272a722ca415c1be654/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction