NEXTDC S7 Sydney

Announced

Australia · 1 project · Last reported

Summary

NEXTDC plans a hyperscale data center campus of about 550 MW on roughly 258,000 square meters of land it agreed to buy in Eastern Creek, western Sydney, in October 2024, subject to development approval. In December 2025 NEXTDC signed a memorandum of understanding with OpenAI to collaborate on planning, developing and operating the S7 campus and a large GPU supercluster as part of OpenAI's program for countries, with a first phase expected in the second half of 2027 if approvals are secured. NEXTDC's site still lists S7 as in planning.

Source record as of 2025-12-05 · Details and sources

NEXTDC’s S7 data centre at 1 Kangaroo Avenue, Eastern Creek, remains a proposal in NSW State significant development planning (SSD-113934740). Assessment requirements were issued to NEXTDC Limited on 6 May 2026 and modified on 31 August 2026. They describe three two-storey buildings with an operational capacity of 612 MW. No consent or construction is recorded. evidence

NSW Department of Planning, Housing and Infrastructure · published 2026-08-31

Location

The interactive map needs JavaScript. Display anchor: -33.80590, 150.85000 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Town or locality reference only; the facility position is not established.

Projects (1)

NEXTDC S7 Sydney

Announced last observed as of · Project announcement

This record reports announced as of 2025-12-05. NEXTDC; NEXTDC

Location: Eastern Creek, New South Wales, AU. NEXTDC names the suburb of Eastern Creek, about 45 km west of the Sydney CBD, without a street address; coordinates are the OpenStreetMap Nominatim centroid of the suburb. NEXTDC; NEXTDC; NEXTDC

Use: Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacityabout 550 MWPlanned · Campus · Unspecified2024-10-17Subject to development approval.NEXTDC
Power capacityat least 550 MWPlanned · Campus · It load2026-10Undated NEXTDC facility page, viewed October 2026, lists 550MW+ of IT capacity.NEXTDC
Land areaabout 25.8 hectaresAcquired · Campus2024-10-17Reported as about 258,000 square meters of developable land.NEXTDC

Companies and organizations

NameRoleNotesSources
NEXTDCDeveloperNEXTDC; NEXTDC; NEXTDC
NEXTDCOwnerAgreed in October 2024 to buy the land for about A$353 million before taxes and costs, with parcels to settle progressively across FY25; the December 2025 release refers to it as NEXTDC's S7 site.NEXTDC; NEXTDC
OpenAIDeveloperUnder a December 2025 memorandum of understanding, OpenAI and NEXTDC would collaborate on planning, developing and operating the campus and a GPU supercluster; the release does not describe a definitive agreement.NEXTDC

Timeline

DateEventActual or plannedNotesSources
2024-10-17Site acquiredActualPurchase agreement announced at about A$353 million before taxes and costs, with land parcels to settle progressively across FY25 subject to conditions.NEXTDC
2025-12-05OtherActualNEXTDC and OpenAI signed a memorandum of understanding for the S7 campus and a GPU supercluster.NEXTDC
2027-H2First operationalPlannedFirst phase expected in the second half of calendar 2027, subject to approvals.NEXTDC
Sources for these details
Companies
  • Developer: NEXTDC (unknown scope) evidence
  • Developer: NEXTDC (unknown scope) evidence
  • Developer: NEXTDC (unknown scope) evidence
  • Owner: NEXTDC (unknown scope) evidence
  • Owner: NEXTDC (unknown scope) evidence
  • Developer: OpenAI (unknown scope) evidence
Source and location review
Status source
NSW Planning Secretary’s additional SEARs: NEXTDC S7 Data Centre, Eastern Creek (SSD-113934740) evidence row
NSW Department of Planning, Housing and Infrastructure · published 2026-08-31 · Government record
Locator
Locality reference only · Compiled location reference · locality evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 57 days before the data update on 2026-10-27

Location details
Coordinates
-33.80590, 150.85000
Geometry licence
source-terms-not-recorded
Use scope
Locality reference only
Scope class
locality
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
NEXTDC names the suburb of Eastern Creek, about 45 km west of the Sydney CBD, without a street address; coordinates are the OpenStreetMap Nominatim centroid of the suburb.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
22e3e100

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for NEXTDC S7 Sydney
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
NEXTDC Announces Massive Expansion Plans with Acquisition of S7 Data Centre Site in Sydney
Archived copy
NEXTDC
Company disclosure
Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Milestone: Site Acquired, Role: Developer, Owner claimsource-terms-not-recordedNEXTDC0e600b1765421eb9cf36b2a978312fda75124f75a23e88bd575c4ae5a1cc4925
Factual source record; not the publisher page
NEXTDC to Join OpenAI in Australia as an Infrastructure Partner
Archived copy
NEXTDC
Company disclosure
Imported: Geometry, Imported: Record, Imported: Status, Milestone: First Operational, Milestone: Other, Role: Developer, Owner claimsource-terms-not-recordedNEXTDC30493bbbc20752eb499523e6183d3ff04f8392eb7bcc2e34318bd7f6f127b704
Factual source record; not the publisher page
NSW Planning Secretary’s additional SEARs: NEXTDC S7 Data Centre, Eastern Creek (SSD-113934740)
Archived copy
NSW Department of Planning, Housing and Infrastructure
Government record
Project announcementCC-BY-4.0© State of New South Wales and Department of Planning, Housing and Infrastructure 2026b3459295eb0a10fd5e34fc84fed4c2bd056ac3c61fb9543c75758d9a40cce3ef
Retained source material; see source provenance
S7 Sydney Data Centre
Archived copy
NEXTDC
Company disclosure
Imported: Geometry, Imported: Record, Imported: Status, Metric: Power Capacity, Role: Developernot statedsource-terms-not-recordedNEXTDCc56ff6d8c73949ebab0fc1b4dcea56018e68fc0304b6c3b6aafcb35fb8837d4f
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). NEXTDC S7 Sydney [site vcc-site-dd0f231b23c8dd96495b]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-dd0f231b23c8dd96495b/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction