Volcano Engine Inner Mongolia Horinger Compute Centre — Phase 1 Campus

Completed

China · 1 project · Last reported

Summary

On 27 October 2026 the Horinger New Area planning and construction bureau reported that the 10-1 data-centre machine-room building works of the Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 A project had recently completed their construction completion-acceptance filing (竣工验收备案). The works are the 10-1 machine-room building, 32,138.14 m2 of floor area, with a stated IT capacity of 26 MW. The record covers construction completion of building 10-1 only: operation is described as a future step and is not asserted, the 26 MW is a design figure and not installed load, and the other Phase 1 A machine-room buildings (10-2 to 10-4), the separately accepted integrated building, the 110 kV substation, Phase 1 B (10-5 to 10-8) and the separate Phase 2 park are not included. evidence

Planning and Construction Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区规划建设局) · published 2026-10-27

Location

The interactive map needs JavaScript. Display anchor: 40.58596, 111.84670 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 A — 10-1 data-centre machine-room building

Completed last observed as of · Authoritative status update

Earlier version (67 pages) of the same EIA form, with the same printed coordinate. Attachment 2 (PDF page 57) reproduces the Horinger New Area Management Committee project filing notice (project code 2409-150123-89-01-454670; builder Hohhot Saibei Hongcheng Technology Co., Ltd.; location Yungu area, east to Shengshi Road (盛世路), south to Yungu Heng 28 Road (云谷横28路), west to Shenglian Road (盛联路), north to Yunkun Avenue (云鲲大街); 259,933.23 m2 of land, of which Phase 1 A 119,698.23 m2 and Phase 1 B 140,235 m2; Phase 1 A four new machine-room buildings (128,274.36 m2), one integrated building (9,406.59 m2) containing the new boiler room, one 110 kV substation and ancillary works; Phase 1 B four machine-room buildings; planned construction 1 October 2024 to 30 October 2026). Attachment 3 (PDF pages 58-59) reproduces the land planning conditions (class 1 industrial land west of the existing parcel line, bounded by Yungu Heng 28 Road, Shenglian Road and Yunkun Avenue) and a parcel plan (宗地图) on the 2000 national geodetic coordinate system with a ten-point boundary-coordinate table. Figure 4 (PDF page 65) is the Phase 1 general layout: machine-room buildings 10-1, 10-2 and 10-3 in the western column, 10-4 south of the integrated building, and the boiler house inside the integrated building at the north of the western half, immediately east of 10-1; 10-5 to 10-8 form the eastern half. Surveyor names printed on the parcel plan are not reproduced. evidence

Hohhot Ecology and Environment Bureau (呼和浩特市生态环境局) · publication date not stated

Acceptance notice dated 18 June 2025: project name Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 project; location Horinger County, Hohhot; builder Hohhot Saibei Hongcheng Technology Co., Ltd.; the full EIA report form is attached (the accepted-version PDF used as the locator source). An acceptance notice is not an approval and an environmental approval for a boiler house is not development consent. evidence

Hohhot Ecology and Environment Bureau (呼和浩特市生态环境局) · published 2025-06-18

Published 12 December 2025 (PubDate meta 2025-12-12 16:22): the Phase 1 A integrated building of the Volcano Engine Inner Mongolia Horinger Compute Centre recently passed completion acceptance; the item repeats the four boundary roads (Shengshi Road east, Yungu Heng 28 Road south, Shenglian Road west, Yunkun Avenue north). Identity context: it ties the integrated building, which contains the EIA's boiler house, to Phase 1 A. Outside the window and a different building, so not a status observation for 10-1. evidence

Inner Mongolia Horinger New Area Planning and Construction Bureau (内蒙古和林格尔新区规划建设局) · published 2025-12-12

EIA report form for the indoor 110 kV substation (4 x 80 MVA) of the Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 A project. It places the station in the south-west corner of the Phase 1 A plant area (厂区内西南角), prints its centre as 40 deg 35 min 0.462 s N, 111 deg 50 min 43.120 s E, and gives four station corner points in table 2-4. Used only as an independent cross-check of the Phase 1 A parcel and coordinate frame: all four corner points and the printed centre fall inside the Phase 1 A parcel computed from the CGCS2000 parcel plan, the corners at its south-west corner (0.5-36 m from the parcel boundary), about 300-410 m south-west of the boiler-house point. The printed centre lies about 78 m from the centroid of the four corners (an internal inconsistency of the report; neither is used as the locator). evidence

Inner Mongolia Autonomous Region Department of Ecology and Environment · published 2025-02-26

Companies
  • Owner: Hohhot Saibei Hongcheng Technology Co., Ltd. (呼和浩特市塞北红城科技有限公司) (current) evidence
  • User: Volcano Engine (火山引擎) (intended) evidence
Source and location review
Status source
Horinger New Area news item: 'Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 A project 10-1 data-centre machine-room building works complete their completion-acceptance filing' (火山引擎内蒙古和林格尔算力中心一期A项目10-1数据中心机房楼工程完成竣工验收备案), 27 October 2026 evidence row
Planning and Construction Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区规划建设局) · published 2026-10-27 · Government record
Locator
Campus locator · Official source · official_eia_on_campus_boiler_house_point_parcel_checked evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 0 days before the data update on 2026-10-27

Location details
Coordinates
40.58596, 111.84670
Geometry licence
all-rights-reserved
Use scope
Campus locator
Scope class
official_eia_on_campus_boiler_house_point_parcel_checked
Authority
Official source
Source entity
Campus
Method
official_eia_geographic_dms_point_transcription_with_cgcs2000_parcel_and_imagery_check
Derivation
direct_geometry
Precision scope
EIA point of the Phase 1 A gas boiler house inside the integrated building, which lies at the north of the Phase 1 A parcel, immediately east of building 10-1. The point is inside the Phase 1 A parcel computed from its CGCS2000 parcel plan, 54 m from the parcel boundary and 155 m from the parcel centroid, and about 165 m east-north-east of the visual centre of building 10-1. It locates the Phase 1 A campus of the compute centre; it is not the footprint or centre of building 10-1, nor an entrance, and it does not locate Phase 1 B (east of Phase 1 A) or the separate Phase 2 park.
Horizontal uncertainty
Not reported

The report states no datum or positional accuracy. The WGS84/CGCS2000 reading is supported by the point lying inside the Phase 1 A parcel computed from the parcel plan's CGCS2000 boundary coordinates and by the parcel's agreement with independent Esri imagery of unstated accuracy and date (manual visual comparison, roughly 10 m). The point marks the integrated-building block about 165 m from the centre of building 10-1. Decimal places are transcription precision, not accuracy.

Geometry evidence
2130cbd0

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Volcano Engine Inner Mongolia Horinger Compute Centre — Phase 1 Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Environmental impact report form (accepted version): Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 project, gas boiler house (火山引擎内蒙古和林格尔算力中心一期项目环境影响报告表), attached to the Hohhot Ecology and Environment Bureau acceptance notice of 18 June 2025
Archived copy
Hohhot Ecology and Environment Bureau (呼和浩特市生态环境局)
Environmental assessment document
Geometry, Owner claimnot statedall-rights-reserved呼和浩特市生态环境局; report form prepared for 呼和浩特市塞北红城科技有限公司68137319695787cf288b09c756bd599374b09a89e0c6766b781905b3eb62dd22
Retained source material; see source provenance
Environmental impact report form (earlier publicised version with attachments and figures): Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 project gas boiler house, attached to the Hohhot Ecology and Environment Bureau acceptance notice of March 2025
Archived copy
Hohhot Ecology and Environment Bureau (呼和浩特市生态环境局)
Environmental assessment document
Site and project identitynot statedall-rights-reserved呼和浩特市生态环境局; report form prepared for 呼和浩特市塞北红城科技有限公司34883c10c49b952dae04cf32b9aba01509000f05e15a09ccb12c0d3e83615337
Retained source material; see source provenance
Environmental impact report form: Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 A project 110 kV substation (火山引擎内蒙古和林格尔算力中心一期A项目110kV变电站工程环境影响报告表), Inner Mongolia Department of Ecology and Environment radiation-EIA approval-result publicity of 26 February 2025
Archived copy
Inner Mongolia Autonomous Region Department of Ecology and Environment
Environmental assessment document
Site and project identityall-rights-reservedInner Mongolia Autonomous Region Department of Ecology and Environmentf9797dc28eff21b9ace520ccd242427ef03c94599f49e7d7173fcca043f3290c
Retained source material; see source provenance
Esri World Imagery EPSG:4326 export around the Volcano Engine Horinger Phase 1 A parcel (request bbox 111.8395-111.8545E, 40.5800-40.5900N)
Archived copy
Esri
Map feature
Site and project identitynot statedall-rights-reservedEsri, Maxar, Earthstar Geographics and the GIS user community (World Imagery)c6a3574a0119df9b9af931682225eaf2661c21ae64e41533ae231ab782eca47c
Retained source material; see source provenance
Hohhot Ecology and Environment Bureau: acceptance notice for the EIA document of the Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 project (关于火山引擎内蒙古和林格尔算力中心一期项目环境影响评价文件受理情况公示)
Archived copy
Hohhot Ecology and Environment Bureau (呼和浩特市生态环境局)
Government record
Site and project identityall-rights-reserved呼和浩特市生态环境局3188e504ea20deea7e90b2630c06e1b307b7dc66ed3a49e1174d5212ff66333d
Retained source material; see source provenance
Horinger New Area major-project information: integrated building of the Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 A project passes completion acceptance (火山引擎内蒙古和林格尔算力中心一期A项目综合楼顺利通过竣工验收), 12 December 2025
Archived copy
Inner Mongolia Horinger New Area Planning and Construction Bureau (内蒙古和林格尔新区规划建设局)
Government record
Site and project identityall-rights-reserved内蒙古和林格尔新区规划建设局, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn)44b652fb2f48f01a578803df526ecc55c3aba91cca9c25ccadf8f39969f2c777
Retained source material; see source provenance
Horinger New Area news item: 'From WAIC to Inner Mongolia Horinger New Area: three looks at the compute acceleration in the free trade zone' (从WAIC到内蒙古和林格尔新区:“三看”自贸试验区里的算力“加速度”), 10 August 2026
Archived copy
Inner Mongolia Horinger New Area Party-Mass Service Center (内蒙古和林格尔新区党群服务中心)
Government record
Site and project identity, Physical status, Operator claimall-rights-reserved内蒙古和林格尔新区党群服务中心, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn)6cccbcc8c8de9c82f37e7af13ba3a6ae74ba5c35b18905bc478a8d386d81ff15
Retained source material; see source provenance
Horinger New Area news item: 'Volcano Engine Inner Mongolia Horinger Compute Centre Phase 1 A project 10-1 data-centre machine-room building works complete their completion-acceptance filing' (火山引擎内蒙古和林格尔算力中心一期A项目10-1数据中心机房楼工程完成竣工验收备案), 27 October 2026
Archived copy
Planning and Construction Bureau of the Hohhot Area of the Inner Mongolia Pilot Free Trade Zone and Horinger New Area (自贸试验区呼和浩特片区、和林格尔新区规划建设局)
Government record
Physical status, User claimall-rights-reserved自贸试验区呼和浩特片区、和林格尔新区规划建设局, via the Horinger New Area Management Committee website (hlgena.huhhot.gov.cn)d75a551cd23680cff10d153497858f225b247d0678bc55b6b77f4781e29d4183
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Volcano Engine Inner Mongolia Horinger Compute Centre — Phase 1 Campus [site vcc-site-f59d2f5037e6cf9243dd]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-f59d2f5037e6cf9243dd/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction