Meta El Paso Data Center

Under construction

United States · 1 project · Last reported

Summary

AI-oriented Meta campus on roughly 1,000 acres in northeast El Paso, Texas, off Stan Roberts Sr. Avenue near US 54. Announced in October 2025 as a USD 1.5 billion project able to scale to 1 GW, it rose to USD 10 billion or more of Meta investment in 2026. In July 2026 Meta placed it in a joint venture 80% owned by BlackRock-managed funds, with a total development cost of about USD 14 billion and capacity due to start coming online in 2028. El Paso Electric has proposed a 366 MW modular gas plant beside the campus; in September 2026 state judges recommended approving it only if ratepayers do not bear its costs.

Source record as of 2026-09-24 · Details and sources

Location

The interactive map needs JavaScript. Display anchor: 31.99404, -106.36316 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (1)

Meta El Paso Current Development

Under construction last observed as of · Authoritative status update

This record reports under construction as of 2026-09-24. Meta Platforms; Inside Climate News

Location: El Paso, El Paso County, Texas, US. Sources place the campus in northeast El Paso off Stan Roberts Sr. Avenue and US 54. Coordinates are a Nominatim point on Stan Roberts Sr. Avenue near that junction, not the parcel centroid. Construction Reporter; KFOX14

Use: Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity1,000 MWPlanned · Campus · Unspecified2026-07Meta first said the site could scale to 1 GW; later reporting and the joint venture release describe 1 GW of compute capacity. IT versus facility scope is not stated.FOX 26 Houston; Silicon UK; Meta Platforms
Power capacity366 MWPlanned · Campus · Onsite generation2026-09-24El Paso Electric's proposed McCloud gas plant on an adjacent site, still awaiting a Public Utility Commission of Texas decision.Construction Reporter; Inside Climate News
Investment1,500,000,000 USDAnnounced · Campus2025-10-15FOX 26 Houston
Investment10,000,000,000 USDReported · Campus2026-03-30Reported as Meta's planned spending after the increase from USD 1.5 billion.Silicon UK
Investmentmore than 10,000,000,000 USDAnnounced · Campus2026-07Meta's own investment commitment.Meta Platforms; Meta Platforms
Investmentabout 14,000,000,000 USDReported · Campus2026-07Total development cost of the Meta and BlackRock joint venture for buildings and long-lived power, cooling and connectivity infrastructure.Meta Platforms
Land areaabout 1,000 acresReported · Campus2026-01-20Construction Reporter
Jobs constructionup to 1,800 countPlanned · Phase · Initial phase2025-10-15Peak construction workforce for the initial phase.FOX 26 Houston
Jobs constructionmore than 4,000 countPlanned · Campus2026-07Peak construction workforce; the July 2026 release said more than 2,300 workers were already on site.Silicon UK; Meta Platforms; Meta Platforms
Jobs permanentabout 100 countPlanned · Campus2025-10-15FOX 26 Houston
Jobs permanentabout 300 countPlanned · Campus2026-07Silicon UK; Meta Platforms; Meta Platforms

Companies and organizations

NameRoleNotesSources
Meta PlatformsDeveloperProvides construction management, administrative and property management services to the joint venture.FOX 26 Houston; Meta Platforms
Meta PlatformsOwnerRetains a 20% stake in the joint venture.Meta Platforms
Meta PlatformsTenantInitial sole occupant, with leases of a four-year initial term and four extension options for a potential 20-year term.Meta Platforms
BlackRock (managed funds)OwnerFunds managed by BlackRock hold 80% of the joint venture announced in July 2026.Meta Platforms
El Paso ElectricUtilityConstruction Reporter; Meta Platforms
City of El PasoGovernmentApproved tax abatement and economic development agreements for the project.KFOX14

Timeline

DateEventActual or plannedNotesSources
2025-10-15AnnouncedActualFOX 26 Houston
2025-H2Construction startedActualReported as breaking ground in late 2025.Silicon UK
2026-03Expansion announcedActualReported on 2026-03-30: Meta's planned investment raised from USD 1.5 billion to USD 10 billion.Silicon UK
2026-07OtherActualJoint venture with BlackRock-managed funds announced to develop and own the campus.Meta Platforms
2026-09OtherActualAdministrative law judges proposed that the Public Utility Commission of Texas approve the McCloud gas plant only if ratepayers do not bear its capital and operating costs; no commission vote had been scheduled.Inside Climate News
2028First operationalPlannedCapacity is expected to begin coming online in 2028.Silicon UK; Meta Platforms

Power supply

TypeDescriptionSources
GridMeta says it planned its energy needs with El Paso Electric and pays the full cost of the energy and infrastructure needed to serve the data center.Meta Platforms
Natural gas onsiteEl Paso Electric proposed the 366 MW McCloud plant on about 31 acres next to the campus, made up of 813 modular 450 kW gas generators supplied by Enchanted Rock; it would serve only Meta for its first five years. Reported cost estimates differ (USD 473 million in January 2026, USD 499 million in September 2026), and a state utility commission vote was still pending in late September 2026.Construction Reporter; Inside Climate News

Meta's joint venture release (s5) displays both 27 and 28 July 2026, so only the month is recorded. Meta's fact sheet PDF (s7) shows no publication date; its embedded file creation date is 2026-09-01.

Sources for these details
Companies
  • Developer: Meta Platforms (unknown scope) evidence
  • Developer: Meta Platforms (unknown scope) evidence
  • Owner: Meta Platforms (unknown scope) evidence
  • Tenant: Meta Platforms (unknown scope) evidence
  • Owner: BlackRock (managed funds) (unknown scope) evidence
  • Utility: El Paso Electric (unknown scope) evidence
  • Utility: El Paso Electric (unknown scope) evidence
  • Government: City of El Paso (unknown scope) evidence
Source and location review
Status source
Meta July 28 El Paso physical construction observation evidence row
Meta · published 2026-07-28 · Company disclosure
Locator
Campus locator · Community source · community_named_campus_reference_point evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 91 days before the data update on 2026-10-27

Location details
Coordinates
31.99404, -106.36316
Geometry licence
CC-BY-SA-2.0, ODbL-1.0, no-open-license-asserted
Use scope
Campus locator
Scope class
community_named_campus_reference_point
Authority
Community source
Source entity
Campus
Method
nominatim_exact_named_campus_reference_point
Derivation
Use the single exact-name community feature, verify its source object geometry, and emit the unchanged service longitude/latitude in GeoJSON order.
Precision scope
Source way explicitly says boundary very approximate. The returned point is only a broad campus locator consistent with the municipal north-of-Stan-Roberts, west-of-US54 description; neither the rectangle nor its slightly cross-state northern edge is selected as a legal boundary. No survey, exact building centroid, active construction footprint or bounded numerical accuracy is claimed.
Horizontal uncertainty
Not reported

Community mapper and geocoder provide no bounded horizontal accuracy; coordinate decimal places are not measurement precision.

Geometry evidence
047b4c1b 52580d24 5492ab7f 816746dd 90966722

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Meta El Paso Data Center
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
El Paso Electric Announces Plans for 366 Megawatt Electric Plant to Support Meta Data Center
Archived copy
Construction Reporter
Trade publication
Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Power Source: Natural Gas Onsite, Role: Utilitysource-terms-not-recordedConstruction Reporter72818f4027cc6b87e4d33775ca744925a4c02e3b19460406fe48a317ce0677e8
Factual source record; not the publisher page
El Paso leaders get update on Meta data center project, city cites enforceable agreements
Archived copy
KFOX14
News
Imported: Geometry, Imported: Record, Role: Governmentsource-terms-not-recordedKFOX1422762adf8c89e4471439705f414bae037cf7063c160abe9402240a202e705619
Factual source record; not the publisher page
El Paso municipal Meta and Wurldwide campus identity
Archived copy
City of El Paso
Government record
Geometry identity context, Site distinctness contextnot statedall-rights-reservedCity of El Paso0953bb349d8fe57516316f3230fb2abc5a3365b685394f6634703590f3e3a3b5
Retained source material; see source provenance
Exact named Meta El Paso Data Center Nominatim point
Archived copy
OpenStreetMap contributors via Nominatim
OpenStreetMap
Site distinctness context, Geometrynot statedODbL-1.0OpenStreetMap contributors via Nominatimca177512cb6cc28ac6c912853387d38829e10c0899c8cd3eeeeab4ec2fb505c5
Retained source material; see source provenance
Meta Announces New Strategic Venture With BlackRock to Develop Data Center in El Paso
Archived copy
Meta Platforms
Company disclosure
Imported: Record, Imported: Status, Metric: Investment, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Power Capacity, Milestone: First Operational, Milestone: Other, Role: Developer, Owner claim, Tenant claimsource-terms-not-recordedMeta Platformsf3e96c82576b73ccecaa94a909be8fa0612f5394e1bab2bdfa2aafd23cf0ba4b
Factual source record; not the publisher page
Meta El Paso Data Center fact sheet
Archived copy
Meta Platforms
Company disclosure
Imported: Record, Metric: Investment, Metric: Jobs Construction, Metric: Jobs Permanent, Power Source: Grid, Role: Utilitynot statedsource-terms-not-recordedMeta Platforms28d350b94425ab7fef7e4a972c44a45661da8b211b23827e8d0e14ba2b4857a5
Factual source record; not the publisher page
Meta El Paso Data Center source object identity and geometry corroboration
Archived copy
OpenStreetMap contributors
OpenStreetMap
Site distinctness context, Geometrynot statedODbL-1.0OpenStreetMap contributorsa35838070fa8563610f33c4d955571bef0f2ec1000d5db8baf2baf958590bf44
Retained source material; see source provenance
Meta July 28 El Paso physical construction observation
Archived copy
Meta
Company disclosure
Geometry identity context, Site distinctness context, Physical statusall-rights-reservedMetadca3908508aca7e2125b19f0be9a08f9cb38a0d83f3006a9ed72c52f529b59ec
Retained source material; see source provenance
Meta Ramps Spending On El Paso Data Centre To $10bn
Archived copy
Silicon UK
Trade publication
Imported: Record, Metric: Investment, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Power Capacity, Milestone: Construction Started, Milestone: Expansion Announced, Milestone: First Operationalsource-terms-not-recordedSilicon UK56b3036860203bd566758df3005ad7cd2bf0daf8d3b3c946d4ba51d86071a41d
Factual source record; not the publisher page
Meta to spend $1.5 billion on AI data center in Texas
Archived copy
FOX 26 Houston
News
Imported: Record, Metric: Investment, Metric: Jobs Construction, Metric: Jobs Permanent, Metric: Power Capacity, Milestone: Announced, Role: Developersource-terms-not-recordedFOX 26 Houstonfa7f27f31c462389807d72863f180d2ba1782896b98315cda7b9fb986fe866b1
Factual source record; not the publisher page
Nominatim object geometry WGS84 datum
Archived copy
Nominatim project
Company disclosure
Site distinctness context, Geometrynot statedno-open-license-assertedNominatim project173fa7a8e032ccee5de4412e19d89149a898ee609c1f069253d78c444b7705a6
Retained source material; see source provenance
Nominatim returned point and object reference semantics
Archived copy
Nominatim project
Company disclosure
Site distinctness context, Geometrynot statedno-open-license-assertedNominatim project2b22abff55df61794873a6648149a09a46262c4f409578cb8d6823de3d6b5f7e
Retained source material; see source provenance
OpenStreetMap attribution and ODbL terms
Archived copy
OpenStreetMap Foundation
OpenStreetMap
Site distinctness context, Geometrynot statedCC-BY-SA-2.0OpenStreetMap Foundation6fb8c3041dd598f5d63befa6ef01badc313abbb41f76431e374eafb72723fac0
Retained source material; see source provenance
TDLR Project Seafox campus registration address
Archived copy
Texas Department of Licensing and Regulation
Government record
Geometry identity context, Site distinctness contextnot statedall-rights-reservedTexas Department of Licensing and Regulationb9b48024caf2b258ff109f3a515aef66827b82eb89c784ce36dd3e8aa5214c3d
Retained source material; see source provenance
Texas Electric Utility Only Considered Gas to Power $10 Billion Meta Data Center
Archived copy
Inside Climate News
News
Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Other, Power Source: Natural Gas Onsitesource-terms-not-recordedInside Climate Newscf9d08b4048f9629958ccbe8791e908de59845318fcf9b12b34ce39bed76d0b6
Factual source record; not the publisher page