CoreWeave Lancaster AI data center (Lancaster AI Hub)

This record covers several sites. It is not counted as an additional site or project.

Site records

AI data center development in Lancaster, Pennsylvania, on former LSC Communications printing plant sites, co-developed by Chirisa Technology Parks and Machine Investment Group with CoreWeave as tenant. In July 2025 CoreWeave said it intended to commit about 6 billion US dollars to equip an initial 100 MW facility expandable to 300 MW. Phase one reuses the plant at 216 Greenfield Road and was under construction by October 2025, targeting summer 2027. A new-build phase two of about 735,000 sq ft needed city land development approval; a site at 1375 Harrisburg Pike is also planned. A 4 billion US dollar joint venture with Blue Owl funds the campus.

This record reports under construction as of 2025-10-19. WITF (LNP | LancasterOnline)

Location: Lancaster, Lancaster County, Pennsylvania, US. City centroid from Wikipedia (s5). Sources give addresses at 216 Greenfield Road and 1375 Harrisburg Pike, but these were not geocoded, so the point is the city centroid rather than either site. CoreWeave; Government Technology (LNP via Tribune Content Agency); WITF (LNP | LancasterOnline); Wikipedia

Use: Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investmentmore than 6,000,000,000 USDAnnounced · Campus2025-07-15CoreWeave's intent to commit funds to equip the data center, as worded in its newsroom copy of the announcement.CoreWeave
Investmentup to 6,000,000,000 USDAnnounced · Campus2025-07-15The investor-relations copy of the same July 15, 2025 announcement words the commitment as up to 6 billion US dollars rather than more than 6 billion.CoreWeave
Investment4,000,000,000 USDReported · Campus2025-09-16Joint venture funding from Blue Owl-managed funds and affiliates of Chirisa Technology Parks and Machine Investment Group.Holland & Knight
Investment10,000,000,000 USDReported · Campus2025-10-19Total cost of the Lancaster AI Hub across the Greenfield Road and Harrisburg Pike sites as reported by LNP.WITF (LNP | LancasterOnline)
Investmentup to 2,500,000,000 USDReported · Phase · Phase two2025-10-19Cost to build and equip, including computer equipment.WITF (LNP | LancasterOnline)
Power capacity100 MWPlanned · Phase · Unspecified · Initial capacity2025-07-15CoreWeave
Power capacityup to 300 MWPlanned · Campus · Unspecified2025-07-15Potential expansion.CoreWeave
Floor area450,000 sq_ftPlanned · Phase · Phase one (216 Greenfield Road)2025-08-08Government Technology (LNP via Tribune Content Agency)
Floor area735,128 sq_ftPlanned · Phase · Phase two2025-10-19Two-story new building.WITF (LNP | LancasterOnline)
Jobs constructionabout 600 countPlanned · Campus2025-07-15CoreWeave
Jobs permanentabout 175 countPlanned · Campus2025-07-15About 70 at launch, growing to about 175 over time.CoreWeave

Companies and organizations

NameRoleNotesSources
Chirisa Technology ParksDeveloperCoreWeave; Holland & Knight; WITF (LNP | LancasterOnline)
Machine Investment GroupDeveloperNamed as co-developer in CoreWeave's announcement.CoreWeave; WITF (LNP | LancasterOnline)
Machine Investment GroupInvestorJoint venture partner in the 4 billion US dollar funding.Holland & Knight
Blue Owl CapitalInvestorFunds managed by Blue Owl are joint venture partners.Holland & Knight
CoreWeaveTenantCoreWeave; Holland & Knight; WITF (LNP | LancasterOnline)
CoreWeaveInvestorDescribed as having invested in the campus.Holland & Knight
PPLUtilityA new PPL substation and switchyard are proposed next to the phase two building.WITF (LNP | LancasterOnline)

Timeline

DateEventActual or plannedNotesSources
2025-07-15AnnouncedActualAnnounced at the Pennsylvania Energy and Innovation Summit in Pittsburgh.CoreWeave
2025Construction startedActualDemolition at the Greenfield Road phase one site was underway by early August 2025, and phase one was described as under construction in October 2025; it needed no land development plan because it reuses an existing building footprint.Government Technology (LNP via Tribune Content Agency); WITF (LNP | LancasterOnline)
2025-09-16OtherActual4 billion US dollar joint venture with Blue Owl-managed funds announced.Holland & Knight
2027First operationalPlannedPhase one completion targeted for summer 2027.Government Technology (LNP via Tribune Content Agency)
2027OtherPlannedDeveloper said phase two could be online by mid to late 2027, pending city planning commission land development approval.WITF (LNP | LancasterOnline)

Power supply

TypeDescriptionSources
GridGrid supply from PPL with a proposed new substation and switchyard; the developer says it is spending 200 million US dollars on grid upgrades.WITF (LNP | LancasterOnline)
OtherBackup generators for power outages, located mainly between the two Greenfield Road buildings; the fuel is not stated.WITF (LNP | LancasterOnline)

CoreWeave's two published copies of its July 15, 2025 announcement differ: the newsroom copy says more than 6 billion US dollars and the investor-relations copy says up to 6 billion; both are recorded. LNP puts the whole Lancaster AI Hub at 10 billion US dollars, a figure that may include equipment and both sites.