TBC Partners Cambois data centre campus

Site records

TBC Partners, a UK joint family office focused on energy transition and impact investments, said in January 2025 it had started developing data centres at Blyth and Didcot, describing them as two 300 MW projects with procured demand connections. In August 2026 it asked Northumberland County Council for a screening opinion on whether an environmental impact assessment is needed for a campus of about 12 hectares on Factory Road, Cambois, near the QTS campus. Construction would take about two years, with occupation and operation intended between 2030 and 2035. A full planning application had not been filed.

This record reports proposed as of 2026-08-18. BeBeez International (republishing DatacenterDynamics)

Location: Cambois, Northumberland, England, GB. The site is on Factory Road, Cambois, beside the A189 just south of the River Wansbeck. Nominatim did not resolve Factory Road, so the Cambois village centroid is used. BeBeez International (republishing DatacenterDynamics)

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity300 MWContracted · Campus · Grid connection2025-01TBC Partners describes two 300 MW projects, at Blyth and Didcot, and says both have procured 300 MW demand connections.TBC Partners
Power capacity300 MWPlanned · Campus · Unspecified2026-08-18Trade report says the Cambois campus could total 300 MW, citing TBC's website; full project details had not been published.BeBeez International (republishing DatacenterDynamics)
Land areaabout 12 hectaresReported · Campus2026-08-18BeBeez International (republishing DatacenterDynamics)

Companies and organizations

NameRoleNotesSources
TBC PartnersDeveloperTBC Partners; BeBeez International (republishing DatacenterDynamics)
Northumberland County CouncilGovernmentPlanning authority asked for the screening opinion.BeBeez International (republishing DatacenterDynamics)

Timeline

DateEventActual or plannedNotesSources
2025-01AnnouncedActualA January 2025 news item on TBC Partners' website says it had begun developing two UK data centres, at Didcot and Blyth.TBC Partners
2026-08OtherActualRequest to Northumberland County Council for an EIA screening opinion; no full planning application yet.BeBeez International (republishing DatacenterDynamics)
2030First operationalPlannedOccupation and operation intended from 2030 to 2035 after about 24 months of construction.BeBeez International (republishing DatacenterDynamics)