Second xAI supercomputer campus, in a building of about one million square feet on Tulane Road in the Whitehaven area of Memphis, near the Mississippi line, which xAI bought in 2025. The site has drawn little or no grid power and runs mainly on gas turbines at a former Duke Energy plant site about 1.5 miles away in Southaven, Mississippi. Mississippi regulators permitted 41 permanent turbines there in March 2026, and environmental and civil rights groups appealed the permit in April 2026. Analyst estimates put its IT load near 1 GW by mid-2026. Anthropic says it has GPU capacity here under an agreement with SpaceX.

This record reports partially operational as of 2026-10-05. Epoch AI; WMC Action News 5

Location: Memphis, Tennessee, US. Center of the OpenStreetMap building tagged 'xAI Macrohard Colossus 2' at 5420 Tulane Road, taken from this project's OpenStreetMap data center layer (no geocoder call); Cleanview gives the same address. MLGW describes the facility as on Tulane Road very near the Tennessee-Mississippi line. Memphis Light, Gas and Water; Cleanview

Use: Ai training

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacityabout 946 MWOperational · Campus · It load2026-06-15Epoch AI analyst estimate, not a company disclosure, from its June 15, 2026 satellite observation. Epoch projects about 1,531 MW of IT load in the first quarter of 2027, with a third building estimated to be complete in February 2027.Epoch AI
Power capacityabout 1,300 MWOperational · Campus · Onsite generation2026-05Cleanview count of about 59 temporary turbines totaling about 1.3 GW in mid-May 2026 imagery of the Southaven generation site (analyst estimate, not a company disclosure). Cleanview reports no utility power at Colossus 2.Cleanview
Power capacityabout 1,200 MWPermitted · Campus · Onsite generation2026-03-1041 permanent gas turbines permitted in March 2026 at the Southaven plant site. The 1.2 GW figure comes from Cleanview (analyst) and WMC; the permit coverage reviewed gives no capacity.Cleanview; WMC Action News 5; Mississippi Free Press
Power capacity260–1,100 MWPlanned · Campus · Grid connection2025-05-05MLGW received an initial, unstudied request for 260 MW and had discussed options from 260 MW to 1.1 GW; xAI had not filed a final request as of May 2025.Memphis Light, Gas and Water
Acceleratorsabout 550,000 countInstalled · Campus2026-05Cleanview figure (analyst estimate, not a company disclosure).Cleanview
Acceleratorsabout 440,000 countInstalled · Campus2026-06-15Epoch AI analyst estimate, not a company disclosure: about 110,000 B200 and 330,000 B300 chips. It differs from Cleanview's figure; both are kept.Epoch AI
Investmentabout 35,800,000,000 USDReported · Campus2026-10-05Epoch AI current capital cost estimate (analyst estimate, not a company disclosure); the page does not say what the figure includes.Epoch AI

Companies and organizations

NameRoleNotesSources
xAIDeveloperWMC Action News 5; Memphis Light, Gas and Water
SpaceXOwnerEpoch AI (analyst) lists the owner as SpaceXAI and WMC's July 2026 report refers to SpaceXAI; Anthropic describes its Colossus 2 capacity agreement as being with SpaceX. No company filing reviewed states ownership.Epoch AI; WMC Action News 5; Anthropic
AnthropicTenantAnthropic's May 2026 funding announcement cites an agreement with SpaceX for GPU capacity in Colossus 1 and Colossus 2; the share of Colossus 2 involved is not stated.Anthropic; Epoch AI
CursorTenantListed as a user by Epoch AI (analyst); reported but not confirmed by Cursor, xAI or SpaceX in the sources reviewed.Epoch AI
MZX Tech LLCPower supplierxAI affiliate that bought the former Duke Energy site at 2875 Stanton Road South, Southaven, and holds the Mississippi air permit for the turbines that power Colossus 2.DeSoto County News; Mississippi Free Press; Southern Environmental Law Center
Memphis Light, Gas and WaterUtilityServes the site with water and limited gas; as of May 2025 xAI had not filed a final request for grid power at Tulane Road.Memphis Light, Gas and Water
Mississippi Environmental Quality Permit BoardGovernmentApproved the Southaven turbine air permit on March 10, 2026.Mississippi Free Press

Timeline

DateEventActual or plannedNotesSources
2025-02-28Construction startedActualEpoch AI dates land clearing next to the existing building from satellite imagery (analyst estimate, not a company disclosure).Epoch AI
2025-03Site acquiredActualWMC reported in March 2025 that xAI was buying about one million square feet of property in southwest Memphis; by May 2025 MLGW said xAI had secured the Tulane Road facility.WMC Action News 5; Memphis Light, Gas and Water
2025-07OtherActualxAI affiliate MZX Tech bought the former Duke Energy plant site in Southaven, Mississippi; Cleanview identifies it as the generation site for Colossus 2.DeSoto County News; Cleanview
2025-10First operationalActualApproximate. Epoch AI's first nonzero compute estimate for the site, about 239 MW of IT load, is dated October 19, 2025 from satellite imagery (analyst estimate, not a company disclosure).Epoch AI
2026-03-10Permit approvedActualMississippi permit board approved 41 gas turbines at the Southaven plant site.Mississippi Free Press
2026-04-09OtherActualSELC filed an appeal of the Southaven turbine air permit on behalf of the NAACP, Young Gifted & Green and the Safe and Sound Coalition.Southern Environmental Law Center
2026-08OtherPlannedPlanned start of removing the 69 temporary Southaven turbines, to finish by July 2027 as a permanent 41-turbine plant replaces them.WMC Action News 5

Power supply

TypeDescriptionSources
Natural gas onsiteBehind-the-meter gas turbines at the former Duke Energy site in Southaven, Mississippi. Regulators permitted 41 permanent units in March 2026; WMC reported 69 turbines on site in July 2026, all to be removed by July 2027.Mississippi Free Press; WMC Action News 5; Cleanview
Battery storageEpoch AI observed a battery facility connected to the building by September 2025 (analyst observation).Epoch AI

MACROHARDRR, the adjacent xAI building just across the state line in Southaven, is tracked separately as xai-macrohardrr-southaven. Some coverage labels it as part of Colossus 2, and the analyst sources cited here do not say whether their Colossus 2 estimates include it, so analyst figures for the two may overlap. Capacity, GPU and cost figures from Epoch AI and Cleanview are analyst estimates, not company disclosures.