xAI MACROHARDRR data center (Southaven)

Site records

Third xAI data center in the Memphis area, made by retrofitting a warehouse of roughly 800,000 square feet that xAI bought in late 2025 in Southaven, Mississippi, just south of Colossus 2 across the state line. Mississippi's governor announced it in January 2026 as an investment of more than $20 billion, the largest economic development project in state history, supported by a state sales and use tax exemption and local fee-in-lieu agreements. Musk said it would lift Colossus training compute to about 2 GW, and a July 2026 report relaying his comments said it holds 220,000 NVIDIA GB300 GPUs.

This record reports operational as of 2026-07-31. WMC Action News 5

Location: Southaven, DeSoto County, Mississippi, US. Center of the OpenStreetMap building tagged 'xAI Macrohardrr' on Stateline Road West, taken from this project's OpenStreetMap data center layer (no geocoder call), about 0.5 km south of the Colossus 2 building. This matches Cleanview's address of 2400 Stateline Road, Southaven, and WREG's description of the warehouse as just south of Colossus 2. Office of Governor Tate Reeves; WREG (via Yahoo News); Cleanview

Use: Ai training

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investmentmore than 20,000,000,000 USDAnnounced · Campus2026-01-08Office of Governor Tate Reeves; WREG (via Yahoo News)
Floor areaabout 810,000 sq_ftUnder construction · Campus2026-01-08Size of the warehouse being retrofitted; Converge Digest and Cleanview give about 810,000 square feet and WREG gives 800,000.Converge Digest; Cleanview; WREG (via Yahoo News)
Accelerators220,000 countInstalled · Campus2026-07-31Elon Musk's figure as relayed by WMC in July 2026; not confirmed in a company filing. No Colossus 2 figure is repeated here.WMC Action News 5

Companies and organizations

NameRoleNotesSources
xAIDeveloperOffice of Governor Tate Reeves; WREG (via Yahoo News)
Mississippi Development AuthorityGovernmentApproved the project for the state Data Center Incentive sales and use tax exemption.Office of Governor Tate Reeves
City of SouthavenGovernmentSupports the project through a fee-in-lieu agreement.Office of Governor Tate Reeves
DeSoto CountyGovernmentSupports the project through a fee-in-lieu agreement.Office of Governor Tate Reeves

Timeline

DateEventActual or plannedNotesSources
2025-12Site acquiredActualMusk disclosed the purchase of an 800,000-square-foot Southaven warehouse on December 30, 2025; the governor's release says xAI bought an existing building for the project.WREG (via Yahoo News); Office of Governor Tate Reeves
2026-01-08AnnouncedActualOffice of Governor Tate Reeves; WREG (via Yahoo News)
2026-02First operationalPlannedTarget stated at the January 2026 announcement; no source reviewed confirms the actual start date.Office of Governor Tate Reeves; Converge Digest

Status is inferred from a July 2026 WMC report that calls Macro-harder an existing site equipped with 220,000 GB300 GPUs, relaying Elon Musk; no source reviewed confirms when operations began. Converge Digest labels the building 'Colossus 2 (MACROHARDRR)', and analyst estimates for Colossus 2 (xai-colossus-2-memphis) may include it; no Colossus 2 figure is repeated here. The 2 GW figure in the announcements refers to xAI's combined Colossus compute, not this building alone.

Related projects: xai colossus memphis, xai colossus 2 memphis