Applied Digital Polaris Forge 1 Campus
Operational Partially operational Under construction
United States · 3 projects · Last reported
Summary
Applied Digital Ellendale 180 MW data-center hosting facility — existing operations
Applied Digital's Form 10-Q for the quarter ended 31 August 2026, filed on 7 October 2026, reports that its 180 MW data-center hosting facility in Ellendale, North Dakota continued to operate at full capacity as of 31 August 2026, providing energized space to crypto-mining customers. This records operation of the hosting facility only. It does not concern the Polaris Forge 1 HPC buildings (separate projects on this site), does not establish the IT load actually drawn, and does not imply any conversion of the hosting facility to AI workloads; 180 MW is the company's stated facility size. evidence
Applied Digital Corporation · published 2026-10-07
Applied Digital Polaris Forge 1
Applied Digital's AI data center campus in Ellendale, North Dakota, leased entirely to CoreWeave under roughly 15-year leases covering 400 MW of critical IT load. The first 100 MW building came online in two 50 MW phases in October and November 2025, and the 150 MW second building came online in two 75 MW phases by October 2026, for 250 MW operating. A third 150 MW building (ELN-04) is under construction, financed through a bridge loan later refinanced with senior secured notes in June 2026.
Source record as of 2026-10-07 · Details and sources
Polaris Forge 1 Current Expansion
Applied Digital's 7 October 2026 results release states that the third HPC building at Polaris Forge 1 (150 MW) is in construction. Building 2's second 75 MW phase reached Ready for Service on 1 October, so the record's remaining campus construction is now the third building; the operating first building and the delivered Building 2 phases remain outside this project's scope. No completion of the remaining works is asserted. evidence
Applied Digital Corporation · published 2026-10-07
Location
The interactive map needs JavaScript. Display anchor: 46.01438, -98.57427 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Campus reference; individual project footprints are not mapped.
Projects (3)
Applied Digital Ellendale 180 MW data-center hosting facility — existing operations
Operational last observed as of · Authoritative status update
The annual report says the company operates hosting sites in Jamestown, North Dakota (a 106 MW facility) and Ellendale, North Dakota (a 180 MW facility) for a single crypto-mining customer, both at full capacity as of 31 May 2026. Its debt notes state that APLD Hosting, LLC, a wholly owned subsidiary, is the borrower of the Starion Term Loan secured by its interests in the master hosting and electric services agreements related to the Jamestown hosting facility; that APLD GPU-01, LLC's AI cloud computing services are serviced at the Jamestown hosting facility; and that APLD ELN-01 LLC is the borrower of the Starion Ellendale Loan. It names APLD ELN-02 LLC, APLD ELN-03 LLC and APLD ELN-02 C LLC as the landlords of the Polaris Forge 1 HPC buildings in Ellendale. Item 2 says the company owns its Polaris Forge and Delta Forge data centers and their land. evidence
Applied Digital Corporation · published 2026-07-29
Stutsman County (2025 roll, Fried Township, Section 17 T141N R63W): parcel 181741040, APLD HOSTING LLC, 2671 Hwy 20 SE, Jamestown, Auditor's Lot 17-2A within the SE1/4 less Lot 17-2C, commercial, one structure; parcel 181744040, APLD HOSTING LLC, 2683 Hwy 20 SE, Jamestown, Auditor's Lot 17-2B within the SE1/4 (21.72 acres), one structure; parcel 181741044, APLD GPU-01 LLC, Auditor's Lot 17-2C within the SE1/4 (2.72 acres), commercial, one structure. Dickey County (2024 roll, Ellendale Township, Section 04 T129N R63W): parcel 755550, APLD ELN-01, LLC, 9685 87th Ave SE, Outlot 4-1 in SE1/4 (40 acres, commercial structures 13,658,300); parcel 755000, APLD ELN-02 A LLC, 9663 87th Ave SE, Outlot 4-4 in SE1/4 (24.78 acres); parcel 755125, APLD ELN-02, LLC, Outlot 4-2 in SE1/4 except Outlot 4-4 (55.51 acres); parcel 755500, APLD ELN-02 Holdings, LLC, Outlot 4-3 in SE1/4 (41.11 acres); parcel 752000, APLD ELN-02 Holdings, LLC, S1/2 of NE1/4 and Government Lots 1 and 2 (154.37 acres). evidence
State of North Dakota (North Dakota GIS Hub) · published 2026-10-26
A statewide query of the tax-roll table for owner names containing APLD, Applied Digital or Applied Blockchain returns 12 parcels: five in Dickey County (APLD ELN-01, LLC; APLD ELN-02, LLC; APLD ELN-02 A LLC; two of APLD ELN-02 Holdings, LLC), four in Cass County (APLD FAR-01 LLC, Harwood) and three in Stutsman County (two of APLD HOSTING LLC at 2671 and 2683 Hwy 20 SE, Jamestown, and one of APLD GPU-01 LLC, all in Section 17, T141N R63W). No other APLD Hosting or GPU-01 parcel exists statewide. evidence
State of North Dakota (North Dakota GIS Hub) · published 2026-10-26
The parcel layer returns 28 polygons. Four of them (38021-8691010, -8691020, -8692010 and -8692050; 40.4, 40.0, 54.9 and 25.0 calculated acres) make up the SE1/4 of Section 4, T129N R63W: their union is one 160.2-acre polygon about 804 by 816 m that contains the existing Polaris Forge 1 campus point (-98.574269, 46.014383), 55 m from its centroid. The tax roll assigns the four outlots of that quarter section to APLD ELN entities. evidence
State of North Dakota (North Dakota GIS Hub) · published 2026-10-26
The table metadata (editingInfo dataLastEditDate 1792986356358, i.e. 2026-10-26T03:45:56Z) show that the tax-roll rows captured on 26 October 2026 were current to that edit; the table relates to the Parcels feature layer through UniqueGISID and carries owner, property address, legal description, deeded acres, structure values, tax-roll year and import date. evidence
State of North Dakota (North Dakota GIS Hub) · published 2026-10-26
- Companies
Source and location review
- Status source
- Applied Digital Corporation, Form 10-Q for the quarter ended August 31, 2026 (fiscal first quarter 2027), filed 7 October 2026 evidence row
Applied Digital Corporation · published 2026-10-07 · Regulatory filing - Locator
- Campus locator · Official source · official_constituent_permit_reference_point evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 57 days before the data update on 2026-10-27
Applied Digital Polaris Forge 1
Partially operational last observed as of · Reported status
Location: Ellendale, Dickey County, North Dakota, US. Town centroid of Ellendale from its Wikipedia coordinates (s9), which also places the town in Dickey County; the company sources name the town but give no street address or parcel. Applied Digital; Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing); Wikipedia
Use: Ai unspecified, Hpc
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 400 MW | Contracted · Campus · It load | 2025-10-27 | Critical IT load fully leased to CoreWeave at full buildout. | Applied Digital; Applied Digital; Applied Digital |
| Power capacity | 250 MW | Operational · Campus · It load | 2026-10-01 | Critical IT load operating across two buildings and 10 data halls after the second 75 MW phase of Building 2. | Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing) |
| Power capacity | 100 MW | Operational · Phase · It load · Building 1 | 2025-11-24 | Applied Digital | |
| Power capacity | 150 MW | Operational · Phase · It load · Building 2 | 2026-10-01 | Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing) | |
| Power capacity | 150 MW | Under construction · Phase · It load · Third HPC building (ELN-04) | 2026-10-07 | The May 2026 bridge-loan release and the October 2026 results call this the third AI data center at the campus, while the June 2026 notes release calls it the fourth building (ELN-04); the notes were to repay the bridge loan, so both refer to the same building. | Applied Digital; Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing) |
| Power capacity | up to 1,000 MW | Planned · Campus · Unspecified | 2025-06-02 | Long-term design ambition for the campus; the same release says more than 1 GW of power was in various stages of load study. | Applied Digital |
| Buildings | 3 count | Planned · Campus | 2025-11-24 | Number of buildings contracted to CoreWeave at the time of the release. | Applied Digital |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Applied Digital | Developer | Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing) | |
| CoreWeave | Tenant | Two leases for 250 MW of critical IT load were announced in June 2025 with an option on a further 150 MW; by October 2025 the company described the full 400 MW of critical IT load as leased to CoreWeave. | Applied Digital; Applied Digital; Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing) |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2025-06-02 | Other | Actual | Two leases with CoreWeave for 250 MW of critical IT load announced, with an option on 150 MW more; the release already described the second building as under construction. | Applied Digital |
| 2025-10-27 | First operational | Actual | First 50 MW phase of Building 1 reached ready for service. | Applied Digital |
| 2025-11-24 | Other | Actual | Second 50 MW phase brought Building 1 to its full 100 MW. | Applied Digital |
| 2026-05-04 | Other | Actual | Closing of a 300 million US dollar bridge facility to fund construction of the third AI building. | Applied Digital |
| 2026-07 | Other | Actual | First 75 MW phase of Building 2 reached ready for service; company materials give June 30 and July 1, 2026 for this step. | U.S. Securities and Exchange Commission (Applied Digital filing); Applied Digital |
| 2026-10-01 | Other | Actual | Second 75 MW phase completed Building 2, bringing the campus to 250 MW operating. | Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing) |
| 2027 | Other | Planned | Target year given in June 2025 for the third 150 MW building to be ready for service. | Applied Digital |
Related projects: applied digital polaris forge 2, applied digital polaris forge 3
Sources for these details
- Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota — Applied Digital; 2025-06-02 · Archived source
- Applied Digital Achieves Ready for Service for Phase 1 at Polaris Forge 1 Building 1 for CoreWeave — Applied Digital; 2025-10-27 · Archived source
- Applied Digital Completes Phase II Ready for Service at Polaris Forge 1, Fully Energizing First 100 MW Building — Applied Digital; 2025-11-24 · Archived source
- Applied Digital Announces $300 Million Senior Secured Bridge Facility — Applied Digital; 2026-05-04
- Applied Digital Announces Pricing of $1.59 Billion of Senior Secured Notes to fund the Fourth Building at Polaris Forge 1 — Applied Digital; 2026-06-09
- Applied Digital Brings an Additional 75 MW of AI Infrastructure Online at Polaris Forge 1 — Applied Digital; 2026-10-02
- Applied Digital Reports Fiscal First Quarter 2027 Results (Form 8-K exhibit) — U.S. Securities and Exchange Commission (Applied Digital filing); 2026-10-07
- Applied Digital Reports Fiscal Fourth Quarter and Full Year 2026 Results — Applied Digital; 2026-07-27
- Ellendale, North Dakota — Wikipedia; publication date not stated · Archived source
- Companies
Source and location review
- Status source
- Applied Digital Brings an Additional 75 MW of AI Infrastructure Online at Polaris Forge 1 evidence row
Applied Digital · published 2026-10-02 · Company disclosure - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 20 days before the data update on 2026-10-27
Polaris Forge 1 Current Expansion
Under construction last observed as of · Authoritative status update
Source and location review
- Status source
- Applied Digital Reports Fiscal First Quarter 2027 Results evidence row
Applied Digital Corporation · published 2026-10-07 · Company disclosure - Locator
- Campus locator · Official source · official_constituent_permit_reference_point evidence
- Source checks
Not reviewed against imagery not_
reviewed_ for_ core_ preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 20 days before the data update on 2026-10-27
Location details
- Coordinates
- 46.01438, -98.57427
- Geometry licence
- no-open-redistribution-license-asserted
- Use scope
- Campus locator
- Scope class
- official_constituent_permit_reference_point
- Authority
- Official source
- Source entity
- Campus
- Method
- NDDEQ_PDF_page18_NAD83_EPSG4269_to_EPSG4326_NAD83_to_WGS84_1
- Derivation
- official_constituent_permit_reference_point
- Precision scope
- Official reference coordinate for the ELN Building 1 backup-generator plant at the exact street address shared by PF1 campus leases. It locates the campus through a constituent plant, not the still-building project, building center or campus boundary. The permit is not current physical-status evidence. EPSG transformation is a no-op with nominal 4m transformation accuracy; total source positional accuracy is unknown.
- Horizontal uncertainty
Not reported
No source-specific numeric accuracy is supplied. Coordinate decimals and transformation agreement are not source positional accuracy.
- Geometry evidence
- dd0153fd
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Applied Digital Achieves Ready for Service for Phase 1 at Polaris Forge 1 Building 1 for CoreWeave Archived copy | Applied Digital Company disclosure | Imported: Record, Metric: Power Capacity, Milestone: First Operational, Tenant claim | source-terms-not-recorded | Applied Digital | 1fc6d503ddbf584c4dab3b423edaaf2d6fcde3d19f4d779ba62f684fb5e3c3b5Factual source record; not the publisher page | ||
| Applied Digital Announces $300 Million Senior Secured Bridge Facility Archived copy | Applied Digital Company disclosure | Imported: Record, Metric: Power Capacity, Milestone: Other | source-terms-not-recorded | Applied Digital | 22a865104100309b393924a26c5b52beba2aad366d374807634b18e4550249caFactual source record; not the publisher page | ||
| Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota Archived copy | Applied Digital Company disclosure | Imported: Geometry, Imported: Record, Metric: Power Capacity, Milestone: Other, Role: Developer, Tenant claim | source-terms-not-recorded | Applied Digital | be17455f39117001c2d564f2717d2cc318180409749a87e6b867acde256ebdbcFactual source record; not the publisher page | ||
| Applied Digital Announces Pricing of $1.59 Billion of Senior Secured Notes to fund the Fourth Building at Polaris Forge 1 Archived copy | Applied Digital Company disclosure | Imported: Record, Metric: Power Capacity | source-terms-not-recorded | Applied Digital | 6777765f5ab9b1b5b705fdde0b32bc5cb58737cd76f58e1ff62b5c6d2b752b36Factual source record; not the publisher page | ||
| Applied Digital Brings an Additional 75 MW of AI Infrastructure Online at Polaris Forge 1 Archived copy | Applied Digital Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Other | source-terms-not-recorded | Applied Digital | 39d60943eb8b3e8fdbd44380172df16f135655b9b6235ed0f2be3bb1b9a2c9c9Factual source record; not the publisher page | ||
| Applied Digital Completes Phase II Ready for Service at Polaris Forge 1, Fully Energizing First 100 MW Building Archived copy | Applied Digital Company disclosure | Imported: Record, Metric: Buildings, Metric: Power Capacity, Milestone: Other, Tenant claim | source-terms-not-recorded | Applied Digital | ff72d167f0c96c7af4c07de6908c3628c674b513fedd6fef9f009710f4753225Factual source record; not the publisher page | ||
| Applied Digital Corporation, Form 10-K for the fiscal year ended May 31, 2026, filed 29 July 2026 (PDF rendition on the issuer's investor site) Archived copy | Applied Digital Corporation Regulatory filing | Site and project identity | no-open-redistribution-license-asserted | Applied Digital Corporation | d5a1a8be0e23fe6ea3f315122f3eb265fc8da3aa53b7f42a2d3d17fd49653158Retained source material; see source provenance | ||
| Applied Digital Corporation, Form 10-Q for the quarter ended August 31, 2026 (fiscal first quarter 2027), filed 7 October 2026 Archived copy | Applied Digital Corporation Regulatory filing | Physical status, Operator claim | no-open-redistribution-license-asserted | Applied Digital Corporation | 13de68ee1d34a5e8ababd5a28bdbdb9a6b5a6e1486988adf3804a7f522b7bd40Retained source material; see source provenance | ||
| Applied Digital filed lease definitions bind PF1 campus to 9663 87th Avenue SE Archived copy | Applied Digital Corporation Company disclosure | Geometry identity context, Site distinctness context | no-open-redistribution-license-asserted | Applied Digital Corporation | bad9611ea0d79f84c9cdcfafcace3bc8ce7dc28719b0bdaba827fd48b9c23d64Retained source material; see source provenance | ||
| Applied Digital fiscal fourth-quarter 2026 operational update - Polaris Forge 1 Archived copy | Applied Digital Corporation Company disclosure | Geometry identity context, Site distinctness context, Physical status | no-open-redistribution-license-asserted | Applied Digital Corporation | 4595c173b9adad5bf1f4e071a8181301058cca4afb318f9e9b081122643b2db8Retained source material; see source provenance | ||
| Applied Digital PF1 phase delivery and Ellendale identity Archived copy | Applied Digital Corporation Company disclosure | Geometry identity context, Site distinctness context | no-open-redistribution-license-asserted | Applied Digital Corporation | c3bc3fb2cf33f34890f94ed0712e3544fadcb5b20aa4da1f58e12cd10e8d0d45Retained source material; see source provenance | ||
| Applied Digital Reports Fiscal First Quarter 2027 Results Archived copy | Applied Digital Corporation Company disclosure | Physical status | all-rights-reserved | Applied Digital Corporation | 800f8b057f347d0ebf3990e1e78e30d5d4969135f172932b7c7439a91bce393eRetained source material; see source provenance | ||
| Applied Digital Reports Fiscal First Quarter 2027 Results (Form 8-K exhibit) Archived copy | U.S. Securities and Exchange Commission (Applied Digital filing) Regulatory filing | Imported: Geometry, Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Other, Role: Developer, Tenant claim | source-terms-not-recorded | U.S. Securities and Exchange Commission (Applied Digital filing) | 8649985d76b4655f369c48afd3e9afdc2128154f81ae9067005f6808cd2a3119Factual source record; not the publisher page | ||
| Applied Digital Reports Fiscal Fourth Quarter and Full Year 2026 Results Archived copy | Applied Digital Company disclosure | Imported: Record, Milestone: Other | source-terms-not-recorded | Applied Digital | 5cbd5aa5b6cc064482b69db35e8293112479ee67e31fc3d03bb532daabdbc1d4Factual source record; not the publisher page | ||
| Ellendale, North Dakota Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | 9573bdc89dfb98c0939b160edcf67852ea1edba82b407cc75954d2384c8b8387Factual source record; not the publisher page | |
| NDDEQ Applied Digital ELN Building 1 permit application locator Archived copy | North Dakota Department of Environmental Quality Government record | Site distinctness context, Geometry | not stated | no-open-redistribution-license-asserted | North Dakota Department of Environmental Quality | 5af0ddbbae762d18f9f6b66fbf14f17d600e0d78d4b74a350b5b2e2634c69951Retained source material; see source provenance | |
| North Dakota GIS Hub statewide Parcels layer: Dickey County parcels around the Polaris Forge 1 campus point (Sections 3-5, 8-10, T129N R63W, and Sections 32-34, T130N R63W) Archived copy | State of North Dakota (North Dakota GIS Hub) Government record | Site and project identity | public-record-source-terms | North Dakota GIS Hub; Dickey County | be7209bc2235e5630642cc7b08a2bc8fbb903d6de42fcfdce482ce072732ebb6Retained source material; see source provenance | ||
| North Dakota GIS Hub statewide parcels, Parcels_TaxRoll table: APLD-owned parcels in Dickey and Stutsman counties with section, township and range Archived copy | State of North Dakota (North Dakota GIS Hub) Government record | Site and project identity, Owner claim | public-record-source-terms | North Dakota GIS Hub; county tax-roll data | e0f80b32329d7f4308a63918f97705e225fd989f25f5ab0daad09f77b1f26c89Retained source material; see source provenance | ||
| North Dakota GIS Hub statewide parcels, Parcels_TaxRoll table: statewide owner search for APLD, Applied Digital and Applied Blockchain entities Archived copy | State of North Dakota (North Dakota GIS Hub) Government record | Site and project identity | public-record-source-terms | North Dakota GIS Hub; county tax-roll data | 473c046cd27409af4c70bb5f31463b1cd14a670762f064b70c2b008506711b90Retained source material; see source provenance | ||
| North Dakota GIS Hub statewide parcels: Parcels_TaxRoll table metadata at retrieval Archived copy | State of North Dakota (North Dakota GIS Hub) Government record | Site and project identity | public-record-source-terms | North Dakota GIS Hub | c0ceff6bfaa60d7a3329740b2c0bb11ade6fe8b05dd3a60ba366e17fd56b7b62Retained source material; see source provenance |
Cite this site
Kyars, K. (2026). Applied Digital Polaris Forge 1 Campus [site vcc-site-0ac82fd201fa1878b892]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-0ac82fd201fa1878b892/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction