Applied Digital Polaris Forge 2

Site records

Applied Digital AI data center campus near Harwood in Cass County, North Dakota, on more than 900 acres. Announced in August 2025 as a 3 billion US dollar, 280 MW project, it was later described as a 1 GW campus. An unnamed US investment-grade hyperscaler leased the first 200 MW of critical IT load in two buildings for about 15 years and holds a right of first refusal on 800 MW more. Construction is funded partly by 2.15 billion US dollars of senior secured notes issued in March 2026; the company expects initial operations by the end of 2026 and the full 200 MW in 2027.

This record reports under construction as of 2026-10-07. Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)

Location: Harwood, Cass County, North Dakota, US. Town centroid of Harwood from its Wikipedia coordinates (s6), which also places Harwood in Cass County; company sources say only that the campus is near Harwood and give no parcel. Applied Digital; Applied Digital via GlobeNewswire (FinancialContent); Applied Digital; Wikipedia

Use: Ai unspecified, Hpc

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investment3,000,000,000 USDAnnounced · Campus2025-08-18Figure given with the original 280 MW plan.Applied Digital
Power capacity280 MWPlanned · Campus · Unspecified2025-08-18Initial size at announcement; the release said the campus could scale beyond this.Applied Digital
Power capacity200 MWContracted · Phase · It load · Initial two buildings2025-10-22Critical IT load leased to an unnamed hyperscaler for an estimated 15 years, about 5 billion US dollars of contracted revenue.Applied Digital via GlobeNewswire (FinancialContent); Applied Digital
Power capacity1,000 MWPlanned · Campus · Unspecified2025-10-22Described as a 1 GW campus; the tenant holds a right of first refusal on a further 800 MW of critical IT load representing the full expansion.Applied Digital via GlobeNewswire (FinancialContent)
Land areamore than 900 acresReported · Campus2025-08-18Land the company says it has contracted.Applied Digital; Applied Digital via GlobeNewswire (FinancialContent)
Buildings2 countPlanned · Phase · Initial two buildings2025-10-22Applied Digital; Applied Digital via GlobeNewswire (FinancialContent)
Jobs permanentmore than 200 countPlanned · Campus2025-08-18Full-time employees expected at full operation, plus long-term contractors.Applied Digital

Companies and organizations

NameRoleNotesSources
Applied DigitalDeveloperApplied Digital; Applied Digital via GlobeNewswire (FinancialContent)
Cass County Electric CooperativeUtilityNamed as the power provider; in August 2025 the cooperative said it was finalizing an agreement.Applied Digital; Valley News Live
OracleTenantReported by Valley News Live in March 2026 without attribution; Applied Digital describes the tenant only as an unnamed US investment-grade hyperscaler, so this is not confirmed by the companies.Valley News Live

Timeline

DateEventActual or plannedNotesSources
2025-08-18AnnouncedActualApplied Digital
2025-09Construction startedPlannedGroundbreaking target given at announcement; by October 2025 the company described the campus as under construction.Applied Digital; Applied Digital via GlobeNewswire (FinancialContent)
2025-10-22OtherActualLease of 200 MW of critical IT load to an unnamed US investment-grade hyperscaler announced.Applied Digital via GlobeNewswire (FinancialContent)
2026-03-10OtherActualClosing of 2.15 billion US dollars of 6.75 percent senior secured notes due 2031 to fund the 200 MW build.Valley News Live; Applied Digital
2026First operationalPlannedIn October 2026 the company said initial operations here would bring its delivered North Dakota capacity to 300 MW by the end of calendar 2026.Applied Digital via GlobeNewswire (FinancialContent); U.S. Securities and Exchange Commission (Applied Digital filing)
2027Fully operationalPlannedTarget for reaching the full initial 200 MW.Applied Digital via GlobeNewswire (FinancialContent)

Power supply

TypeDescriptionSources
GridPower secured through Cass County Electric Cooperative, with Minnkota Power Cooperative also working toward a final agreement as of August 2025.Applied Digital