Applied Digital Polaris Forge 1

Site records

Applied Digital's AI data center campus in Ellendale, North Dakota, leased entirely to CoreWeave under roughly 15-year leases covering 400 MW of critical IT load. The first 100 MW building came online in two 50 MW phases in October and November 2025, and the 150 MW second building came online in two 75 MW phases by October 2026, for 250 MW operating. A third 150 MW building (ELN-04) is under construction, financed through a bridge loan later refinanced with senior secured notes in June 2026.

This record reports partially operational as of 2026-10-07. Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)

Location: Ellendale, Dickey County, North Dakota, US. Town centroid of Ellendale from its Wikipedia coordinates (s9), which also places the town in Dickey County; the company sources name the town but give no street address or parcel. Applied Digital; Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing); Wikipedia

Use: Ai unspecified, Hpc

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity400 MWContracted · Campus · It load2025-10-27Critical IT load fully leased to CoreWeave at full buildout.Applied Digital; Applied Digital; Applied Digital
Power capacity250 MWOperational · Campus · It load2026-10-01Critical IT load operating across two buildings and 10 data halls after the second 75 MW phase of Building 2.Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)
Power capacity100 MWOperational · Phase · It load · Building 12025-11-24Applied Digital
Power capacity150 MWOperational · Phase · It load · Building 22026-10-01Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)
Power capacity150 MWUnder construction · Phase · It load · Third HPC building (ELN-04)2026-10-07The May 2026 bridge-loan release and the October 2026 results call this the third AI data center at the campus, while the June 2026 notes release calls it the fourth building (ELN-04); the notes were to repay the bridge loan, so both refer to the same building.Applied Digital; Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)
Power capacityup to 1,000 MWPlanned · Campus · Unspecified2025-06-02Long-term design ambition for the campus; the same release says more than 1 GW of power was in various stages of load study.Applied Digital
Buildings3 countPlanned · Campus2025-11-24Number of buildings contracted to CoreWeave at the time of the release.Applied Digital

Companies and organizations

NameRoleNotesSources
Applied DigitalDeveloperApplied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)
CoreWeaveTenantTwo leases for 250 MW of critical IT load were announced in June 2025 with an option on a further 150 MW; by October 2025 the company described the full 400 MW of critical IT load as leased to CoreWeave.Applied Digital; Applied Digital; Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)

Timeline

DateEventActual or plannedNotesSources
2025-06-02OtherActualTwo leases with CoreWeave for 250 MW of critical IT load announced, with an option on 150 MW more; the release already described the second building as under construction.Applied Digital
2025-10-27First operationalActualFirst 50 MW phase of Building 1 reached ready for service.Applied Digital
2025-11-24OtherActualSecond 50 MW phase brought Building 1 to its full 100 MW.Applied Digital
2026-05-04OtherActualClosing of a 300 million US dollar bridge facility to fund construction of the third AI building.Applied Digital
2026-07OtherActualFirst 75 MW phase of Building 2 reached ready for service; company materials give June 30 and July 1, 2026 for this step.U.S. Securities and Exchange Commission (Applied Digital filing); Applied Digital
2026-10-01OtherActualSecond 75 MW phase completed Building 2, bringing the campus to 250 MW operating.Applied Digital; U.S. Securities and Exchange Commission (Applied Digital filing)
2027OtherPlannedTarget year given in June 2025 for the third 150 MW building to be ready for service.Applied Digital

Related projects: applied digital polaris forge 2, applied digital polaris forge 3