Microsoft La Muela datacenter campus (Aragón)
Announced
Spain · 1 project · Last reported
Summary
Planned Microsoft datacenter campus at the Centrovía industrial estate in La Muela, west of Zaragoza, the largest by area and investment of the three campuses in Microsoft's Aragón plan. The site was declared of general interest in late 2023. The regional plan (PIGA Región MSFT), given initial approval in November 2025, assigns it 146 hectares and about EUR 2.18 billion, with 50 MW secured for a first phase and up to 300 MW sought later through a new substation. The plan still lacked final approval in August 2026, and a modified version went out for public comment in July 2026. Forbes reported first operation was expected from 2030.
Source record as of 2026-09-04 · Details and sources
Orden VFL/1410/2026 of 28 September 2026, published in the Boletín Oficial de Aragón on 2 October 2026, modifies the initial approval of the PIGA "Implantación de la Región Microsoft en Aragón" promoted by Microsoft 7724 Spain, SL to include and initially approve the corrected environmental impact study of the urbanisation project of the La Muela campus (phase 5 of the Centrovía estate), and resubmits it to public information with a hearing for the La Muela town council. This dated government record keeps the campus announced; the plan is still at initial approval, and no licence or works are established. evidence
Gobierno de Aragón, Boletín Oficial de Aragón · published 2026-10-02
Location
The interactive map needs JavaScript. Display anchor: 41.60680, -1.08320 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Approximate site reference; the exact facility position is unverified.
Projects (1)
Microsoft La Muela datacenter campus (Aragón)
Announced last observed as of · Project announcement
This record reports announced as of 2026-09-04. elDiario.es; elDiario.es
Location: La Muela, Zaragoza, Aragón, ES. Nominatim point for the Polígono Industrial Centrovía in La Muela, which sources name as the site area (the campus involves an expansion of the estate); the 146-hectare boundary is not published in the sources. Vozpópuli; elDiario.es
Use: Cloud, Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Investment | 2,179,000,000 EUR | Reported · Campus | 2025-11-14 | Per-site figure in the PIGA as reported by elDiario.es; program-level totals are described in the record notes. | elDiario.es |
| Power capacity | 50 MW | Planned · Phase · Unspecified · First phase | 2025-11-14 | elDiario.es says Microsoft has this power secured for the first phase at each campus. | elDiario.es; Forbes España |
| Power capacity | up to 300 MW | Planned · Campus · Unspecified | 2025-11-14 | Second-phase aspiration per campus in the PIGA, as reported by elDiario.es; Forbes gives 250-300 MW per campus over about ten years. | elDiario.es; Forbes España |
| Land area | 146 hectares | Planned · Campus | 2025-11-14 | elDiario.es |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Microsoft | Developer | Vozpópuli; elDiario.es; Forbes España | |
| Gobierno de Aragón | Government | Declared the project of general interest and is processing the PIGA regional plan. | Vozpópuli; elDiario.es; Forbes España |
| Ayuntamiento de La Muela | Government | Agreed to sell Microsoft the land needed to complete the expansion of the Centrovía industrial estate. | elDiario.es |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2023 | Other | Actual | Vozpópuli and EFE report that the Centrovía site in La Muela received general-interest status in the final months of 2023. | Vozpópuli |
| 2025-11-14 | Other | Actual | Initial approval of the PIGA Región MSFT plan covering La Muela, Villamayor de Gállego and Zaragoza, opening a public information period. | elDiario.es; Forbes España |
| 2026-07-30 | Other | Actual | A modification of the PIGA was published in the Boletín Oficial de Aragón for public comment. | elDiario.es |
| 2030 | First operational | Planned | Forbes reported the first phase was expected to operate from 2030. | Forbes España |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Grid supply through a new substation (named Plaza) starting at 132 kV with a later upgrade to 220 kV. | elDiario.es |
Program-level figures differ by scope and date: EUR 6.6 billion across three sites in 2024 (La Cartuja, Centrovía and Villamayor de Gállego), EUR 5.356 billion across the three PIGA campuses and a wider EUR 10 billion plan including land and servers (November 2025), and EUR 2.9 billion across three campuses (August 2026). Only the per-site PIGA figure is recorded as a metric. No government primary source was opened; Boletín Oficial de Aragón entries should be added when available.
Related projects: microsoft aragon villamayor de gallego, microsoft aragon zaragoza puerto venecia
Sources for these details
- Aragón da luz verde a un centro de datos de Microsoft con una inversión de 2.000 millones — Vozpópuli; 2024-07-03
- Microsoft avanza con su red de centros de datos en Zaragoza, donde proyecta una de sus mayores regiones en Europa — elDiario.es; 2025-11-14
- Microsoft obtiene luz verde para su ambicioso proyecto de centros de datos en Aragón — Forbes España; 2025-11-14
- La 'prioridad extranjera' para PP y Vox en Aragón: expropian suelo para un centro de datos de Microsoft a 2 euros el metro — elDiario.es; 2026-08-02 · Archived source
- ZeC presenta 25 alegaciones al plan de Microsoft y exige a la alcaldesa de Zaragoza paralizar un centro de datos — elDiario.es; 2026-09-04
- Companies
- Developer: Microsoft (unknown scope) evidence
- Developer: Microsoft (unknown scope) evidence
- Developer: Microsoft (unknown scope) evidence
- Government: Gobierno de Aragón (unknown scope) evidence
- Government: Gobierno de Aragón (unknown scope) evidence
- Government: Gobierno de Aragón (unknown scope) evidence
- Government: Ayuntamiento de La Muela (unknown scope) evidence
Source and location review
- Status source
- BOA no. 192 of 2 October 2026 (csv BOA20261002014): ORDEN VFL/1410/2026, de 28 de septiembre, modifying Orden FOM/1520/2025 (initial approval of the Plan de Interés General "Implantación de la Región Microsoft en Aragón", Microsoft 7724 Spain, SL) to include and initially approve the environmental impact study of the urbanisation project of the La Muela area evidence row
Gobierno de Aragón, Boletín Oficial de Aragón · published 2026-10-02 · Government record - Locator
- Approximate site reference · Compiled location reference · approximate_site evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 25 days before the data update on 2026-10-27
Location details
- Coordinates
- 41.60680, -1.08320
- Geometry licence
- source-terms-not-recorded
- Use scope
- Approximate site reference
- Scope class
- approximate_site
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- Nominatim point for the Polígono Industrial Centrovía in La Muela, which sources name as the site area (the campus involves an expansion of the estate); the 146-hectare boundary is not published in the sources.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- aeaecec7
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Aragón da luz verde a un centro de datos de Microsoft con una inversión de 2.000 millones Archived copy | Vozpópuli News | Imported: Geometry, Imported: Record, Milestone: Other, Role: Developer, Role: Government | source-terms-not-recorded | Vozpópuli | e73a9f07a6eec0f0bfce6f3b69ec10d57bfb85ce371c390f27d2c3c859d95830Factual source record; not the publisher page | ||
| BOA no. 192 of 2 October 2026 (csv BOA20261002014): ORDEN VFL/1410/2026, de 28 de septiembre, modifying Orden FOM/1520/2025 (initial approval of the Plan de Interés General "Implantación de la Región Microsoft en Aragón", Microsoft 7724 Spain, SL) to include and initially approve the environmental impact study of the urbanisation project of the La Muela area Archived copy | Gobierno de Aragón, Boletín Oficial de Aragón Government record | Project announcement | public-sector-information | Boletín Oficial de Aragón, Gobierno de Aragón | cd823209d75beb3b1ce051248224dfd6c52fab5b57a2007e06dde1fd0c706c40Retained source material; see source provenance | ||
| La 'prioridad extranjera' para PP y Vox en Aragón: expropian suelo para un centro de datos de Microsoft a 2 euros el metro Archived copy | elDiario.es News | Imported: Geometry, Imported: Record, Imported: Status, Role: Government | source-terms-not-recorded | elDiario.es | 3d9bfb19628e149cb95cf317a0df8e546085cf8813cf0bb6833b3412ad1921f0Factual source record; not the publisher page | ||
| Microsoft avanza con su red de centros de datos en Zaragoza, donde proyecta una de sus mayores regiones en Europa Archived copy | elDiario.es News | Imported: Record, Metric: Investment, Metric: Land Area, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Role: Developer, Role: Government | source-terms-not-recorded | elDiario.es | 501a1f66e7ce05f58750a3ecdadafb5faa555140208c27bd7324657de1852354Factual source record; not the publisher page | ||
| Microsoft obtiene luz verde para su ambicioso proyecto de centros de datos en Aragón Archived copy | Forbes España News | Imported: Record, Metric: Power Capacity, Milestone: First Operational, Milestone: Other, Role: Developer, Role: Government | source-terms-not-recorded | Forbes España | 0c2b25a0eff692b960c8edef2b22f3b0ed17fc7c1dfa7f3667c491ec379861ceFactual source record; not the publisher page | ||
| ZeC presenta 25 alegaciones al plan de Microsoft y exige a la alcaldesa de Zaragoza paralizar un centro de datos Archived copy | elDiario.es News | Imported: Record, Imported: Status, Milestone: Other | source-terms-not-recorded | elDiario.es | ab78b320de1bd72b75b43151ed9692d6cba87b79ed32475387e2ad6c975d723fFactual source record; not the publisher page |
Cite this site