Microsoft La Muela datacenter campus (Aragón)

Announced

Spain · 1 project · Last reported

Summary

Planned Microsoft datacenter campus at the Centrovía industrial estate in La Muela, west of Zaragoza, the largest by area and investment of the three campuses in Microsoft's Aragón plan. The site was declared of general interest in late 2023. The regional plan (PIGA Región MSFT), given initial approval in November 2025, assigns it 146 hectares and about EUR 2.18 billion, with 50 MW secured for a first phase and up to 300 MW sought later through a new substation. The plan still lacked final approval in August 2026, and a modified version went out for public comment in July 2026. Forbes reported first operation was expected from 2030.

Source record as of 2026-09-04 · Details and sources

Orden VFL/1410/2026 of 28 September 2026, published in the Boletín Oficial de Aragón on 2 October 2026, modifies the initial approval of the PIGA "Implantación de la Región Microsoft en Aragón" promoted by Microsoft 7724 Spain, SL to include and initially approve the corrected environmental impact study of the urbanisation project of the La Muela campus (phase 5 of the Centrovía estate), and resubmits it to public information with a hearing for the La Muela town council. This dated government record keeps the campus announced; the plan is still at initial approval, and no licence or works are established. evidence

Gobierno de Aragón, Boletín Oficial de Aragón · published 2026-10-02

Location

The interactive map needs JavaScript. Display anchor: 41.60680, -1.08320 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Approximate site reference; the exact facility position is unverified.

Projects (1)

Microsoft La Muela datacenter campus (Aragón)

Announced last observed as of · Project announcement

This record reports announced as of 2026-09-04. elDiario.es; elDiario.es

Location: La Muela, Zaragoza, Aragón, ES. Nominatim point for the Polígono Industrial Centrovía in La Muela, which sources name as the site area (the campus involves an expansion of the estate); the 146-hectare boundary is not published in the sources. Vozpópuli; elDiario.es

Use: Cloud, Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investment2,179,000,000 EURReported · Campus2025-11-14Per-site figure in the PIGA as reported by elDiario.es; program-level totals are described in the record notes.elDiario.es
Power capacity50 MWPlanned · Phase · Unspecified · First phase2025-11-14elDiario.es says Microsoft has this power secured for the first phase at each campus.elDiario.es; Forbes España
Power capacityup to 300 MWPlanned · Campus · Unspecified2025-11-14Second-phase aspiration per campus in the PIGA, as reported by elDiario.es; Forbes gives 250-300 MW per campus over about ten years.elDiario.es; Forbes España
Land area146 hectaresPlanned · Campus2025-11-14elDiario.es

Companies and organizations

NameRoleNotesSources
MicrosoftDeveloperVozpópuli; elDiario.es; Forbes España
Gobierno de AragónGovernmentDeclared the project of general interest and is processing the PIGA regional plan.Vozpópuli; elDiario.es; Forbes España
Ayuntamiento de La MuelaGovernmentAgreed to sell Microsoft the land needed to complete the expansion of the Centrovía industrial estate.elDiario.es

Timeline

DateEventActual or plannedNotesSources
2023OtherActualVozpópuli and EFE report that the Centrovía site in La Muela received general-interest status in the final months of 2023.Vozpópuli
2025-11-14OtherActualInitial approval of the PIGA Región MSFT plan covering La Muela, Villamayor de Gállego and Zaragoza, opening a public information period.elDiario.es; Forbes España
2026-07-30OtherActualA modification of the PIGA was published in the Boletín Oficial de Aragón for public comment.elDiario.es
2030First operationalPlannedForbes reported the first phase was expected to operate from 2030.Forbes España

Power supply

TypeDescriptionSources
GridGrid supply through a new substation (named Plaza) starting at 132 kV with a later upgrade to 220 kV.elDiario.es

Program-level figures differ by scope and date: EUR 6.6 billion across three sites in 2024 (La Cartuja, Centrovía and Villamayor de Gállego), EUR 5.356 billion across the three PIGA campuses and a wider EUR 10 billion plan including land and servers (November 2025), and EUR 2.9 billion across three campuses (August 2026). Only the per-site PIGA figure is recorded as a metric. No government primary source was opened; Boletín Oficial de Aragón entries should be added when available.

Related projects: microsoft aragon villamayor de gallego, microsoft aragon zaragoza puerto venecia

Sources for these details
Companies
  • Developer: Microsoft (unknown scope) evidence
  • Developer: Microsoft (unknown scope) evidence
  • Developer: Microsoft (unknown scope) evidence
  • Government: Gobierno de Aragón (unknown scope) evidence
  • Government: Gobierno de Aragón (unknown scope) evidence
  • Government: Gobierno de Aragón (unknown scope) evidence
  • Government: Ayuntamiento de La Muela (unknown scope) evidence
Source and location review
Status source
BOA no. 192 of 2 October 2026 (csv BOA20261002014): ORDEN VFL/1410/2026, de 28 de septiembre, modifying Orden FOM/1520/2025 (initial approval of the Plan de Interés General "Implantación de la Región Microsoft en Aragón", Microsoft 7724 Spain, SL) to include and initially approve the environmental impact study of the urbanisation project of the La Muela area evidence row
Gobierno de Aragón, Boletín Oficial de Aragón · published 2026-10-02 · Government record
Locator
Approximate site reference · Compiled location reference · approximate_site evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 25 days before the data update on 2026-10-27

Location details
Coordinates
41.60680, -1.08320
Geometry licence
source-terms-not-recorded
Use scope
Approximate site reference
Scope class
approximate_site
Authority
Compiled location reference
Source entity
Project
Method
imported_reference_point
Derivation
imported_reference_point
Precision scope
Nominatim point for the Polígono Industrial Centrovía in La Muela, which sources name as the site area (the campus involves an expansion of the estate); the 146-hectare boundary is not published in the sources.
Horizontal uncertainty
Not reported

The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.

Geometry evidence
aeaecec7

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Microsoft La Muela datacenter campus (Aragón)
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Aragón da luz verde a un centro de datos de Microsoft con una inversión de 2.000 millones
Archived copy
Vozpópuli
News
Imported: Geometry, Imported: Record, Milestone: Other, Role: Developer, Role: Governmentsource-terms-not-recordedVozpópulie73a9f07a6eec0f0bfce6f3b69ec10d57bfb85ce371c390f27d2c3c859d95830
Factual source record; not the publisher page
BOA no. 192 of 2 October 2026 (csv BOA20261002014): ORDEN VFL/1410/2026, de 28 de septiembre, modifying Orden FOM/1520/2025 (initial approval of the Plan de Interés General "Implantación de la Región Microsoft en Aragón", Microsoft 7724 Spain, SL) to include and initially approve the environmental impact study of the urbanisation project of the La Muela area
Archived copy
Gobierno de Aragón, Boletín Oficial de Aragón
Government record
Project announcementpublic-sector-informationBoletín Oficial de Aragón, Gobierno de Aragóncd823209d75beb3b1ce051248224dfd6c52fab5b57a2007e06dde1fd0c706c40
Retained source material; see source provenance
La 'prioridad extranjera' para PP y Vox en Aragón: expropian suelo para un centro de datos de Microsoft a 2 euros el metro
Archived copy
elDiario.es
News
Imported: Geometry, Imported: Record, Imported: Status, Role: Governmentsource-terms-not-recordedelDiario.es3d9bfb19628e149cb95cf317a0df8e546085cf8813cf0bb6833b3412ad1921f0
Factual source record; not the publisher page
Microsoft avanza con su red de centros de datos en Zaragoza, donde proyecta una de sus mayores regiones en Europa
Archived copy
elDiario.es
News
Imported: Record, Metric: Investment, Metric: Land Area, Metric: Power Capacity, Milestone: Other, Power Source: Grid, Role: Developer, Role: Governmentsource-terms-not-recordedelDiario.es501a1f66e7ce05f58750a3ecdadafb5faa555140208c27bd7324657de1852354
Factual source record; not the publisher page
Microsoft obtiene luz verde para su ambicioso proyecto de centros de datos en Aragón
Archived copy
Forbes España
News
Imported: Record, Metric: Power Capacity, Milestone: First Operational, Milestone: Other, Role: Developer, Role: Governmentsource-terms-not-recordedForbes España0c2b25a0eff692b960c8edef2b22f3b0ed17fc7c1dfa7f3667c491ec379861ce
Factual source record; not the publisher page
ZeC presenta 25 alegaciones al plan de Microsoft y exige a la alcaldesa de Zaragoza paralizar un centro de datos
Archived copy
elDiario.es
News
Imported: Record, Imported: Status, Milestone: Othersource-terms-not-recordedelDiario.esab78b320de1bd72b75b43151ed9692d6cba87b79ed32475387e2ad6c975d723f
Factual source record; not the publisher page
Cite this site

Kyars, K. (2026). Microsoft La Muela datacenter campus (Aragón) [site vcc-site-155a753d051b04508b1c]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-155a753d051b04508b1c/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction