Microsoft Zaragoza (Puerto Venecia) datacenter campus

Site records

Planned Microsoft datacenter campus in the city of Zaragoza beside the Puerto Venecia shopping area, one of three campuses in the PIGA Región MSFT regional plan. The November 2025 plan assigns it 57 hectares and about EUR 1.44 billion, with 50 MW secured for a first phase and up to 300 MW sought later via the Torrero-Valdeconsejo substation. The regional government declared it of general interest in September 2025 and began expropriating about 16.5 hectares of private land. Landowners and the ZeC party contested the project in 2026. Microsoft says only land clearing is authorized until the plan receives final approval.

This record reports announced as of 2026-09-04. elDiario.es; elDiario.es

Location: Zaragoza, Aragón, ES. Nominatim point for Puerto Venecia (Torrero-La Paz district); sources place the campus next to Puerto Venecia and Parque Venecia, but the parcel boundary is not published. elDiario.es; elDiario.es

Use: Cloud, Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investment1,443,000,000 EURReported · Campus2025-11-14Per-site figure in the November 2025 PIGA as reported by elDiario.es.elDiario.es
Power capacity50 MWPlanned · Phase · Unspecified · First phase2025-11-14elDiario.es; Forbes España
Power capacityup to 300 MWPlanned · Campus · Unspecified2025-11-14Second-phase aspiration per campus in the PIGA, as reported by elDiario.es; Forbes gives 250-300 MW per campus over about ten years.elDiario.es; Forbes España
Land area57 hectaresPlanned · Campus2025-11-14elDiario.es reported in August 2026 that about 16.5 hectares of private land at the site were being expropriated.elDiario.es

Companies and organizations

NameRoleNotesSources
MicrosoftDeveloperelDiario.es; Forbes España; elDiario.es
Gobierno de AragónGovernmentDeclared the campus of general interest, started expropriation and is processing the PIGA regional plan.elDiario.es; Forbes España; elDiario.es

Timeline

DateEventActual or plannedNotesSources
2025-09OtherActualRegional government declared the campus of general interest and opened expropriation of private land.elDiario.es
2025-11-14OtherActualInitial approval of the PIGA Región MSFT plan covering La Muela, Villamayor de Gállego and Zaragoza, opening a public information period.elDiario.es; Forbes España
2026-07-30OtherActualA modification of the PIGA was published in the Boletín Oficial de Aragón for public comment; the ZeC party filed 25 objections citing trees, flood risk and water and energy use.elDiario.es
2030First operationalPlannedForbes reported the first phase was expected to operate from 2030; Microsoft's plan foresees about four years for the first phase after final approval.Forbes España; elDiario.es

Power supply

TypeDescriptionSources
GridGrid supply through the Torrero-Valdeconsejo substation, starting at 132 kV with a later upgrade to 220 kV.elDiario.es

Landowners facing expropriation say work has begun, which Microsoft disputes, saying only land clearing is permitted before the plan is finally approved. 2026 coverage also mentions a second large data centre planned on rural land at Cartuja Baja in Zaragoza without naming its developer; it is not part of this record. No government primary source was opened; Boletín Oficial de Aragón entries should be added when available.

Related projects: microsoft aragon la muela, microsoft aragon villamayor de gallego