Microsoft La Muela datacenter campus (Aragón)

Site records

Planned Microsoft datacenter campus at the Centrovía industrial estate in La Muela, west of Zaragoza, the largest by area and investment of the three campuses in Microsoft's Aragón plan. The site was declared of general interest in late 2023. The regional plan (PIGA Región MSFT), given initial approval in November 2025, assigns it 146 hectares and about EUR 2.18 billion, with 50 MW secured for a first phase and up to 300 MW sought later through a new substation. The plan still lacked final approval in August 2026, and a modified version went out for public comment in July 2026. Forbes reported first operation was expected from 2030.

This record reports announced as of 2026-09-04. elDiario.es; elDiario.es

Location: La Muela, Zaragoza, Aragón, ES. Nominatim point for the Polígono Industrial Centrovía in La Muela, which sources name as the site area (the campus involves an expansion of the estate); the 146-hectare boundary is not published in the sources. Vozpópuli; elDiario.es

Use: Cloud, Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investment2,179,000,000 EURReported · Campus2025-11-14Per-site figure in the PIGA as reported by elDiario.es; program-level totals are described in the record notes.elDiario.es
Power capacity50 MWPlanned · Phase · Unspecified · First phase2025-11-14elDiario.es says Microsoft has this power secured for the first phase at each campus.elDiario.es; Forbes España
Power capacityup to 300 MWPlanned · Campus · Unspecified2025-11-14Second-phase aspiration per campus in the PIGA, as reported by elDiario.es; Forbes gives 250-300 MW per campus over about ten years.elDiario.es; Forbes España
Land area146 hectaresPlanned · Campus2025-11-14elDiario.es

Companies and organizations

NameRoleNotesSources
MicrosoftDeveloperVozpópuli; elDiario.es; Forbes España
Gobierno de AragónGovernmentDeclared the project of general interest and is processing the PIGA regional plan.Vozpópuli; elDiario.es; Forbes España
Ayuntamiento de La MuelaGovernmentAgreed to sell Microsoft the land needed to complete the expansion of the Centrovía industrial estate.elDiario.es

Timeline

DateEventActual or plannedNotesSources
2023OtherActualVozpópuli and EFE report that the Centrovía site in La Muela received general-interest status in the final months of 2023.Vozpópuli
2025-11-14OtherActualInitial approval of the PIGA Región MSFT plan covering La Muela, Villamayor de Gállego and Zaragoza, opening a public information period.elDiario.es; Forbes España
2026-07-30OtherActualA modification of the PIGA was published in the Boletín Oficial de Aragón for public comment.elDiario.es
2030First operationalPlannedForbes reported the first phase was expected to operate from 2030.Forbes España

Power supply

TypeDescriptionSources
GridGrid supply through a new substation (named Plaza) starting at 132 kV with a later upgrade to 220 kV.elDiario.es

Program-level figures differ by scope and date: EUR 6.6 billion across three sites in 2024 (La Cartuja, Centrovía and Villamayor de Gállego), EUR 5.356 billion across the three PIGA campuses and a wider EUR 10 billion plan including land and servers (November 2025), and EUR 2.9 billion across three campuses (August 2026). Only the per-site PIGA figure is recorded as a metric. No government primary source was opened; Boletín Oficial de Aragón entries should be added when available.

Related projects: microsoft aragon villamayor de gallego, microsoft aragon zaragoza puerto venecia