Crusoe Abilene AI factory campus for Microsoft
Under construction
United States · 1 project · Last reported
Summary
Crusoe's second AI campus in Abilene, Texas, on Lancium-owned land adjacent to its first Abilene campus, announced in March 2026 to support large-scale AI workloads for Microsoft. The 900 MW site has two buildings, each designed for 336 MW of critical IT load, a 900 MW behind-the-meter on-site power plant paired with medium-voltage battery storage, and closed-loop, non-evaporative liquid cooling. Land clearing and site preparation were under way at announcement, Crusoe said in July 2026 that it was building the campus, and the first building is expected to be energized in mid-2027.
Source record as of 2026-07-15 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: 32.45000, -99.75000 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Town or locality reference only; the facility position is not established.
Projects (1)
Crusoe Abilene AI factory campus for Microsoft
Under construction last observed as of · Reported status
Location: Abilene, Texas, US. Crusoe places the campus in Abilene, adjacent to its existing campus, without an address. Coordinates are the Abilene city point from its Wikipedia article; the city spans Taylor and Jones counties, so no county is recorded. Crusoe; Crusoe; Wikipedia
Use: Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 900 MW | Planned · Campus · Unspecified | 2026-07-15 | Crusoe's headline size for the new site; it does not say whether this is IT or facility power. | Crusoe; The Register; Crusoe |
| Power capacity | 336 MW | Planned · Phase · It load · Building 1 | 2026-03-27 | Each of the two buildings is designed to deliver 336 MW of critical IT load; the first is due to be energized in mid-2027. | Crusoe; The Register |
| Power capacity | 336 MW | Planned · Phase · It load · Building 2 | 2026-03-27 | Crusoe; The Register | |
| Power capacity | 900 MW | Planned · Campus · Onsite generation | 2026-03-27 | Behind-the-meter on-site power plant; Crusoe did not disclose the generation technology or fuel. | Crusoe; The Register |
| Buildings | 2 count | Planned · Campus | 2026-03-27 | Crusoe; The Register |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Crusoe | Developer | Crusoe; Crusoe; Crusoe | |
| Microsoft | Tenant | Crusoe says the campus will support large-scale AI workloads for Microsoft; lease terms were not disclosed. | Crusoe; The Register |
| Lancium | Owner | Crusoe describes the land as adjacent Lancium-owned land. | Crusoe |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2026-03-27 | Announced | Actual | Crusoe; The Register | |
| 2026-03 | Construction started | Actual | Land clearing and site preparation were under way when the campus was announced. | Crusoe; The Register |
| 2027 | First operational | Planned | First building expected to be energized in mid-2027. | Crusoe; The Register |
Power supply
| Type | Description | Sources |
|---|---|---|
| Other | A 900 MW behind-the-meter on-site power plant that Crusoe says supports grid resilience; Crusoe has not said what fuel or technology it uses. | Crusoe; The Register |
| Battery storage | Medium-voltage battery energy storage paired with the on-site plant. | Crusoe |
This is a separate build from the eight-building Stargate Abilene campus (openai-stargate-abilene); Crusoe gives about 2.1 GW for its two Abilene campuses combined. The Register reports that Oracle and OpenAI had planned to lease this expansion before negotiations and financing fell through, and that Meta had been expected to take it before Microsoft; these are press reports, not company statements, and are not recorded as parties. In September 2026 Crusoe said it had two campuses under development in Abilene but gave no new status detail for this one.
Related projects: openai stargate abilene
Sources for these details
- Crusoe announces new 900 MW AI factory campus in Abilene, Texas to support Microsoft AI infrastructure — Crusoe; 2026-03-27 · Archived source
- Microsoft takes up residence next to OpenAI, Oracle at Crusoe's 900 MW Texas datacenter expansion — The Register; 2026-03-27 · Archived source
- Crusoe and Lancium announce 1.0 gigawatt AI data center campus in Childress, Texas — Crusoe; 2026-07-15 · Archived source
- Crusoe developing data center campus in Armstrong County, Texas — Crusoe; 2026-09-28
- Abilene, Texas — Wikipedia; publication date not stated
- Companies
Source and location review
- Status source
- Crusoe and Lancium announce 1.0 gigawatt AI data center campus in Childress, Texas evidence row
Crusoe · published 2026-07-15 · Company disclosure - Locator
- Locality reference only · Compiled location reference · locality evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 104 days before the data update on 2026-10-27
Location details
- Coordinates
- 32.45000, -99.75000
- Geometry licence
- source-terms-not-recorded
- Use scope
- Locality reference only
- Scope class
- locality
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- Crusoe places the campus in Abilene, adjacent to its existing campus, without an address. Coordinates are the Abilene city point from its Wikipedia article; the city spans Taylor and Jones counties, so no county is recorded.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 2eb43ea9
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Abilene, Texas Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | 1335f68509546dc007e77b287c8242e9833f9fb1415bc3ed75f335b5379e5904Factual source record; not the publisher page | |
| Crusoe and Lancium announce 1.0 gigawatt AI data center campus in Childress, Texas Archived copy | Crusoe Company disclosure | Imported: Geometry, Imported: Record, Imported: Status, Metric: Power Capacity, Role: Developer, Owner claim | source-terms-not-recorded | Crusoe | 4d1aa2f770404cff50c307a7b07185fe4be73407eca19a77941aec8127709429Factual source record; not the publisher page | ||
| Crusoe announces new 900 MW AI factory campus in Abilene, Texas to support Microsoft AI infrastructure Archived copy | Crusoe Company disclosure | Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Power Capacity, Milestone: Announced, Milestone: Construction Started, Milestone: First Operational, Power Source: Battery Storage, Power Source: Other, Role: Developer, Tenant claim | source-terms-not-recorded | Crusoe | 11a79aaa38ddd15a6c449a5c37e2c9bc641419f26c7bbab3796b8c41f10a0467Factual source record; not the publisher page | ||
| Crusoe developing data center campus in Armstrong County, Texas Archived copy | Crusoe Company disclosure | Imported: Record, Role: Developer | source-terms-not-recorded | Crusoe | e93231e8761bf20586a525de9046cffd3bb8c90beaf61e9e3e5a0cb777210cdbFactual source record; not the publisher page | ||
| Microsoft takes up residence next to OpenAI, Oracle at Crusoe's 900 MW Texas datacenter expansion Archived copy | The Register News | Imported: Record, Metric: Buildings, Metric: Power Capacity, Milestone: Announced, Milestone: Construction Started, Milestone: First Operational, Power Source: Other, Tenant claim | source-terms-not-recorded | The Register | 8cea85a73caee51bb46b84d70aa2c595a1e7c14ecebac42407121526e77691a3Factual source record; not the publisher page |
Cite this site
Kyars, K. (2026). Crusoe Abilene AI factory campus for Microsoft [site vcc-site-9f7647940a58e048e38f]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-9f7647940a58e048e38f/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction